Crime Lab-A

Crime Lab – Electrical Coordination Study

PM = Rycca Thacker, Mike Barth

04/29/26 – HCFD requests DEG to visit the site to discuss issues with exterior lighting circuitry. DEG to submit SOSS for partial electrical coordination study for affected circuits.
06/23/26 – DEG receives PO and signed SOSS. Electrical Study commences.
07/29/26 – DEG conducts site visit to document all existing breaker model and serial numbers to perform the analysis. Project Analysis being modeled in easy power program.
08/26/26 – Coordination study and report draft sent to HCFD for review.
09/23/26 – trades electricians to adjust settings. Project complete.
10/28/26 – Project complete. Can this be archived.
10/29/26 – TTC archived.

Crime Lab – Electrical Coordination Study Read More »

Crime Lab – Leak Investigation (F032)

PM: Rycca Thacker, John Millar
08/28/25 – County asked THP to review water infiltration at the coroner building.
09/05/25 – THP completed an initial site visit to investigate the conditions.
02/25/26 – THP had follow meetings and discussion with HC. THP published an email with summary of potential leak areas and an opinion /of probable costs.
04/03/26 – Based on THP recommendations, County directed THP to complete water tests of the suspect areas.
04/09/26 – THP and HC staff completed water testing at the louvers and screen wall. Testing found multiple leaks in the screen wall.
06/25/26 – Project Archived.

Crime Lab – Leak Investigation (F032) Read More »

Crime Lab – Emergency Power System Upgrades 2024

PM: John Nester, Mike Barth
05/29/24 – TEI submits SOSS for approval.  Project pending PO and Signed SOSS.
06/26/24 – TEI receives approved SOSS and PO.  Documents in Process. Trades will be doing this work, TE to send final dwgs in for review. It will permitted through City of Blue Ash.
07/24/24 – TEI sends drawings to HCFD for review.
08/28/24 – TEI obtains permit from Blue Ash. TEI delivers permit and approved drawings to Keith Otis. Electricians state that material procurement stage – once materials arrive – will get installed.
09/25/24 – HamCo Trades Electricians to notify TEI when they are ready for inspections.
10/30/24 – TEI coordinates breaker types with trades. TEI to arrange inspections when notified by trades.
12/11/24 – Inspections pending call from trades re completed installation.
01/29/25 – Inspections pending call from trades re completed installation.
02/26/25 – Trades calls TEI and are ready for inspections. TEI to schedule with trades and Blue Ash.
09/24/25 – DEG and trades meet with blue ash and has approved inspection. Blue ash did not have records for final inspections for re-circuiting work. that inspection is scheduled for 10/01
10/29/25 – Revised documents in plan review stage.
12/10/25 – Permit applied for – pending approval for final inspection.
01/28/26 – DEG follow up with the City of Blue Ash.
02/25/26 – DEG and trades gets final inspections. All inspections and work passed with City of Blue Ash. Project complete.
02/26/26 – Give County as-built drawings and archive the project.

Crime Lab – Emergency Power System Upgrades 2024 Read More »

Crime Lab – Emergency Power Upgrades

PM: John Nester, Mike Barth
03/29/23 – TEI Submits SOSS.  Project pending approval of SOSS and PO.
04/27/23 – TEI receives PO and Signed SOSS.   TEI finalizing drawings for HCFD review and then will get permits for installation by trades.
05/23/23 – TEI sends review set to HCFD.  Will apply for IBI permit upon receipt/implementation of owner’s review comments.
06/28/23 – TEI meets with John Nester, Andrea Hatton, In Zelner and the HC Electricians to review.  Minor changes were made and the drawings were submitted to Blue Ash for plan review and permit.  Plan review passed and permit is ready for pick up at Blue Ash with a balance of $50 +change.  TEI to pick up permit for HC and work can commence.
7/26/23 – TEI picks up permit and delivers to trades.   Trades is working on the modifications to the branch circuits.
08/24/23 – Trades to notify TEI when work is completed and TEI will arrange for inspections.
09/26/23 – County electricians reach out to TEI for review of as-built documents.  Tentative meeting the week of 10/02.
10/26/23 – TEI and county electricians meet to review as-built documents.  TEI incorporates the as-builts onto the CAD files.   TEI drawings will be sent to HCFD upon completion of QC review.
12/06/23 – HamCo electricians indicate that there are a few more changes that the facility is wanting to make.   Electricians to get modifications to TEI to incorporate in the AS-builts.
01/30/24 -The Sally Port Doors were moved to EM power.  Electricians Told TEI circuitry information to include on as-builts.
02/28/24 – TEI updating permit drawings and will submit to Blue Ash for engineering review and final final inspections.
07/24/24 – REFERENCE OTHER STRING FOR UPDATES.

Crime Lab – Emergency Power Upgrades Read More »

Crime Lab – Emergency Power Study

PM: John Nester, Mike Barth
12/15/22 – ThermalTech submitted SOSS and it’s approved. TEI to schedule fieldwork next week.
01/06/23 – TEI met Ian on site for kickoff meeting.  MCB, Alex, TTC onsite to review.
01/25/23 – Bert said to concentrate on immediate needs first.
02/23/23 – TEI submits immediate needs draft report to HCFD.
03/29/23 – TEI to develop schedule for Phase II of report.  TEI submits SOSS for implementation of Phase I study results.
04/27/23 – See Emergency Power upgrades for Phase 1 updates.   TEI and HCFD to develop schedule for phase 2 study.
10/26/23 – TEI and HCFD develop schedule (preliminary with options focusing on emergency heat in winter) to be sent to Bert on 10/27/23, and final draft sent to Bert on 11/10/23

Crime Lab – Emergency Power Study Read More »

Crime Lab – PM Schedules

06/25/21 – ThermalTech has been working on project over the last few weeks. New equipment was added to the worksheet, TTC to review final list.
07/29/21 – Susan contacted me about completion and I suggested that we could get these done by August 13. She reviewed our test work in DEV and had some questions. Ryan and Nathan will help me complete this work.
08/12/21 – Discussed progress with Susan and committed to a 8/31 completion for 9/1 PM’s. TE has updated Coroner’s Equipment list to check one more time before completion. We are verifying no duplicates exist.
08/25/21 – TTC sent in final list for equipment creation with 3 or 4 questions. Talked to Susan, Steve and Bert about process to finish. I received codes and values back from Facilities to use on our equipment creation list.
10/01/21 – Final equipment list sent to County for upload to Archibus.
10/08/21 – Needed to add asset column for equipment list and warranty item needs to be added.
10/19/21 – Revised worksheet and equipment list sent back to County. I still have to create warranty information for equipment when we enter the PM’s.
12/01/21 – Crime Lab PM’s entered minus a couple of extraneous electrical PM that TTC is checking the needs on.
12/13/21 –  Electrical PM not needed for exit signs, security gate, or power conditioner.  Steve checked in on warranty items and TTC reported that TTE can enter these manually, I just need a review on how to enter the warranty items.  We are meeting this week on how to do this work.
01/22/22 – All equipment and warranties are entered and up to date.
05/25/22 – Ready to Archive.

Crime Lab – PM Schedules Read More »