10/29/20 – Site visit to confirm existing conditions. Meeting scheduled for 10/29 with Kevin Maue for preliminary review. Meeting scheduled for 11/5 with Towards Independence.
11/05/20 – Meeting with Towards independence for review
12/11/20 – Submitting SD drawings and estimate to Kevin Maue for review.
01/20/21 – Email from Kevin Maue indicating decision by DDS on direction towards end of February.
02/25/21 – No Update
03/25/21 – No Update
04/29/21 – No Update
05/12/21 – Sent broken down cost estimate ( kitchen renovations for each building) to Kevin Maue
06/25/21 – No Update.
07/27/21 – Champlin spoke to Kevin Maue. Kevin expects approval to proceed on all three homes on 7/28.
08/12/21 – SOSS sent to County.
08/18/21 – Kevin Maue sent Champlin questions related to SOSS
10/28/21 – No Update.
12/14/21 – No Update.
01/26/22 – No Update.
02/24/22 – No Update.
03/31/22 – No Update.
04/28/22 – No Update.
06/30/22 – SOSS approved for Geier renovation DD-CA. Kickoff meeting held to confirm scope.
07/28/22 – Kickoff meeting occurred. Program and scope changes were discussed. New plan in progress.
08/25/22 – Revised plan sent to Kevin Maue for review.