05/22/21 – SOSS Submitted to County
06/02/21 – Received signed SOSS
08/09/21 – Meeting held with users to review scope.
08/26/21 – County said to let THP look at floor loading for this work. OK to get them involved now. Previous work created a lot of penetrations in the existing floor and new furniture was heavy. THP to review. New furniture should be less substantial than existing spaces.
10/28/21 – Keep masterplan work in place because this building will remain in the county portfolio for repurposed training facilities.
12/14/21 – No Update.
02/24/22 – Combined Estimate required. need to schedule a meeting to resolve scope overlap.
03/31/22 – SD plan of Combined 2022 estimates created. Meeting is needed to confirm final SD scope.
04/28/22 – We discussed the scope in the Admin Office spaces? Were the Radio Room involved? and we decided that we have not. Should we include Mission Critical involved in this report? Kitchen and Locker room are included.
05/26/22 – Finalizing estimate.
06/30/22 – Combined scope plans provided to TEI for estimate. Finalizing estimate
08/25/22 – SD set sent to HC. Plans need further broken down and resent.
09/29/22 – Site visit scheduled for 10/11.
10/27/22 – Scope refined after field visit. Owner Review Issuance scheduled for 11/11.
12/15/22 – Masterplan drawings need to be changed to reflect current project. waiting until bids are accepted to update according to which alternate is chosen.
01/26/23 – Updated plans will be completed by end of next week.
03/30/23 – Updated plans and estimate uploaded to Archibus.
04/27/23 – No Update.
05/25/23 – No Update.
07/27/23 – No Update.
08/31/23 – No Update.
09/28/23 – No Update.
12/07/23 – No Update.
02/29/24 – No Update.
03/28/24 – No Update.
04/25/24 – No Update.
05/30/24 – No Update.
06/27/24 – No Update.
08/29/24 – No Update.
09/26/24 – No Update.
10/31/24 – No Update.
06/26/25 – No Update but keep on list per HC.
03/26/26 – Leave on list.
07/30/26 – OK to Archive, RT