PM: Bert Watts, Mike Murphy
12/06/21 – Signed SOSS received.
01/25/22 – Preliminary plans and schedule created. Will be discussed at JC Door replacement Kick-off.
02/24/22 – Product research completed. Price Estimate in progress.
03/31/22 – Estimate and summary provided to County.
04/28/22 – Waiting on PO.
05/26/22 – Documentation in progress
06/30/22 – Documentation in progress
07/28/22 – Documentation in progress
08/25/22 – Documentation being finalized.
09/29/22 – Final Review to be submitted to County 9/30
10/27/22 – Some corrections submitted. Hard copies to be delivered today for sheriff review.
12/15/22 – ODRC approval. Project to go out to bid 12/22
01/26/23 – Bid opening is 1/30.
02/22/23 – Triton was apparent low bidder but their product did not meet specs. They are saying that they can provide the correct product for 1.6 million.
03/30/23 – Triton pulled their bid. Fabcor was the next lowest bidder. Contracts in progress.
04/27/23 – Contracts returned. Fabcor is starting the submittal process.
05/25/23 – Kickoff meeting held on site. Fabcor to finalize submittals for ORDC review. Fabcor to schedule site visit to field verify all dimensions.
06/29/23 – 4 Screens to be installed prior to the rest as a trial. submittal returned. Jails yet to schedule installation.
07/27/23 – Windows are on order. Jails has been on site to measure the remaining window sizes.
08/31/23 – 4 test screens to be installed next week. County to get approval from state for the rest of the screens.
09/28/23 – Test screens installed and reviewed. List of items from Champlin and Jails sent to Kane for review before the large install. Still waiting on State approval to return submittals.
10/25/23 – State approved submittals. Sample from Kane that fixed mock up issues received. Review meeting scheduled with Captain Wilson 10/26.
12/07/23 – Comments from mockup returned to Jails. Jails to follow up with a schedule.
02/29/24 – Schedule provided by Jails. Install to begin in April.
03/28/24 – Install to begin 4/1.
04/25/24 – Installation ongoing. North 5th floor to be complete next week.
05/30/24 – Installation ongoing. South 5th floor to be complete next week.
06/27/24 – Installation ongoing.
08/29/24 – Installation ongoing.
09/26/24 – Installation ongoing. Lexan CO approved. Day space CO in progress.
10/31/24 – Installation ongoing.
12/12/24 – Installation ongoing. Day space CO approved. Quote to add Lexan to previously installed screens incoming.
01/30/25 – Installation ongoing. Lexan install in psych unit ongoing. Dayspace screens to be installed next.
02/27/25 – Original contract work complete. Dayspace area is ongoing. Second round of Lexan install ongoing.
03/27/25 – Dayspace mock up rejected. Revised submittal returned. Correct mockup to be installed prior to manufacturing of the remaining dayspace screens.
04/24/25 – Revised mock up also rejected. Kane to provide solution to prevent mesh damage.
05/29/25 – Kane provided solution. Mock up revision #2 to be installed.
06/26/25 – Mock up approved. Manufacturing of dayspace windows to begin.
07/31/25 – Delay from steel mesh manufacturer pushes install into October/November.
08/28/25 – No update.
09/25/25 – No update.
10/30/25 – Jails will remobilize end of november.
12/11/25 – Day space installation ongoing.
01/28/26 – Scope to be complete by end of 2/6. Closeouts requested.
02/26/26 – CO work is complete. Additional screens in Med unit is requested. Awaiting pricing from Jails.
03/26/26 – CO approved for Med unit screens. Delivery date to be provided by Jails.
04/30/26 – No update.
05/28/26 – No update.
06/25/26 – Closeouts in progress. final change order screen installed.
07/30/26 – Closeouts reviewed. Missing items requested. OK to close out the project.