Hamilton County Facilities

2020 – Sewer Deduct Meter

PM: Tony Matre, Terry Cannon
05/28/24 – Cooling tower makeup water reviewed and approved by GCWW and should be on bill next billing cycle.
06/27/24 – Irrigation sewer deduct ready to review by County. It’s ready to send to GCWW.
07/24/24 – Second deduct meter sent to County for review. TTC followed up by email.
08/28/24 – Received Tony signatures on final paperwork, ready for submission to GCWW.
09/24/24 – Second application has been given to GCWW and MSD, they confirm they have it but it has not been reviewed or processed yet.
10/30/24 – Additional data requested and sent last week to MSD.
12/12/24 – MSD and GCWW have all the data they need, we are waiting on their approved and meter review. The first meter has been on the bills since June, and we are getting a deduct for it. Meter number S03787, so far, they have saved a little over $1,000 in sewer charges in the first few months with the meter online.
01/02/25 – We have the meter and the transmitter has been located. We are moving towards installation in the near future.
01/27/25 – HC has installed the meter and transmitter. ThermalTech is coordinating the final inspection with MSD.
02/26/25 – Meter has been installed and approved. We will check water bills to see when it shows up on the GCWW bill.
03/25/25 – Sewer deduct meter not on water bill yet.
04/23/25 – March water bill has both sewer deduct meters logged on the bill but the irrigation meter has no usage usage yet. This project is ready to archive.
05/28/25 – Archived.

Scroll to Top