09/18/20 – New Arc Flash project SOSS sent to County, followed up with some additional drawings to Tony from study. This project can probably be archived.
09/24/20 – Approved SOSS has been received. Arc Flash to begin.
12/09/20 – Duke Energy information finally received from Duke, and model is developed. Site visit to coordinate and confirm existing conditions to be scheduled ASAP (post quarantine).
01/26/21 – TEI conducts field survey, develops model and is finalizing the model. Model results to be sent to Charlie at CMI for review no later than 01/29/21.
02/23/21 – TEI completes model and sends to Charlie at CMI for review and comments. Upon receipt of Charlie’s comments, TEI will implement, print and apply labels.
03/24/21 – TEI receives and incorporates comments from CMI. Model completed and labels are printed and TEI is scheduled to apply labels week of 03/29/21.
04/28/21 – Labels applied. TEI to submit printed results to HCFD and the project is complete.
05/26/21 – Project complete. OK to Archive