Hamilton County Facilities

CH – Law Library Text Room Renovation

PM – Jesse Estes, Sam Hofmann, Terry Cannon
12/07/23 – Signed SOSS received. Kickoff meeting requested.
01/22/24 – Load calculations are complete, fieldwork is started and mostly complete. Initial findings for AHU and HVAC needs sent to project team. In subsequent discussions it was decide to upgrade the unit for what we need in this space and do not try to “make” existing unit work if its undersized. TTE will design with that in mind.
01/31/24 – Review drawings to be ready in two weeks. TE to finish MEP review for that issuance.
02/29/24 – Final review meeting ready to be scheduled.
03/28/24 – Review meeting to be scheduled for first week of April.
04/25/24 – Review meeting held. Notes from Library received and changes have been made. They need to approve budget.
06/27/24 – Budget is still being worked out. Mothers room to be listed as an alternate. CDs in progress. Pull Mother’s Room out as an alternate. Laura got more money but not all of it. RR Alternate #1, Mother’s Room Alternate #2.
07/25/24 – No Update.
08/29/24 – Voting on new budget today and it should go forward soon.
09/26/24 – Budget was approved. Project to continue in October.
10/31/24 – Project goes out to bid today.
12/12/24 – Bid opens today.
01/30/25 – Alpha was awarded the bid. Contract still in progress. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract in progress.
03/27/25 – Kickoff scheduled for 4/2. Submittals incoming.
04/24/25 – Submittals in progress.
05/29/25 – Pre-mobilization meeting held. Alpha to provide schedule.
06/26/25 – Demo in progress. Freight elevator is down and has stopped work. RTU submittals were returned and we are working on an electrical requirements on the submittal with the vendors now. We have had several meetings trying to lock this down. Lead times range from 6 to 10 weeks.
07/31/25 – Demo is complete. Abatement of flooring to begin this week. Alpha to submit PCO related to plaster repair. AHU submittals have been received and approved with a new manufacturer. It took a long time to get there and there may be a credit to the project when all is said and done (Carrier/CaptivAire to York).
08/28/25 – Abatement will begin 9/2. Work paused during abatement delay. County is requesting more funds for plaster repair CO. Alpha was released to work up to cost of deduct from flooring removal.
09/25/25 – Framing has begun. Bathrooms to be turned over by end of October.
10/30/25 – Bathrooms to be turned over before 11/4. Asbestos concern to be investigated by the county. Work continues.
12/11/25 – Abatement of above ceiling pipe is complete. Alpha to remobilize and continue work.
01/28/26 – Bathroom back punch complete. Several items outstanding. Mid february completion.
02/26/26 – Library punch complete. Punch work outstanding.
03/26/26 – Back punch complete and work verified. Waiting on closeouts.
04/30/26 – Minor additional backpunch items sent to Alpha. Waiting on closeouts.
05/28/26 – No update.
06/25/26 – Closeouts outstanding. Shelf collapsed and new pins are being installed.
07/30/26 – No Update.
08/28/26 – Trades to fix all shelves. Alpha to come fix damaged shelves and adjust doors.
09/24/26 – Alpha to fix damaged shelves and conceal fasteners. Dehumidifier running to remedy door issues.
10/29/26 – Alpha to fix shelves and plaster in conference room.