Hamilton County Facilities

230 – WHT & TPC Critical Façade Repairs [TPC Work Only] (F003)

PM: John Nester, Fateme Shahiyan

04/26/24 – THP provided SOSS Hamilton County.
05/09/24 – County approved SOSS.
05/24/24 – THP provided review documents.
05/28/24 – County provided comments to review documents.
05/31/24 – THP provided Economic inclusion work sheet.
06/04/24 – Economic inclusion package returned to THP.
06/07/24 – THP issued bid documents.
06/20/24 – Prebid meeting occurred.
06/21/24 – Addendum no. 1 issued.
06/26/24 – Bid opening scheduled for July 23, 2024.
07/23/24 – The County received one bid from BCR. Base Bid was 8% over the project opinion of probable cost.
07/24/24 – Department of Economic Inclusion noted the bid was responsive.
07/25/24 – THP and the County to review the bid.
08/15/24 – THP published bid summary letter, recommending BCR.
09/26/24 – Earlier, County sent contract to BCR for execution.
10/04/24 – Contract executed and published.
10/15/24 – Preconstruction meeting occurred.
10/21/24 – County published rooftop safety tie inspection report.
10/25/24 – BCR published submittals for review by THP.
10/29/24 – THP returned submittals to BCR.
10/25/24 – BCR published submittals for review by THP.
10/29/24 – THP returned submittals to BCR.
11/08/24 – BCR published the SOV for review by THP.
11/19/24 – BCR published their schedule for the project
12/04/24 – BCR sent the Pay App No.1 to THP
12/10/24 – BCR Resubmit the Change order No.1
12/10/24 – BCR sent revised Pay App No.1 to THP and THP approved it.
12/10/24 – BCR completed about 30% of the work including sounding and opening up the lintel areas on the fifth floor and providing temporary flashing over the top of the ledge angle.
01/30/25 – Project status – BCR completing sounding, concrete and masonry repairs on West Elevation of Todd Portune Center. Remaining work is corner of south elevation of the TPC. Due to low temperatures crews moved to the 230 WHT building to complete knock down survey work. Crews will return after work at 230 WHT is complete.
02/24/25 – Project is still on hold and crew are still working on 230 WHT.
03/17/25 – BCR Completed all repairs at TPC. THP did the final site visit and did not observe any problem with repairs.
03/25/25 – THP send the pay app No.4 from BCR, to HC for the final review.
04/23/25 – Project is completed and BCR needs to provide closeout documents.
05/27/25- BCR is working on the closeout documents, and they are planning to provide all documents by end of the week.
06/25/25 – HC requested Change Order #3 (CO#3) for the emergency concrete repair on the north elevation of the Portune Center. BCR has provided CO#3 to HC, and HC is currently working to get it approved. BCR is planning to send the supporting documentation, including the cost breakdown with any applicable markups, to THP and HC by the end of this week.
07/01/25 – Change order #3 approved.
07/14/25 – BCR started work.
07/24/25 – THP visited the site and reviewed the work. Field report published.
07/25/25 – BCR finished knock down work.
08/26/25- BCR provided the last pay app for the emergency repair to THP for review. BCR planning on complete the closeout documents and send it to the county by end of the next week.
09/15/25- BCR dropped off the closeout documents to HC/Matt Butz. The electronic documents, notarized warranties were missing. BCR planning to provide all documents by end of this week.
12/11/25 – All project closeout sent to County and final pay application approved.
02/26/26 – Ready to archive.