Hamilton County Facilities

Hillcrest – Birch Cottage Removal (F095)

PM: Bert Watts, Paul Bellman
09/28/23 – Hamilton County requested SOSS.
10/30/23 – THP provided SOSS for review.
11/20/23 – County approved SOSS.
12/07/23 – Chris Belcher with Pinnacle coordinate contractor effort to abate the cottage the first week of December. Pinnacle plans to update their NESHAP report once the work is complete.
01/22/23 – THP issued 90% Drawing Owner Review set to Hamilton County.
02/16/24 – THP issued Bid Documents to Hamilton County.
02/20/24 – Hamilton County Purchasing advertised documents to bid.
03/04/24 – Pre-bid meeting held.
03/19/24 – Addendum 1 issued to Purchasing.
03/28/24 – Bid opening scheduled for April 10, 2024.
04/18/24 – THP scheduled Bid review with O’Rourke for 04/25/24.
05/16/24 – Hamilton County requested documents from O’Rourke.
05/30/24 – THP to follow up with requested documents (Schedule of Values, Schedule, Safety plan, general submittals) and schedule pre-construction meeting.
06/05/24 – THP emailed O’Rourke regarding submittals and Pre-construction Meeting.
06/25/24 – THP sent follow-up email to O’Rourke.
06/26/24 – Hamilton County received Asbestos Inspection – Notice of Compliance. O’Rourke to start sending submittals on plumbing material and valves in conjunction with other things.
07/16/24 – Pre-Construction meeting held.
07/17/24 – Pre-Construction meeting notes distributed to all parties. Mobilization scheduled for 7/29/24 (tentative).
07/29/24 – Mobilization and utility work started.
08/16/24 – Demolition complete.
08/23/24 – Final grading complete.
08/28/24 – Seeding and strawing postponed – hold retainage. THP to review pay-app.
09/12/24 – Hamilton County and THP – Final Site walk through.
09/19/24 – THP issued Field Report.
09/25/24 – THP issued closeout list to O’Rourke.
10/09/24 – O’Rourke issued Closeout Documents to THP.
11/27/24 – THP sent pencil copy of Closeout Documents to Hamilton County for approval.
12/10/24 – THP sent final Punch List to be signed and notification for payroll documentation.
12/11/24 – O’Rourke is sending Closeout Documents to Hamilton County.
12/13/25 – Closeout Documents sent to Hamilton County.
01/03/25 – Finalizing Final Pay Application for retainage.
02/26/25 – No updates on Certified Payroll from O’Rourke/Park’s Electric.

Scroll to Top