07/11/19 – ThermalTech Issued SOSS-F-113.
08/21/19 – County issued SOSS and PO to ThermalTech.
10/21/19 – Project Issued for Bidding.
10/28/19 – Prebid held for project.
10/30/19 – TEI working on Addendum 1 questions.
12/12/19 – Project is in for contract and approval. County reports the contract is with the vendor.
01/21/20 – Pre Const held with Andy, TTC and Triton.
01/28/20 – Pre Const meeting notes distributed. CO costing approved by TTC to Marley.
01/29/20 – Triton sent in SOV, project schedule and submittals.
02/24/20 – Triton really pushing for background checks, Tony to check on Monday and let us know. Triton needs to get started very soon to have any chance of getting done even by April 15.
03/24/20 – Triton emailed today that the project has been put on hold for this spring and summer and it will be done in October 2020 due to the government shutdown and delivery orders.
04/27/20 – Material has arrived at Triton. Pictures were sent to ThermalTech for approval for payment of stored materials. Covid-19 has this project on hold for the time being.
05/27/20 – No additional updates this month due to Covid.
06/23/20 – TEI updated the submittals and sent to Triton for the job. Block fill is in the Triton yard and awaiting installation in November 2020. There were a couple of items on the submittal review that Triton will check on with the mfgr. Brent Ernsthausen and Clay are our new PM on this job.
07/29/20 – Triton and Brent back on job, TTE caught up on prep work for these towers with Brent for fall work.
08/26/20 – Discussed paying Triton payapps based on equipment stored in their yard. TTC sent photos along with approved payapp.
09/18/20 – Allowance Usage #1 email out and signed by TTE and Triton, we are awaiting final approval by County.
10/28/20 – Pre Const meeting moved to 11/4/20 1:00 pm.
12/10/20 – CT#2 demo is complete. Crane is scheduled on 12/19 with a street closure anticipated. Triton keeping us up to date with email updates from Clay. The project is proceeding along nicely.
12/28/20 – Verbal approval on extra work for cooling tower C-3 replacements was given. Triton continuing work on the towers and order for new galvanized pans was placed with Stoermer.
01/26/21 – Triton continues to grind out the towers and prepare them for rebuild awaiting the parts from Stoermer for rework on the towers.
02/24/21 – Triton stopped for the cold but now back underway. Tower completion should not be an issue.
02/26/21 – Sealing was completed yesterday. With sealing completed, this has allowed us to install the nozzles and piping back into the towers. We are scheduling the alignment for the gearbox. We will begin the fill next week and should be completed next week as well. We will do the clean off of the roof the following week.
03/25/21 – Triton wrapping up final CT work with the hopes the towers will be ready to fill next week. They are working on the gearbox connections this week.
04/29/21 – Triton complete with all work. ThermalTech issued a punchlist to Triton for this project. There is a low water level alarm reporting back to JCI that is in alarm.
05/26-21 – Allowance #1 & #2 out to Tony for signature for the allowance usages related to the interior pans and repairs. There is a small amount that has to be paid as a change order to the job for extra work on the four pans repair, this will now include the level water floats that monitor the basin water levels. Triton has completed and returned the punchlist for this job minus these final items. Triton will purchase and install the floats in the next few weeks.
06/25/21 – New water level valves installed. Triton fixing final leak on CT. Closeout paperwork started. We need Tony to approve and sign allowances and change order #1.
07/28/21 – Project Complete.