JC – CARE Pod Counseling Rooms

PM: Matt Butz, Sam Hofmann
04/25/24 – Project update at Partner Meeting
5/29/24 – Field verification confirmed. CDs in progress.
06/27/24 – Final floor plan given to Matt for confirmation of scope from sheriffs.
07/25/24 – Bid set in progress. scheduled for owner review on 8/9.
08/29/24 – Owner review set submitted. Project to be out to bid in next couple weeks.
09/26/24 – Project is out to bid. Pre-bid scheduled for 10/1.
10/31/24 – Only bid received was non responsive. Project is back out to bid today.
12/12/24 – Bid opening today.
01/30/25 – Alpha was awarded the bid. Kickoff to be scheduled in near future. Permit to be submitted in near future.
2/27/25 – Contract finalized. Kick off to be scheduled in near future.
03/27/25 – Kickoff held. Submittals incoming.
04/24/25 – Submittals returned. Change order #1 processed. Mobilization to be scheduled.
05/29/25 – Project scheduled to begin 6/30.
06/26/25 – Start date delayed due to hollow metal frame manufacturer issue.
07/31/25 – All issues solved. Waiting on Alpha to schedule mobilization.
08/28/25 – Waiting on confirmation for glazing ship date. Alpha has reached out numerous times to McAndrews and has not gotten a firm response.
09/25/25 – Glazing will be delivered by end of november. Alpha will mobilize next week and install temporary glazing until the BR rated glazing comes in. Frames were delivered in one single piece which are too large to fit into any elevator. Frames will be cut in half in the field and welded back together once in place.
10/30/25 – Alpha’s mason walked out on the job. A couple masons reviewed the project before they settled on one. Electrical work is complete. Alpha is convinced that the mid November deadline will still be met.
12/11/25 – Punch walk through tenatively scheduled for week of 12/22. Mason work is almost complete.
01/28/26 – Back punch complete. Waiting on closeouts.
02/26/26 – Waiting on closeouts.
03/26/26 – Closeout items missing sent to Alpha. Awaiting final submission.
04/30/26 – Waiting on hard copies.
05/28/26 – No Update.
06/25/26 – Hard copies delivered. Final pay app approved.