Hamilton County Facilities

JC – Emergency Power Upgrade 2025

PM: Matt Butz, Mike Barth
11/06/24 – THP update – THP provided an email with budget to rebid the project.
01/30/25 – Restart post to track 2025 project for this project.
01/24/25 – THP update – THP provided a formal SOSS.
02/26/25 – Prebid Meeting occurred on 02/26/25. Attendance by DK, Dunn Electric and Driekast. Bids due on 4/10/25.
03/07/25 – Terracon on site for test boring. Preliminary results included sandy dirt findings. Official report coming later this month.
03/25/25 – Terracon invoiced project for work but final report not here yet.
03/26/25 – Project bidding. Lots of questions being submitted by Glenwood. Bids are due 04/10.
04/23/24 – Project bids received. (2) bidders. Glenwood and Alpha. Glenwood apparent low bidder. DEI approves bids. TEI vets bid ln 04/22/25 – TEI to submit letter of recommendation to start the contract phase.
05/28/25 – Project in contract phase.
06/25/25 – Project in contract phase. Contract contacts TEI asking about status.
07/30/25 – DEG, HCFD, Bldg Mgr meet with Glenwood Electric for a pre construction KO meeting. at time of bid, the generators and switchgear quoted Glenwood 6-8 weeks for submittals, and then 40 weeks +/- for shipping of gear. Glenwood released the submittals end of last week. Likely startup of construction summer 2026.
08/27/25 – DEG has not received submittals to date.
09/24/25 – DEG receives equipment submittals. Submittals under review and approval.
10/29/25 – DEG working with contractors to get the permits in order.
01/28/26 – Issues with one switch that contractor and DEG working on.
02/25/26 – CO #001 issued. All gear should be on order. Estimated delivery June/July 2026.
03/25/26 – Glenwood submits several RFIs on the project. DEG reviewing RFIs.
04/29/26 – Glenwood submits pay applications for procured material. DEG to visit the crane yards to certify the equipment.
05/27/26 – Project construction pending material procurement.
06/23/26 – DEG speaks with Glenwood, and the gear manufacturer has production delays, the anticipated mobilization date has slid to 09/01. The existing equipment in the areas where the work is to occur needs to be relocated prior to mobilization.
07/29/26 – Project mobilization pending procurement of equipment.
08/26/26 – DEG meets with Glenwood at FDL and Ohio Cat to certify some of the equipment. Gen sets are on site in Dayton Crane Yard. Glenwood to schedule certifying the equipment trip with DEG.
09/23/26 – Pre-construction meeting occurred. glenwood site super has been on site to get knowledge of the building. Construction to begin around 10/01/2026
11/06/25 – THP issued permit drawings to be submitted with Davies set.
10/01/26 – Triton issued RFI No. 1.
10/05/26 – THP responded to RFI No. 1.
10/28/26 – Construction underway. Multiple meetings and discussions re fitting generator on oversized skid into the basement. Skid to be modified to fit into the building. ATS location for North tower is final coordination item at the time.