PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
05/16/23 – Hamilton County approved the SOSS.
08/31/23 – THP plans to complete work from October through November.
09/28/23 – Rappelling of courtyard façade scheduled for October 3rd.
10/03/23 – Rappelling canceled due to additional rappelling needed at A&D building. THP to reschedule.
02/29/24 – Rappelling scheduled for March 20th and March 21st (weather pending).
03/20/24 – Rappelling completed in the courtyard, but cancelled for the exterior of the building due to high winds.
03/28/24 – THP to reschedule rappelling for mid April.
04/25/24 – THP to reschedule final rappelling in mid May.
05/30/24 – THP plans to schedule rappel end of June.
06/24/24 – Email status of report and repairs to address both City issues.
06/27/24 – Budget sent to County for City repairs.
9/26/24 – THP to reach out to the City and determine placing repair package on hold for larger project.
12/10/24 – THP closing out the project.