Hamilton County Facilities

TPC – Data Center Decommissioning (9th Floor)

PM: John Nester Butz, Terry Cannon
09/19/22 – Submitted SOSS.
09/23/22 – SOSS approved.
10/26/22 – Drawing created for rebid.
12/15/22 – Champlin has head start on this job, ThermalTech planning on having this ready for review in January 2023.
01/24/23 – Ready to re-kickoff this job and get this out to bid early in 2023.
02/16/23 – Sent Review set to Matt, got ITB, estimate and dates all set. Issue 2/27, prebid 3/8, Bid Opening 4/3.
03/27/23 – Addendum 1 is issued.
03/29/23 – No additional questions received, bid opening Monday, April 3. TTC confirmed two bidders are planning on bidding.
04/25/23 – Bids were opened and Alpha is the apparent low bidder on this job. We have had an online post-bid meeting with Alpha and we followed up with a review of the proposed SOV for the project which was sent back with comments to Alpha. A follow-up phone call with Alpha discussed discrepancies between the budget and bid prices. A final recommendation is being made to he County.
05/21/23 – Pre-Award minutes shared with the team. Contract in approval stages.
06/28/23 – Contracts approved, we are seeting up the Pre-Const Mtg second week of July.
07/26/23 – Pre-Const meeting scheduled for August 18.
08/29/30 – Holding for startup.
09/27/23 – Holding for Startup, should I tell Alpha March 2024 or stick with January 2024.
10/25/23 – Talked to new Alpha PM and will setup meeting to discuss schedule and background check requirements with him. Brandon Winsted.
12/06/23 – Alpha in holding pattern awaiting kickoff of project on our schedule.
01/09/24 – Coordination Meeting #2 held between City and County. PO has been issued by the County to the City for the new fiber line. CAGIS ready to move servers by the end of January. Next meeting to have CLEAR in attendance.
01/30/24 – Coordination Meeting #3 held between City and County. City ready to execute PO to Thayer for fiber run between buildings. TE issued an updated drawing showing the fiber to terminated in CH 2nd Floor in Rack #17. City stated a new Integration Router will be installed in the new County server room in Rack #17 to reduce downtime of the cutover for the Integration router. We need to find a router for the Heroin task force when we demo the 9th floor. 9th Floor demo scheduled for April/May. Next meeting in four weeks.
02/23/24 – Updated Alpha on project progress. Assumed start date May 2024.
03/22/24 – Met with Alpha last week in the room. Pre Const Mtg mid April to be scheduled.
04/24/24 – TTC advised Alpha that our demolition start date will probably be June/July timeframe and that the service elevator will probably be worked on in May, June and July this year. CMSNet is currently getting a quote to move the database server out of the 9th floor over to the CH Server Room.
05/28/24 – Contacted Alpha and pushed back start date to August 2024.
06/26/24 – Admin CH fiber is installed, ttc to get photos today of server room progress. Another City/County meeting was held on Tuesday, ttc sent minutes out for review. July 21 6am is tentative date for Integration router relocation to Admin basement.
07/24/24 – Project walk through scheduled with Alpha for starting to mark existing equipment and demo.
08/20/24 – TTE contact Risk Mgmt and the final server was moved out of the 9th floor room.
08/19/24 – Alpha Construction started in the room. This week they removed ceiling pads and inspected the area. Asbestos contractor coming next week.
08/26/24 – Asbestos contractor began working in the space this week. An exhaust duct was routed across the 9th floor to the nearest window for ventilation. The Ante Room is under remediation now. The main room will be started next week. The floor demo to begin the third week of September.
09/24/24 – Building permit was submitted on 9/18. Fire permit was submitted on 9/18. 2024P08366 but permit is not ready for issuance yet. asbestos remediation has been completed in the ante room and server room, all clear has been issued. Demolition for the raised floor and ceiling is underway. Alpha asked about the status of the E-Waste products in the space and several pieces of equipment are still powered up. County coming on Thursday to remove products.
10/30/24 – Demolition nearly complete in the space. Alpha submitted COR for interior Liebert demo. Fire protection permit is approved and Preferred will be onsite next week to start their work. As soon as the wet
fire system is pulled into room, Alpha will start remaining demo and asbestos remediation.
12/12/24 – Fire protection is complete and the Halon tanks are removed from the building. Asbestos abatement is ongoing at this time and supposed to be done by the end of this week.
12/31/24 – Alpha sent and email outlining the delays in completion due to Testing agency staffing issues and told us completion will not be until early 2025. Testing actually completed their work today and Alpha will be back on Friday to wrap up their work. This job will be ready to punchlist next week Jan 6 – Jan 10. TTC advised all team members.
01/15/25 – Punchlist visit by ThermalTech and Champlin, Jesse and John G were in attendance.
01/28/25 – Punchlist distributed to contractor.
02/26/25 – Project is complete, punchlist has been issued and completed, now Alpha Const is working on back punchlist options. Alpha said they would have closeout documents sent to use by Friday.
03/25/25 – Alpha working on closeout documents for this project including finalizing punchlist, final payapp, and sending closeout documents.
04/21/25 – Punchlist #2 has been submitted to the contractor for completion which includes repairs to two broken windows on the 9th floor and additional electric items.
05/28/25 – Everything completed on second punchlist except windows which are coming in in two weeks.
06/25/25 – Alpha replacing broken windows Thursday to complete punchlist.
07/30/25 – All work is complete including the windows, waiting on owner approval for window repairs.
08/26/25 – All work is complete and approved. TTC will drop off closeout documents on Thursday.
08/28/25 – Closeout documents turned over to County this morning.
09/24/25 – Archived.