10/03/19 – Project request made Scott Weikel for glass security panels to be installed at public counters on the 9th and 10th floor of the Taft Building.
11/01/19 – Champlin scheduled for field visit to verify locations and dimensions of work area.
11/18/19 – Cost estimate uploaded to Archibus. SD drawings sent to County.
05/20/20 – Meeting at Taft center to discuss scope. Attended by Sam and Mike from Champlin, Rycca, Jessica, and Bryan from County and Scott from the Taft center.
06/03/20 – additional site visit to verify existing conditions
06/03/20 – Meeting at Taft Center to choose product. Attended by Sam, Mike, and Jose from Champlin. Rycca and Bryan from County and Scott from the Taft Center.
07/02/20 – Draft of ITB sent to County for approval
07/27/20 – final copy of ITB and Plans approved. Prebid meeting set for 08/03/20 at 10 am
08/20/20 – Bids received and apparent low is James Hunt Construction.
09/03/20 – Contract signed by Hunt
09/14/20 – Submittal returned to Hunt
10/29/20 – Construction planned for the weekend of 11/21. Punchlist to be scheduled monday 11/23.
11/21/20 – Project ran into complications. New date of install is the weekend of 12/19-20. Punchlist to follow.
12/26/20 – Installation 12/26-12/27 Champlin performed punchlist 12/27
01/18/21 – Additional punchlist issued.
01/23/21 – Glass and 1 dented post cover replaced. sometime this week 2nd post cover to be replaced.
02/24/21 – Back punch by Sam Hofmann, Danny Rusconi, Rycca Thacker and Scott Weikel. Final touch up items to be completed 2/25 at 4pm
02/25/21 – All punch items completed
03/25/21 – Project essentially complete. Final payment sent. The project can be archived.