Hamilton County Facilities

JC – Drinking Fountain Replacements

PM: John Nester, Terry Cannon
03/25/21 – SOSS approved.
04/23/21 – Acorn and StreamKey suggested moving the airtrol valve inside. After discussion with Facilities, this doesn’t seem like a solution. About 30 drinking fountains need a close connection. We are working on better solutions.
04/29/21 – The first draft of the drawings are ready for review.
05/26/21 – StreamKey reaching out to Acorn to send a revised mock-up for the close quarter’s actuation valve for us to test before we bid out this work. 32 drinking fountains required this type of actuator. We rejected the interior drinking fountain installation.
06/15/21 – Worked with StreamKey this week to iron out final samples of the AirTrol retrofit kit. Acord will manufacturer one item and send it to the County for testing. It will ship to StreamKey who will deliver it to County for testing.
07/28/21 – Drawings and Specs sent to HamCo for final review. Project will be Issued for Bidding on 8/2/21.
08/18/21 – Addendum 1 issued.
08/25/21 – Bids were opened today and we received several good bids within reason of each other. They are all significantly under the published estimate.
08/28/21 – Triton was the apparent low bid. TEI vets the bid and sends a recommendation to HCFD to proceed with Triton. Pre-construction meeting and kickoff meeting conducted.
12/02/21 – Onsite kickoff & coordination meeting with Facilities and JC held with Triton.  The material is onsite and Mike Adams will be our lead plumber from Triton.  We meet with John, Andy, and Danny for previous plumbing work and kickoff.
01/24/22 – All work complete and TTE to start punchlist.
01/25/22 – North Building Punchlist complete. TTE to send to Triton for rework. Relocate controllers mounted on the duct, provide tubing management.
02/24/22 – Triton says all punchlist is complete in the North building and almost done with the South building.
03/31/22 – Punchlist completed in North building, same work was proactively done in South building. TEI coming down to punchlist the South building in April.
04/26/22 – South building punchlist is complete. TTC to distribute. All drinking fountains are working expect one does not drain and one does not have a drain pipe any longer. All base bid work looks good.
05/25/22 – Punchlist distributed to Triton. County fixed a couple of owner-related items. Requested pricing from Triton on helping with Lobby sinks but prices seemed a little high. We have some money left in the PO from the allowance. I will request closeout documents from Triton next, the project is complete and working well.
06/30/22 – The project is done, closeout documents are here. Waiting on final payapp from Triton.
07/27/22 – Closeout documents are being finalized. O&M manuals are at the Courthouse awaiting final paperwork.
08/22/22 – Taking project to closeout, requesting additional equipment from Triton.