10/21/20 – Authorized to proceed with design and bid phase.
12/10/20 – two options sent to county and Public Health for review.
01/06/21 – Review meeting with Users – Finalized scope
01/22/21 – Received TTE sd documents
01/26/21 – Uploaded SD Drawing and Estimate to Archibus.
02/18/21 – Received comments from owner
01/25/21 – Champlin working on SOSS to take project through completion.
03/11/21 – SOSS approved.
03/25/21 – CD’s being developed. Review meeting with users to be scheduled in the near future.
04/06/21 – User Review Meeting. Finalized scope.
04/20/21 – Final CD documents and budget given to County.
04/28/21 – County approves final plans. Champlin to get ITB number from Purchasing.
05/11/21 – Project Posted by Purchasing
05/21/21 – Prebid meeting held at 250 WHT
05/24/21 – Addendum 01 posted.
06/03/21 – One bid received. Budget exceeded and bid had to be rejected.
06/14/21 – Rejection letter sent to John Nester after bid review and discussions with other pre-bid attendees.
06/22/21 – Email from John Nester suggesting to combine this project with Public Health Lobby for new bid.
10/28/21 – Ready to Archive.