08/15/22 – Hamilton County requested SOSS.
09/29/22 – THP to publish SOSS on 9/30/22.
10/20/22 – Hamilton County approved the SOSS.
01/26/23 – THP developing design documents.
02/23/23 – THP is continuing to develop design documents. We have partially surveyed the façade for specific damage, and are developing repair/stabilization details. THP will return this week to finish survey.
03/23/23 – THP is developing design documents and plans to have owner review set ready by week of 3/27. We have some remaining survey work from within the courtyard to complete
04/27/23 – THP plans to issue bid review documents May 2nd.
04/27/23 – THP plans to issue bid review documents.
07/13/23 – THP published updated bid review documents to the County.
08/10/23 – THP published bid documents. Bid documents included new XBE program requirements.
08/22/23 – Prebid meeting occurred.
08/23/23 – Addendum No. 1 issued.
08/30/23 – Addendum No 2 issued.
09/07/23 – Bid opening occurred. One bidder over budget. Bid rejected.
09/13/23 – THP issued a bid summary email.