JC – Building Envelope Assessment (F109)

01/22/18 – Hamilton County requested an SOSS
01/25/18 – THP provided SOSS as requested by Hamilton County.
02/15/18 – THP approved SOSS.
04/26/18 – THP scheduled field work to begin the first week of May including rappelling. Work is weather dependent.
05/02/18 – THP completed site rappelling surveys.
05/11/18 – THP completed site ground survey.
05/31/18 – THP working on reports.
06/28/18 – THP working on reports. THP verbally noted the façade did not have any safety issues that would impact a City of Cincinnati building façade inspection report.
01/31/19 – THP working on report. County draft report anticipated February 15 and final report completed February 28.
05/29/19 – THP completed internal City Draft of report and Façade section. Roofing assessment to be complete the first week of June.
06/05/19 – THP completed roof assessment.
06/06/19 – THP completed roof assessment.
06/27/19 – THP issued City Facade Application report to County for review.
02/27/20 – THP published the report to the County.
07/30/20 – Discussed at Partner meeting. Leave open for now.