PM: Matt Butz, Sam Hoffman, Mike Barth
04/25/24 – Champlin has submitted SOSS, ThermalTech submitted SOSS recently.
05/30/24 – SOSS returned. Project kickoff to be scheduled in near future. BW said that this project on the fast track due to a recent incident in the parking lot.06/27/24 – Kickoff to be scheduled.
07/25/24 – Meeting held on site with County, Champlin, and several judges. Champlin is investigating fencing options and guard booth options for review. Plan will be modified based on comments in the field.
08/12/24 – THP completed a cursory field measurements for review of the proposed fencing.
08/12/24 – THP sent proposal to Champlin for review.
08/27/24 – THP sent SOSS to County for review.
08/29/24 – THP working on design with Champlin.
08/29/24 – Second meeting held for more investigation. THP found that additional structure will be needed for fence and guard booth.
09/25/24 – THP issued bid documents 9/20/24.
10/31/24 – Project is out to bid. Opening on 11/8.
01/30/25 – Tumlin was awarded the bid. Kickoff held. Permit submitted 1/29. Pending zoning and historical society approval. Submittals incoming.
02/27/25 – Submittals in progress. Tentative schedule received. Rejection received from the historical society.
03/27/25 – Submittals in progress. Zoning hearing scheduled for 4/2 for historical variance.
04/24/25 – Historical approval provided given some aesthetic changes to the project. Tumlin to provide pricing on the changes.
05/29/25 – Working with guard booth manufacturer to meet energy code requirements.
06/20/25 – THP submitted Bulletin #1. This covers the revisions that resulted from historic review board comments.
06/25/25 – THP received preliminary pricing from KT Holden for resurfacing lots: 250k.
07/31/25 – County approved moving forward with the Resurfacing project.
08/26/25 – THP modified the footing design to accommodate a continues concrete curb. THP preparing final sketch to be published on 8/30 with Bulletin No. 4.
09/24/25 – THP issued bulletin #4 on 8/29/25 to add grade beam for field conditions and new parking lot resurfacing work. Project in CA
10/30/25 – Grade beams installation onging. Guard booth will be lowered into place this weekend. Progress continues.
01/28/26 – Steel for door installed. Work ongoing.
02/26/26 – Cold formed steel going up in the next couple weeks. Fence material delivered. Phase 2 is pushed back slightly to align work.
03/26/26 – Phase 1 nearly complete. Cladding structure to begin weather dependent. Phase 1 fence installed. Phase 2 tentative date is 4/13.
04/30/26 – Phase 1 complete this week. Following for punch and commissioning. Phase 2 to begin 5/11. Parking on e court street and bus stop coordinated with city to prep for phase 2. Rycca, Mike and Derrick met onsite for security plants. SOSS incoming.
05/28/26 – SOSS for security plant beds submitted. Sheriffs have solved their booth connection issue and kicked off phase 2.
06/25/26 – Phase 2 to switch over mid July. Doors and booth to be tested to ensure seamless transition.
07/30/26 – Phase 2 has begun. Demo exposed some underground conditions that are being resolved. Phase 1 issues have been worked out, including new controls after being struck by lightning.
08/28/26 – Issues discovered below grade have been solved. Grade beams almost complete. Steel has been erected.
10/29/26 – Finishing fence this week. Programming second door. Ready for turn over next week.