PM: John Nester, Terry Cannon
03/25/21 – SOSS Approved
04/29/21 – The first draft of drawings are ready for review. TTC to send to JN.
05/26/21 – TTC initial review is finally complete and back in for changes. We will get a review set to the County by Friday, June 18 that includes both mechanical and electrical.
06/18/21 – Review set sent to County. The basic design is complete. TTE reached out to JCI for a controls budget number for the project.
06/21/21 – JCI provided existing sequences that were missed from our as-built drawings. We confirmed the existing unit has steam heat, city water cooling and a VFD that is linked to the washer control. We are are proposing upgrading the controls to monitor the dryers, running the VFD at three speeds, insulating the lint collection plenum and reducing the required outdoor air for better space control.
06/24/21 – County sent AIA contracts for inclusion in the bid manual. 90 Days completion time.
07/26/21 – New equipment submittal received from Trane with budget pricing. $18k for new unit. TTC working out new control sequence with JCI and finalizing pricing for bidding. Target bid issuance in next two weeks.
08/23/21 – Mechanical drawings and equipment selections are complete. Drawings sent to JCI for final controls sequences for the job. Electrical needs VFD information to relocate VFD to EF wall for reuse in new scheme.
08/26/21 – Project will be ready for bidding 9/1.
09/25/21 – Addendum 1 issued.
09/27/21 – Addendum 2 issued.
09/28/21 – Prebid went well, many bidders attended.
10/07/21 – Bid opening complete. two bidders, Debra & Blau. DK apparent low bidder.
10/28/21 – Pre-Award meeting with Debra went well, recommended for this job. project pending contract for the contractor.
12/13/21 – Project contract and PO are being finalized by the County. DK has sent submittals that TEI has reviewed. We are awaiting the project paperwork to be in place to return submittals and hold pre-const meeting.
01/22/22 – Submittals returned to DK and project schedule requested.
02/24/22 – update forthcoming from DK.
03/31/22 – Control submittals are in, TEI to review.
04/28/22 – Checked with DK and Trane, Unit will be here in June. Control submittals are returned and ready. DK to verify delivery date so we can setup the next const mtg.
05/25/22 – Dave and I both have reached out to Trane to get an updated delivery on this unit but we cannot get it out of them yet. As soon as we have that, we can set the schedule.
06/14/22 – Trane delayed the delivery until 8/17/22. We will schedule the pre-const meeting closer to this delivery.
07/27/22 – Checked in on delivery date – no confirmation from Trane yet.
08/24/22 – DK mobilizing for unit replacement work. We don’t have an isolation valve where we need one to work on this unit without drawing the entire north building so we will do hot taps and run new 2″ piping to the HVAC unit. The existing unit can remain on and cool during the demolition work doing it this way.
09/22/22 – HVEC-1 is demolished. New piping and hot taps are done. The new unit is being installed now. Some spacing issue is going to make changing the filter tricky.
10/26/22 – Everything installed with the unit, piping under pressure test, only electric and controls are left to complete.
12/15/22 – Per Debra all work is complete except for the controls work, waiting on JCI to finish. Ready for punchlist.
01/24/23 – I have been working with JCI to get their subs background check approved so they can finish the control work on the unit. The MEP work is complete. It’s down to controls. I can punchlist this job.
02/2/23 – JCI has background checks complete, working on final controls programming, rest of work is complete.
04/17/23 – Electrical and Controls vendors on site this month to startup up the unit. After some back and forth we finally have power and controls. the unit is ready for a punchlist.
04/26/23 – The unit was making noise yesterday. ThermalTech and DK on site to get this resolved. The blower motor was realigned by noon and put back online.
05/21/23 – Unit is up and running JCI made additional control changes last week. First stage cooling and fan where scheduled on anytime the space was in operation. 2nd and 3rd stages tied to the dryers. TTE needs to commission and punchlist this project.
06/28/23 – After checking on the unit three times this month, I can confirm it is providing cold air to the laundry room measure air at less than 65F this week. I still need to do the final punchlist. JCI technician has left JCI, trying to find who our new engineer is.
07/26/23 – Punchlist scheduled 7/26 at 1pm.
07/27/26 – Punchlist distributed to project team.
08/29/23 – Request closeout documents from DK again. I am holding final payapp.
09/27/23 – DK says they are working on closeout documents but we do not have them yet. We are also working on JCI controls punchlist with JCI but they have not confirmed who is out new technician. I asked DK to find out who is finishing this job for JCI and reached out to Dustin Stewart, our new sales engineer.
10/25/23 – JCI working on new technician for closeout and controls punchlist but no one has been assigned yet. County sent approved list through TTE to JCI today. Working on closeout with Debra Kuempel. Unit seemed to do fine this summer, it was definitely better in the room with the new unit running.
12/06/23 – TTC has been talking to DK and JCI about assigning a new technician for our work. But as of yet, no avail. TTC called Dustin Stewart and Greg Platt to get this moving!
01/24/24 – Motor bearing bad on unit. DK removed motor and took it out for rebuild at A-1. They will reinstall the motor ASAP.
01/30/24 – Closeout documents received from DK. JCI cancels punchlist visit due to family emergency. TE rescheduled to next Tuesday.
02/23/24 – Met JCI onsite this month and it went well.
03/22/24 – Project is ready for closeout.