PM: Matt Butz, Terry Cannon
08/27/20 – BOCC agenda has these items on the agenda today. Rebid 9/3, Prebid 9/10, and Opened on 9/24.
09/24/20 – Five bids came in for this job. We are setting up the post-bid interview with the apparent low bidder. The bids did come in under budget and we are hopeful we can award the project.
09/28/20 – Post bid reviews are complete. The meetings went well and additional follow-up questions were answered and researched. Recommendation sent to County by partners.
10/19/20 – City in receipt of permit drawings and examination fees for initial submit from GBBN and ThermalTech.
10/23/20 – Permit accepted by the City and uploaded to their online upload portal. This does not mean the permit is approved, it has just been successfully uploaded for review.
12/10/20 – Triton started submitted paperwork on this job and the safety plan was approved today. The project is progressing forward with early-stage work by the contractor, design team, and owner.
01/05/21 – Team working on permitting & submittals.
01/20/21 – Pre-Const Mtg held at site with Sheriff, Facilities, and Triton. GBBN distributed meeting notes afterward on 1/22.
01/21/21 – GBBN sends a gig letter from City on permit approval.
01/22/21 – ThermalTech and GBBN work on additional permitting requests by the City.
01/25/21 – City says submission is acceptable but we have to take out a third permit for the Courthouse work. TTE tells GBBN that an HVAC permit is not required for that work.
02/05/21 – Plans reviews say approved and “en route”.
02/24/21 – Project submittals underway. GBBN working on permitting approvals. No devices can be supported by the new security ceilings. Jails suggested that we change the shower doors in lieu of a new shower curtain instead of shower door. Filling out a change order for Phase 4 on this job, could save $20k. IBI will be submitted after the building permits are ready.
02/26/21 – GBBN and TEI working with Josh at Triton on security ceiling submittals. We are coordinated access panel locations and attachment methods for in-ceiling devices.
03/01/21 – Permits are approved and ready for pickup on this project. Your permit applications have been APPROVED and are ready for issuance. The permit numbers are 2020P09115, 2020P09116, 2021P01219.
03/04/21 – IBI to require that their Plan review/permitting shall follow the lead from the building department. TEI to submit for (3) plan reviews to get (3) permits associated with the building permits.
03/04/21 – TEI reviewing Camera submittals from Glenwood. Sent the following in email to Glenwood and cc’ed Triton and GBBN. As a follow up to the voice mail that I left for you at your office the other day, I am trying to review/approve the submittals for the security cameras on the Justice Center Capacity and Recovery Project. On the Bill of Materials, the Camera Model Number indicated is a Vicon V804D-W312MIR, however, the cut sheet included is for a V802D-W312MIR Camera. There are resolution differences between these two cameras, so I was wanting to confirm which Camera that you are actually intending to provide.
03/25/21 – Submittals and permitting were worked on this week. TTC has controls submittals to review, talked to JCI yesterday about status. GBBN, Jails, Triton working on keying issues, Const Mtgs to hopefully start early April. GBBN setting up coordination meeting with Sheriff, Facilities, Triton and GBBN to discuss door hardware items.
04/29/21 – Pre Const and Const Mtg #1 held. Equipment has long lead times, limited demo and mobilization has begun. Triton coordinating with CH and JC on Jax area work and beginning const process. Triton to issue Const Mtg from yesterday. A schedule has been issued. All MEP submittals have been reviewed and return. Most GC submittals have been reviewed and returned. Spencer and Josh working on JAILS submittals. Design team to update completion date with Triton for this job as original completion date was July 2021.
05/26/21 – Additional construction meetings were held and demo work is underway in the JAX area. Payapp #1 pencil copy was submitted by Triton and change order work included VAV Access Panels and table top painting.
05/27/21 – Review project handoff with Spencer including change order work for tabletops and HVAC access panels.
06/25/21 – Bi-Weekly const mtgs are being held. Demo is the South building is underway. JAX area is under construction. Medical records move is forthcoming. The schedule not finalized yet due to door delivery unknowns. Lighting installation questions came in this week and Barth instructed Glenwood to install them per the drawings as lay-in fixutres.
07/28/21 – Weekly construction meetings continue. We are having a hard time getting a project schedule from Triton on this job. Triton to provide one very soon. Demo continues but we are getting to the point where new work needs to begin to keep phasing n place. TEI confirmed with Clay Bryngelson of Triton that the schedule was sent to HCFD (Matt and Rycca) for approval and then will issue to all parties.
08/19/21 – Const Mtg held, RFI #4 submitted on shower location. The preliminary schedule is distributed. State officials were down checking on progress.
08/26/21 – Clay and Scott are doing the project management on the JC Recovery project and things are moving along better than before. Plumbing submittal for Drinking fountain submitted and returned. P, we iping specialties submitted and returned. RFI #4 was answered by GBBN. Work continues in the South building. Jax is nearing completion. Exhaust fans can stay in JAX area as is.
10/28/21 – Construction continues with meetings the first and third Thursdays of the month. Core drill issues and location have been coordinated with THP, Triton and TEI. Walls for showers, toilets, and pipe chases evaluated and coordinated. GBBN and THP coordinate the core drill locations. Currently working in SE pod and building walls. Waiting for asbestos abatement team approval. coordinated core drill locations in the SW last week.
11/18/21 – Const mtgs continued every other week with the Sheriff. Today we discussed progress in the SE pod and coordinate Medical, Jax, and OB/Gyn changes. Schedule was briefly discussed. Core drill summary discussed and needs to be done. Jails products need to get on order, current wait time is 14-16 weeks.
12/09/21 – Schedule mtg with Triton. We discussed updating the schedule to match the July 1 deadline. Clay provided a revised schedule with July 1 deadline that we review at the meeting. This is the drop dead date with the County and State for this work. THP, GBBN and Triton to meet on Friday to review cores.
12/10/21 – Met on site and picked new locations for core drills for SW pad. We will meet all THP requirements for coreing the floor in this location. 3/4 core drills are moved to make this work.
12/13/21 – TTC releases field report with notes and questions from the fieldwork.
01/25/22 – Project meeting this week went well. Plumbing and fixtures are being installed and pipe in SE and SW pods. NE and NW demo is underway. Abatement scheduled for this week. The handwashing sink for the OBGYN sketch was sent by TTE to Triton for piping up new location and we will be using the bathroom sink for the main room.
02/24/22 – Triton making progress in the South building. North building core drills are complete. North demo is almost complete. Window RFI submitted and answered for piping. We have a meeting with Triton this afternoon on project issues. We’re meeting to discuss the project specifics this afternoon.
03/31/22 – Southeast and Southwest pods are progressing ahead of NE and NW. The plumbing equipment is installed, electrical coming along, and ceilings coming in next week. NE and NW demo underway, medical wall not out yet. HVAC and controls are started. Window tint was approved last week.
04/25/22 – THP anticipates reviewing core locations for the northeast area the week of May 2nd.
04/28/22 – NE pod verbally approved for rotation of plumbing fixture. COR #8 and #9 submitted by Triton for consideration. Ceiling is being installed in the South building. Medical and medical wall scheduled for demo and move in May. This will allow core drill and final coordination for NW pod in early May.
5/16/22 – THP, Thermal Tech, Triton, and GBBN met onsite to discuss core hole locations for the NW pod. See GBBN’s field report for summary and pictures of core hole locations and discussion. Also, a couple items in the NorthEast pod were discussed: lintel bearing at 4” masonry wall and existing structural bolts through existing column.
05/25/22 – Weekly meetings continue for coordination with Triton on project progress. Significant progress was made in the North building during the past month. Final core drills are complete in the NE pod. NW pod ADA changes were finalizing with Triton, GBBN to issued Bulletin 2A to capture these changes worked out with Triton and County. We need to revisit scheduled completion for this work with Triton at next core meeting.
05/25/22 – THP working on answers for the lintel bearing at 4” masonry wall and the existing bolts through the existing column.
06/30/22 – The South building pod work is making progress. The ceiling grid is installed. The above ceiling inspection did not pass because the latest IBI drawings were not on site. Triton looking to update this. The North building work is progressing as well. Once the masons are done in the NW pod they will move to the NE and relocate the wall. The door installation was moved ahead of the window and windows cuts.
07/27/22 – Progress continues in all four pods. Clay has moved on and Jason is taking over PM duties. We need to update the Core meetings since Clay moved on. Jason emailed an updated schedule for the window cuts and we are working on final details on the order. ThermalTech scanned the pods this month and turned over the scan files to Matt on a thumb drive for their use.
08/04/22 – Window cutting delayed per Triton. “Bad news from Donaly as well this afternoon after they looked at their files on who were badged. One of the people they had badged is no longer with the company so they only have 1 person badged and cannot do the work next week since they only have 1 person. Please notify the Sheriff team that we are on hold until we get them thru the badging process. We will hold off on scaffolding until the work is ready to be completed. I will also notify the rest of my team, including scaffolding. Sorry for the delay in this portion of work. We will work to reschedule as soon as they are badged.”
08/18/22 – Const Mtg. Triton updated us on project progress to date. Scaffoldign arriving next Monday and Tuesday. Triton to coordinate delivery with Sheriff and Facilities. Two hallway door frames are set into place for masons to start blocking in. Triton to coordinate shutdowns with secure access to space during demo & new work. All plumbing inspections are complete and approved. Relocated WC/LAV set into place on relocated wall. Ceilign work is ongoing, all grid is in, working on tiles. We confirmed there is not ceiling on the observation deck on this job. Change order to fix flooring will be approved but Triton has to improve coordination and phasing so it doesn’t get messed up a second time.
08/22/22 – Washer & Dryer and Caulk submittals came in and were sent back for revisions.
09/01/22 – Good meeting with Triton, they are ramping up work to meet deadlines. Jails coming back next week to keep working on ceilings and doors.
09/08/22 – Core meeting, more coordination with Triton and pushing for completion. Washer & Dryer approved with credit for last two years of warranty from Triton. Windows openings are in the side of the building, Triton and Neiheisel are fabricating the weeps and sill plates for modified design.
09/15/22 – Const Mtg at JC, work continues. Floor grinding is starting second shift and Jails is onsite finalizing all work.
09/24/22 – Core meeting. Big discussion on cabinetry and casework. Triton submitted a laminated multi-use cabinet until the SS arrives. This led to a discussion about who is providing the other cabinets in the Observation Shack. After some research, it was determined the Sheriff is providing the cabinets that Triton is not per Alt 2 adn Triton still needs to provide the Multi-Use cabinet. RFI-28 returned on Sunday to Triton.
10/26/22 – Two secure hallway doors complete, two more hallway doors almost done, concrete polishing complete, observation platform almost done, beds are on site, tables at Jails, ceiling mostly installed, HVAC is complete, fire protection is complete, plumbing and plumbing accessories complete. RFI submitted on Deal Tray, RFI submitted on Observation glass. Exterior Windows are the hang up at this time, Jails is not or will not get them installed. Duct cleaning, tunnel repair and first floor finish will be last.
12/15/22 – Work continues on this project on a daily basis. South pod has been punched. TTC to finish his and send all three by end of week. Final windows for North building to arrive 12/28, Jails says they have 4 to 5 days of work left after the windows are installed. Deal trays, sills, jamb covers and door pulls are final details we are working out. Shower heads needs to be repositioned to keep water in the shower basins.
01/24/23 – Punchlsit were completed on 1/19 for MEP and 1/20 for GC. All punchlist sent to Triton. The windows are installed, the deal trays are installed, the bunk walls are done with painting happening now. The scaffolding was removed last week. Teh first floor epoxy was the wrong color. We are down to a new set of “opportunities” to get coordinated with Triton, including cameras, air balance, epoxy floors, sills and jambs. Change Order #8 was approved, signed by TTE and sent to Triton.
02/22/23 – Triton finished all four pods and acquired TCO for all four pods this week. Back punchlist were distributed to Triton for final work. No weld certificate is needed, TTE to tell Triton.
03/30/23 – Working with Triton on matrix issues and a potential change order for reworking the bandwidth associated therewith. Commissioners scheduled to walk the site tomorrow. Terry, Matt, Mike will attend.
03/23/23 – No updates from THP.
03/31/23 – The walk through was canceled. TTC working on Special Inspections with City after speaking to inspector yesterday. Scheduled for 4/14/23 all day with Terracon.
04/10/23 – Door and all hardware is installed in South pod. Triton is working to schedule the painter down to the jobsite to complete the painting of the door. Replacement shower curtains are installed in all pods. Attic stock has all been moved downstairs and placed by the cages as requested by Andy. All Jail Product crates have been removed from the loading dock area.
04/14/23 – Teracon onsite for weld inspections. Public walk through today with Commissioners and City and state dignitaries.
04/17/23 – Pneumatic actuator replaced in SE pod, Triton sent video showing it was working.
04/26/23 – Scheduling building cleaning with Triton and project closeout documents have been sent in for approvals.
05/21/23 – Project is complete and Substantial Completion sent. Window washing starts this week.
06/28/23 – Project cleaning is complete. Closeout documents have been received. Triton has billed for all but retainage. Issues with Jails have been worked out.
07/26/23 – Triton met us on site two weeks ago. As of today, they have not met their cleaner on site to fix the wall streaks. All As-Buit drawings sent in for this job.
08/28/23 – Triton sent request for second camera model for O&M manuals, and cleanign of the outdoor wall.
09/27/23 – Third party cleaning company was onsite today and recleaned the outside of the building with an 80ft crane and pressure washing with chemicals. Final pictures look good. Triton shared final condition today about 4pm. Triton ordered new part for leak on 3rd floor.
10/25/23 – Waiting on Phase 5 approval from State of Ohio. Outside of building is cleaned and third-party cleaning company worked out. Retainage payment signed and sent by GBBN, hold until county satisficed with State Review process.
01/31/24 – Project closed out and all paperwork submitted. Waiting on final certified payroll before we close this job out.
02/23/24 – Closeout complete and drawings submitted.
02/29/24 – Ready to archive.
03/22/24 – TTE requested updated closeout documents and all AIA closeout forms from Triton.
04/25/24 – Triton stopped over to look at floor tile cracks. Tommy believe the sub-floor came loose in only one pod. They will remove and repair under warranty. Champlin to assit ThermalTech in updating CAFM drawings.
05/28/24 – Project ready to archive.