PM: John Nester, Paul Bellman
04/06/23 – Hamilton County requested SOSS.
04/06/23 – THP, Kleingers, and HC – Site Visit – Review Scope
04/25/23 – Received Kleingers proposal.
05/09/23 – Received Terracon’s proposal.
05/23/23 – THP submitted SOSS to County for Review.
07/12/23 – Hamilton County approved S0SS.
08/21/23 – Terracon on site to mark boring locations.
08/23/23 – OUPs to mark utilities prior to boring.
08/24/23 – Terracon on site for drilling of test bore locations.
09/12/23 – Hamilton County communicated to THP the flipping of Base Bid and Alternate work.
09/18/23 – THP received parking options from Kleingers. Need to review with Hamilton County.
09/26/23 – THP scheduled on site meeting with Kleingers and Hamilton County. Meeting cancelled – Reschedule Teams Mtg.
10/09/23 – THP and County had meeting to review budget and scope of work. Scope of work adjusted to available funds.
10/10/23 – County Issued AIA forms for bid documents.
10/20/23 – Kleingers sent THP review bid drawings and technical specifications.
10/20/23 – THP issued review bid documents – project manual, drawings, and XBE opinion of probable costs.
10/26/23 – Issue of bid documents anticipated for October 31, 2023.
10/30/23- Documents advertised to bid.
11/08/23 – Prebid meeting occurred.
11/09/23 – Addendum No. 1 issued.
12/07/23 – Bid opening scheduled for 12/13/23.
12/13/23 – Bid opening. (3) bids received and under review.
02/23/24 – Hamilton County sent THP Contract Document A101 for review.
02/29/24 – KT Holden low responsive bid. Hamilton County sent AIA contract to KT Holden for review and execution.
03/25/24 – KT Holden returned signed contract to Hamilton County.
03/22/24 – Approved Contract issued to KT Holden by Hamilton County.
05/14/24 – Preconstruction meeting held on site.
05/16/24 – Hamilton County issued notice to proceed to KT Holden.
05/17/24 – Preconstruction meeting minutes issued.
05/20/24 – KT Holden submitted Schedule of Values and submittals.
05/22/24 – KT Holden submitted for permit.
05/28/24 – Kleingers returned submittals. THP to review and return.
05/21/24 – KT Holden picked up approved permit.
06/25/24 – THP returned submittals to KT Holden. Revised submittals returned to THP and sent to Kleingers.
06/25/24 – KT Holden indicated work is scheduled for August.
07/18/24 – THP emailed KT Holden for schedule update.
07/24/24 – KT Holden Scheduled for mobilization on 8/05/24.
08/23/24 – Kleingers conducted a site visit. Utilities and sawcuts were marked.
08/28/24 – KT Holden on site and started construction.
09/03/24 – KT Holden working on asphalt removal and subgrade work.
09/11/24 – KT Holden asphalt work begins.
09/12/24 – KT Holden concrete work begins.
09/25/24 – Hamilton County, THP, and Kleinger met for final site walk through. THP issued Field Report and Punch list.
09/25/24 – KT Holden submitted Pay App #1 and #2 for review.
10/07/24 – THP returned Pay App #1 and #2 to Hamilton County.
10/31/24 – THP will send Closeout requirements to KT Holden.
11/27/24 – Building Inspection passed and Inspector will close permit in system.
12/11/24 – THP Reviewing Closeout documents and submit pencil copy to County for review prior to printing.
01/24/25 – KT Holden sent Closeout documents to Hamilton County – Confirmation received. Final Pay Application needs to be submitted.
02/04/25 – THP sent Hamilton County Final Pay Application #4.
02/27/25 – THP to archive project.