Hamilton County Facilities

Hillcrest Birch Cottage Removal Assessment (F078)

PM: Bert Watts, Paul Bellman
– Hamilton County requested SOSS.
04/26/23 – Pinnacle Enviromental to provide proposal.
05/01/23 – THP submitted SOSS to County for review.
05/10/23 – County approved SOSS.
05/22/23 – THP sent Pinnacle Contract for signature.
07/07/23 – THP received signed Contract from Pinnacle.
07/18/23 – THP forwarded Pinnacle contacts for background checks.
08/21/23 – Pinnacle Environmental on site for NESHAP Hazardous Material Inspection.
09/27/23 – THP Requested proposals from ThermalTech and Pinnacle. Provide SOSS to Hamilton County.
10/19/23 – THP received Pinnacle Pre-Demolition NESHAP report.
10/20/23 – THP published Pinnacle report to the County.
12/07/23 – Chris Belcher with Pinnacle coordinate contractor effort to abate the cottage the first week of December. Pinnacle plans to update their NESHAP report once the work is complete.
01/18/24 – THP reached out to Chris Belcher with Pinnacle for final report.
01/31/24 – THP reached out again to Chris Belcher with Pinnacle for Ffnal report.