Hamilton County Facilities

Crime Lab – Electrical Coordination Study

PM = Rycca Thacker, Mike Barth

04/29/26 – HCFD requests DEG to visit the site to discuss issues with exterior lighting circuitry. DEG to submit SOSS for partial electrical coordination study for affected circuits.
06/23/26 – DEG receives PO and signed SOSS. Electrical Study commences.
07/29/26 – DEG conducts site visit to document all existing breaker model and serial numbers to perform the analysis. Project Analysis being modeled in easy power program.
08/26/26 – Coordination study and report draft sent to HCFD for review.
09/23/26 – trades electricians to adjust settings. Project complete.
10/28/26 – Project complete. Can this be archived.
10/29/26 – TTC archived.