PM: Matt Butz, Paul Bellman
04/01/25 – County requested SOSS for Fall Protection upgrade to the existing roof.
04/24/25 – THP to publish SOSS for review.
05/21/25 – SOSS approved.
06/25/25 – THP requesting roofing plans to start layout.
07/30/25 – THP working on DD drawings and plan to send draft to HC late next week.
08/27/25 – THP finalizing DD drawings and plan to send to HC at the end of the week.
09/24/25 – THP working towards CD drawings. Need to schedule a review meeting with HC.
10/15/25 – Documents issued for bid on 10/15/25.
10/29/25 – Pre-bid meeting held 10/27/25.
11/19/25 – THP issued summary letter to HC recommending NR Lee Restoration.
12/11/25 – HC finalizing paperwork for Contract approval.
01/14/26 – HC issued fully approved Contract to HR Lee Restoration.
01/27/26 – Preconstruction Meeting held virtual.
01/28/26 – THP issued Preconstruction Meeting Minutes.
02/19/26 – Preconstruction Meeting held On-site.
02/20/26 – THP issued Preconstruction Meeting Minutes.
03/25/26 – HR Lee is scheduled to deliver telehandler forklift 3/26 or 3/27 and material on 3/31. Work scheduled to begin shortly after.
04/08/26 – THP and HC reviewed on site substantial completion by HR Lee.
04/20/26 – HR Lee submitted Change Order for requested additional railing at small roof. THP to review with HC.
05/26/26 – HC issued signed and approved CO for additional railing. HR Lee placed order and updated schedule requested. Closeout documents in progress.
06/25/26 – THP is scheduling a final walk-thru with all parties. Closeout documents in process.
07/14/26 – On site final walk.
08/21/26 – THP sent CO #2 for requested safety line and final punch items to HR Lee for signature. Signed CO#2 returned to HC.
09/22/26 – On site review of final punch list items. HR Lee to schedule remaining work by next week.
10/08/26 – HR Lee completed final punch list items and THP and HC reviewed and approved.
10/15/26 – HR Lee submitted final closeout docs.
10/29/26 – HR Lee submitted paint touch up procedures from manufacturer for warranty work and would like to schedule paint touch up of bases.