Hamilton County Facilities

SPHQ – Parking Lot Repave (F025)

PM: John Nester, Paul Bellman

04/01/25 – County requested SOSS to repaving of the Patrol HQ Parking Lot.
04/02/25 – THP completed a preliminary walk of the site.
04/18/25 – THP coordinated consultant proposals from Kleingers and Terracon.
04/24/25 – THP to publish SOSS for review.
05/07/25 – SOSS approved.
05/19/25 – Design kick off meeting complete.
05/29/25 – Civil survey and underground detective work complete.
06/25/25 – Terracon scheduled for underground exploration. THP coordinating with HC.
07/16/25 – Terracon completed borings and sent Draft report.
08/15/25 – Terracon sent final boring report.
08/28/25 – Meeting scheduled with THP, Kleingers, and Terracon to review boring report to finalize plans. Told Rycca THP can have this out late September.
10/15/25 – Documents issued for bid on 10/15/25.
10/29/25 – Pre-bid meeting held 10/27/25.
12/11/25 – Project on hold till further notice.