Hamilton County Facilities

CH – B-95 Facilities Accounting Renovation

PM: Mike Murphy
05/25/21 SOSS Submitted to County
06/25/21 Meeting Scheduled for 7/13
07/13/21 Meeting occurred.
07/16/21 SP-1 and SP-2 sent to county with two option.
07/29/21 Meeting scheduled to review options.

08/26/21 Layout settled. Waiting pricing from furniture vendor.

10/13/21 – Site visit to confirm existing conditions with Champlin, Thermaltech and County.

10/19/21 – Final SD set and Estimate uploaded to Archibus.

12/14/21 – Signed SOSS received for DD thru CA.

02/24/24 – Permit applications

03/31/22 – Building permit picked up and delivered to County.

04/28/22 – No update.

05/26/22 – No update.

07/28/22 – Building and IBI inspection scheduled for 8/4.

08/25/22 – Final building and IBI inspections preformed.