PM: Bert Watts, Mike Murphy
12/06/21 – Signed SOSS received
01/26/22 – Plans and Schedule created. Will be discussed at JC Door Replacement Kickoff.
02/24/22 – Product research completed. Price Estimate in progress.
03/31/22 – Estimate and summary provided to County.
04/28/22 – Waiting on PO.
05/26/22 – Documentation in progress.
06/30/22 – Documentation in progress.
07/28/22 – Documentation in progress
08/25/22 – Documentation being finalized.
09/29/22 – Final Review to be submitted to County 9/30
10/27/22 – Some corrections submitted. Hard copies to be delivered today for sheriff review.
12/15/22 – ODRC approval. Project to go out to bid 12/22
01/26/23 – Bid opening is 1/30.
02/22/23 – Bid opening is pushed to 3/3. Final addendum to be issued before 2/28.
03/30/23 – The bid has been cancelled. An invitation for manufacturers to demo their products has been put out for 4/5.
04/05/23 – Manufacturer presentations held. Willo, Airteq, and Habersham displayed their products to the county and sheriffs.
04/27/23 – Revised bid sent to the prosecutors office for review. Once approved, the project will be ready to rebid.
05/25/23 – Project has been rebid. Pre-bid meeting is 6/2.
06/29/23 – Bids received. Project is awardable.
07/27/23 – Lowest Bidder – Jails – bid is under review with prosecutor to determine if bid is awardable. Second lowest bidder – cornerstone – vetted.
08/31/23 – PO is approved and contract has been sent. Kickoff meeting to be held in the near future.
09/28/23 – Kickoff meeting held. Site visit to measure existing conditions scheduled for week of 10/9. 4 cell mock up to be scheduled at site visit.
10/25/23 – Site visit occurred. Mock up submittal returned. Mock up installation to be scheduled in near future.
12/07/23 – Mock ups to be installed 1/9.
02/29/24 – Mock ups ran into trouble connecting with the PLC. Cornerstone could not figure it out onsite. They sent locks to be tested by Stanley. Locks have not been successfully programmed yet.
03/28/24 – Stanley determined that the locks can be used with modification to the PLC system. Cost of the upgrade is around $500,000. Conversation of next steps ongoing.
04/25/24 – Working mock-ups installed. Schedule to be determined for Securitas to be on site for upgrading power.
05/30/24 – Work to begin 6/17. Work is expected to take 2-3 weeks per floor.
06/27/24 – Locks delivery was delayed. The locks had to be re-programed. Cornerstone to overnight one re-programed lock to ensure functionality. Prep work on George 51 is complete.
07/24/24 – Matt punchlisted project last Sunday. They met the State on Monday. One door hitting the wall, so we need to add a new bumper.
08/29/24 – Installation ongoing. Cornerstone getting to a unit per 2 weeks.
10/31/24 – Installation ongoing. No issues have been resolved by airteq regarding quality control. Meeting to discuss issues with Cornerstone and Airteq will take place next week.
12/12/24 – Installation ongoing. Power upgrade is complete. Rewiring lock power is in progress. New switches to be installed at end of January.
01/30/24 – Last unit work ongoing. Cornerstone and Airteq VPs to attend a meeting in February to work out warranty issues.
02/27/25 – Meeting held with VPs of Airteq and Cornerstone to finalize warranty discussion. 5 year warranty agreed upon. Medical unit to be complete this week. outstanding work will be repairing damaged locks.
03/27/25 – All contract work complete. Closeouts to be submitted and correction work to be done.
04/24/25 – Replacement housing and attic stock to be delivered in near future. Cornerstone will begin correcting outstanding punch items.
05/29/25 – No Update.
06/26/25 – No Update.
07/31/25 – No Update.
08/28/25 – No Update.
09/25/25 – Attic stock and corrected housings delivered and replacement process has began. Closeouts outstanding.
10/30/25 – Still have a couple of things left to do. We need a list of lock boxes left to do.
12/11/25 – List of outstanding punch items provided. Closeouts under review.
01/28/26 – Punch work complete. Attic stock is outstanding. Closeout corrections requested.
02/26/26 – Closeouts will be delivered next week. Attic stock needs to be replenished from warranty work orders.
03/26/26 – Still waiting on closeout docs. Attic stock is still not on site. Warranty period has not began.
05/28/26 – No update.
06/25/26 – No update.
08/28/26 – Phillip onsite to review rust damage. Champlin to provide report.
09/24/26 – Report submitted. No update on solution.
10/29/26 – Roller bolts have been discovered missing on several doors. Sheriffs to provide report.