JC – Door Phase 6
PM: Matt, Sam
10/29/26 – Project created.
Justice Center
PM: Matt Butz, Sam Hofmann
08/28/25 – Sheriffs provided scope of doors to be included in phase 5. Review set will be complete shortly.
09/25/25 – Review documents provided to county. Project will go out to bid on monday.
10/30/25 – Alpha is apparent low bidder. Bid vet occured 10/29. Alpha subbing out majority of the work to Cornerstone.
12/11/25 – Cornerstone is awarded the bid after contradictions in Alphas LOIs and Bid Vet statements came to light. Project in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract signed. Kick off to be scheduled in near future.
03/26/26 – Cornerstone has taken field measurements. Submittals incoming.
04/30/26 – No update.
05/28/26 – Submittal received and returned. Schedule needs to be determined by Sheriffs.
06/25/26 – No update. Tentative fall start.
07/30/26 – Delivery scheduled for end of August.
08/28/26 – Mobilization in 2 weeks.
09/24/26 – two phases complete. Work ongoing.
10/29/26 – Project ongoing.
JC – Cell Door and Frame Replacement (Phase 5) Read More »
PM: Jesse Estes, Sam Hofmann
09/25/25 – Project kickoff held and scope determined. Review documents will be ready for County next week.
10/30/25 – Project in bid phase. Bids open 12/1.
12/11/25 – Triton is low bidder. Project in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – Bulletin #1 issued to include emergency L31 scope. Triton to provide schedule to begin work asap.
04/30/26 – Submittals approved. Triton to provide schedule.
05/28/26 – Triton mobilized 5/26. Epoxy demo ongoing.
06/25/26 – Half of South 3rd floor pods are complete. 5th floor Hall is next.
07/30/26 – First phase grinding and polishing is complete. Furniture will be installed next week.
08/28/26 – Furniture install ongoing. Backpunch scheduled for next wednesday.
09/24/26 – Phase 2 in progress.
10/29/26 – 2 pods complete in phase 2. Work ongoing.
JC – Polished Concrete – Phase 2 Read More »
PM: Matt Butz, Mike Barth
11/06/24 – THP update – THP provided an email with budget to rebid the project.
01/30/25 – Restart post to track 2025 project for this project.
01/24/25 – THP update – THP provided a formal SOSS.
02/26/25 – Prebid Meeting occurred on 02/26/25. Attendance by DK, Dunn Electric and Driekast. Bids due on 4/10/25.
03/07/25 – Terracon on site for test boring. Preliminary results included sandy dirt findings. Official report coming later this month.
03/25/25 – Terracon invoiced project for work but final report not here yet.
03/26/25 – Project bidding. Lots of questions being submitted by Glenwood. Bids are due 04/10.
04/23/24 – Project bids received. (2) bidders. Glenwood and Alpha. Glenwood apparent low bidder. DEI approves bids. TEI vets bid ln 04/22/25 – TEI to submit letter of recommendation to start the contract phase.
05/28/25 – Project in contract phase.
06/25/25 – Project in contract phase. Contract contacts TEI asking about status.
07/30/25 – DEG, HCFD, Bldg Mgr meet with Glenwood Electric for a pre construction KO meeting. at time of bid, the generators and switchgear quoted Glenwood 6-8 weeks for submittals, and then 40 weeks +/- for shipping of gear. Glenwood released the submittals end of last week. Likely startup of construction summer 2026.
08/27/25 – DEG has not received submittals to date.
09/24/25 – DEG receives equipment submittals. Submittals under review and approval.
10/29/25 – DEG working with contractors to get the permits in order.
01/28/26 – Issues with one switch that contractor and DEG working on.
02/25/26 – CO #001 issued. All gear should be on order. Estimated delivery June/July 2026.
03/25/26 – Glenwood submits several RFIs on the project. DEG reviewing RFIs.
04/29/26 – Glenwood submits pay applications for procured material. DEG to visit the crane yards to certify the equipment.
05/27/26 – Project construction pending material procurement.
06/23/26 – DEG speaks with Glenwood, and the gear manufacturer has production delays, the anticipated mobilization date has slid to 09/01. The existing equipment in the areas where the work is to occur needs to be relocated prior to mobilization.
07/29/26 – Project mobilization pending procurement of equipment.
08/26/26 – DEG meets with Glenwood at FDL and Ohio Cat to certify some of the equipment. Gen sets are on site in Dayton Crane Yard. Glenwood to schedule certifying the equipment trip with DEG.
09/23/26 – Pre-construction meeting occurred. glenwood site super has been on site to get knowledge of the building. Construction to begin around 10/01/2026
11/06/25 – THP issued permit drawings to be submitted with Davies set.
10/01/26 – Triton issued RFI No. 1.
10/05/26 – THP responded to RFI No. 1.
10/28/26 – Construction underway. Multiple meetings and discussions re fitting generator on oversized skid into the basement. Skid to be modified to fit into the building. ATS location for North tower is final coordination item at the time.
JC – Emergency Power Upgrade 2025 Read More »
PMs: Matt Butz, Terry Cannon
01/17/25 – SOSS Requested.
02/26/25 – SOSS received, TEI starting preliminary engineering.
03/25/25 – Internal kickoff meeting held this month. Drawings are being updated with existing conditions for the building. Our first design meeting to be in April.
04/23/25 – Project design has begun, we should have preliminary review ready in a couple of weeks, and then we can meet and talk particulars for this project.
05/28/25 – First round of internal reviews complete. We are picking up TTC markups, creating a construction cost estimate, and filling out electrical coordination sheet. We will have the mechanical drawing issued for owner review on 5/30.
06/25/25 – No comments back from anyone that I know of, should we move to bidding?
07/28/25 – We sent drawings back for comment and requested AIA documents for bidding. Ready to bid but ITB not requested until budget is set.
08/28/25 – Budget set at $200,000. Comments and AIA contracts forthcoming from Facilities for this project.
09/24/25 – Prebid held last Friday, it was well attended. Addendum 1 due out this week.
10/29/25 – Pre Award meeting held with Geiler today and they can be recommended for this project.
12/12/25 – In contract approval stage.
01/25/26 – Sent before BOCC on Jan 19 for approval. We are awaiting notice to proceed. We have reviewed submittals already and are waiting on project kickoff to send them back to Geiler.
02/25/26 – Contract and PO are ready. DEG preparing for project kickoff. Pump submittals are approved.
03/25/26 – No kickoff meeting yet, submittals are approved, awaiting go ahead from County to move on this one.
04/29/26 – Kickoff meeting held early this month. Geiler commented that pumps were bid to be replaced when entire chilled water system was down. We are going to get everything in place and start this project in November 2026.
05/27/26 – DEG approved first pay application for $5500 and will send to County. Project on hold until November.
06/25/26 – Payapp received. Equipment in town, DEG to review at Geiler warehouse.
07/30/26 – Equipment approved, waiting on next Payapp from Geiler.
08/26/26 – Hold till November start.
09/23/26 – On hold until November, TTC approved and sent in Payapp 1, Payapp 2 already paid.
10/23/26 – Payapp 1 has cleared at Geiler.
10/26/26 – Pre-const meeting November 5. TTC removed the tentative tag on the meeting and update the invite.
JC – Condenser Pumps Replacement Read More »
PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and Elevar will schedule walk-thru after fist walk of 230 bldg. Need updated drawings from Champlin and door labels from HCFD that match fire door report.
04/24/05 – Walk-thru not scheduled yet.
05/28/25 – Elevar needs building info that matches between original LSS report and building plans. Current plans don’t have door numbers listed and LSS report has inaccurate photos of doors. Walk-thru on hold pending further info.
06/26/25 – JC walk-thru scheduled for 07/02 – 07/03.
07/31/25 – Walk-thru performed but drawings have not been updated yet.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates almost complete but can review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. No update on whether paint removal from stickers was successful.
06/25/26 – Paint removal will occur at JC. Elevar reviewed JC with Sheriff’s and a few items will be revised. No updates on progressing project into bidding.
07/30/26 – Elevar had questions regarding anti-ligature closer locations at JC and emailed to HCFD. List of doors needing paint removed sent to HCFD. Need final allowance amount from HCFD to add to bidding docs for door re-certificaiton/replacement if paint removal doesn’t work.
08/27/26 – Questions still remain for JC anti-ligature items but will be confirmed prior to bidding. HCFD to provide allowance figure for re-certification.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.
JC – Fire Door Repairs Read More »
PM: Matt Butz, Mike Barth
12/06/23 – TEI receives approved SOSS. Design Kick off meeting to be scheduled.
01/30/24 – TEI, HCFD and HCSO meet to discuss project objectives and kick off project on 01/30. Options and existing conditions were discussed. Card reader to be connected to the VAX system in the building managed by Risk Management. Door across the hall from Lincoln Base to be added to access control system as an alternate.
02/28/24 – TEI developing plans for this project. Based on kick off meeting for Council Rooms – the VAX controller may be upsized to accommodate additional doors that are desired to be on VAX system.
03/27/24 – TEI Proceeding with documents. Upon VAX confirmation, will complete documents.
04/24/24 – Documents in progress. Review set to be sent to HCFD upon completion.
05/29/24 – no updates.
06/26/24 – Documents near complete. TEI will send HCFD review set in next couple of weeks.
07/24/24 – TEI to deliver review set by end of week of 8/5/24.
08/28/24 – TEI sends documents to HCFD for review. Will issue bid package once review comments received and included in documents.
12/11/24 – HCFD and TEI meets with HCFD to review documents. Final comments to be incorporated and project issued for bidding first of year.
01/29/25 – Documents sent to DK for GSA Pricing.
02/26/25 – DK sends GSA pricing for project to HCFD and TEI. Project pending contract.
03/26/25 – Pending contract approval.
04/23/25 – Pending contract approval.
05/28/25 – Project in contract phase.
06/25/25 – DK, DEG and HCFD have construction KO meeting. Construction to commence approx 06/27.
07/30/25 – DEG reaches out to DK for installation update.
08/27/25 – All equipment installation nearly complete.
09/24/25 – Base bid work complete. Pending CO work (added door).
12/10/25 – Change order issued for additional work. Pending procurement and installation of additional devices.
01/28/26 – Project pending the completion of the CO work.
02/25/26 – No update
03/25/26 – no update.
06/23/26 – Project closeout and final pay apps requested from DK.
07/29/26 – DEG follows up with DK for Closeouts.
08/26/26 – no updates
09/23/26 – Grant extended. Additional security measures drawing by DEG and priced by DK.
10/28/26 – Installation of additional items in progress.
JC – Server Room Access Control Upgrades 2023 Read More »
PM: Matt Butz, Sam Hofmann
01/21/22 – Signed SOSS Received.
03/23/22 – Meeting with Sheriffs to define scope. Number of doors defined. Hold pending door lock replacement project scope.
06/30/22 – Scope to be defined at project kickoff meeting for current set of doors.
07/28/22 – Scope to be defined at project kickoff meeting for current set of doors.
08/23/22 – Scope finalized. Plans to be sent and confirmed with sheriffs.
09/29/22 – Project out to Bid
10/27/22 – Triton won bid.
12/15/22 – Contracts signed and returned.
01/26/23 – No update.
02/25/23 – No update.
03/30/23 – Triton has subbed Jails Products again. Submittals to arrive shortly.
04/27/23 – No Update.
05/25/23 – No Update.
06/29/23 – No Update.
07/27/23 – No Update.
08/31/23 – Submittals received. Changes noted. Meeting to discuss with Sheriffs to be scheduled in near future.
09/28/23 – Meeting held with Captain Wilson. Submittals to be returned with changes as required.
10/25/23 – No update.
12/07/23 – No update.
07/27/23 – No Update.
08/31/23 – Submittals received. Changes noted. Meeting to discuss with Sheriffs to be scheduled in near future.
09/28/23 – Meeting held with Captain Wilson. Submittals to be returned with changes as required.
10/25/23 – No update.
12/07/23 – No update.
02/29/24 – Kick off to be scheduled close to delivery.
03/28/24 – Triton asked question. Site visit to confirm to be scheduled for next week.
04/25/24 – Waiting on sheriffs to answer keying questions.
05/30/24 – Questions sent to Triton. Triton has not responded.
06/27/24 – New project manager assigned to project. Doors to ordered in near future.
02/27/25 – Doors are ordered and scheduled for delivery the last week of April.
03/27/25 – No update.
04/24/25 – Mobilization scheduled for early May.
05/29/25 – Delivery was delayed. mobilization scheduled for mid June.
06/26/25 – Mobilization scheduled for Monday.
07/31/25 – Frames came in with incorrect dimensions. They will all be modified by Triton and remobilized in a couple weeks.
08/28/25 – Modified frames were manufactured for thicker wall dimension. Triton to provide correct frames as soon as possible.
09/25/25 – Corrected frames will arrive with Cornerstones delivery.
10/30/25 – Frames to be delivered monday. Triton to mobilize and complete their scope.
12/11/25 – Triton discovered that the doors were the wrong thickness. Cornerstone doors can be used to cover all but one of their doors. The one door has been ordered and will be delivered shortly.
01/28/26 – Door delivery date has been pushed back. Work has been paused.
02/26/26 – Door still not delivered. Door suppossedly will be delivered tomorrow. two more doors in this project once the door delivered is completed.
03/26/26 – Final phase to begin next week.
04/30/26 – Frames came in the wrong size. Frames to be delivered next week. Project to be complete end of May.
05/28/26 – Cornerstone to complete final pod for Triton. 6/24 install date.
06/25/26 – Demo revealed damage to block walls. Change order accepted. Cornerstone to complete work. Mobilized this week.
07/30/26 – Work is complete. Closeouts ongoing.
08/28/26 – No Update.
09/24/26 – Change order to order new millenium pac units submitted. No update on closeouts.
JC – 2022 Cell Door Replacement (Ph 2 Triton) Read More »
PM: Bert Watts, Mike Murphy
12/06/21 – Signed SOSS received
01/26/22 – Plans and Schedule created. Will be discussed at JC Door Replacement Kickoff.
02/24/22 – Product research completed. Price Estimate in progress.
03/31/22 – Estimate and summary provided to County.
04/28/22 – Waiting on PO.
05/26/22 – Documentation in progress.
06/30/22 – Documentation in progress.
07/28/22 – Documentation in progress
08/25/22 – Documentation being finalized.
09/29/22 – Final Review to be submitted to County 9/30
10/27/22 – Some corrections submitted. Hard copies to be delivered today for sheriff review.
12/15/22 – ODRC approval. Project to go out to bid 12/22
01/26/23 – Bid opening is 1/30.
02/22/23 – Bid opening is pushed to 3/3. Final addendum to be issued before 2/28.
03/30/23 – The bid has been cancelled. An invitation for manufacturers to demo their products has been put out for 4/5.
04/05/23 – Manufacturer presentations held. Willo, Airteq, and Habersham displayed their products to the county and sheriffs.
04/27/23 – Revised bid sent to the prosecutors office for review. Once approved, the project will be ready to rebid.
05/25/23 – Project has been rebid. Pre-bid meeting is 6/2.
06/29/23 – Bids received. Project is awardable.
07/27/23 – Lowest Bidder – Jails – bid is under review with prosecutor to determine if bid is awardable. Second lowest bidder – cornerstone – vetted.
08/31/23 – PO is approved and contract has been sent. Kickoff meeting to be held in the near future.
09/28/23 – Kickoff meeting held. Site visit to measure existing conditions scheduled for week of 10/9. 4 cell mock up to be scheduled at site visit.
10/25/23 – Site visit occurred. Mock up submittal returned. Mock up installation to be scheduled in near future.
12/07/23 – Mock ups to be installed 1/9.
02/29/24 – Mock ups ran into trouble connecting with the PLC. Cornerstone could not figure it out onsite. They sent locks to be tested by Stanley. Locks have not been successfully programmed yet.
03/28/24 – Stanley determined that the locks can be used with modification to the PLC system. Cost of the upgrade is around $500,000. Conversation of next steps ongoing.
04/25/24 – Working mock-ups installed. Schedule to be determined for Securitas to be on site for upgrading power.
05/30/24 – Work to begin 6/17. Work is expected to take 2-3 weeks per floor.
06/27/24 – Locks delivery was delayed. The locks had to be re-programed. Cornerstone to overnight one re-programed lock to ensure functionality. Prep work on George 51 is complete.
07/24/24 – Matt punchlisted project last Sunday. They met the State on Monday. One door hitting the wall, so we need to add a new bumper.
08/29/24 – Installation ongoing. Cornerstone getting to a unit per 2 weeks.
10/31/24 – Installation ongoing. No issues have been resolved by airteq regarding quality control. Meeting to discuss issues with Cornerstone and Airteq will take place next week.
12/12/24 – Installation ongoing. Power upgrade is complete. Rewiring lock power is in progress. New switches to be installed at end of January.
01/30/24 – Last unit work ongoing. Cornerstone and Airteq VPs to attend a meeting in February to work out warranty issues.
02/27/25 – Meeting held with VPs of Airteq and Cornerstone to finalize warranty discussion. 5 year warranty agreed upon. Medical unit to be complete this week. outstanding work will be repairing damaged locks.
03/27/25 – All contract work complete. Closeouts to be submitted and correction work to be done.
04/24/25 – Replacement housing and attic stock to be delivered in near future. Cornerstone will begin correcting outstanding punch items.
05/29/25 – No Update.
06/26/25 – No Update.
07/31/25 – No Update.
08/28/25 – No Update.
09/25/25 – Attic stock and corrected housings delivered and replacement process has began. Closeouts outstanding.
10/30/25 – Still have a couple of things left to do. We need a list of lock boxes left to do.
12/11/25 – List of outstanding punch items provided. Closeouts under review.
01/28/26 – Punch work complete. Attic stock is outstanding. Closeout corrections requested.
02/26/26 – Closeouts will be delivered next week. Attic stock needs to be replenished from warranty work orders.
03/26/26 – Still waiting on closeout docs. Attic stock is still not on site. Warranty period has not began.
05/28/26 – No update.
06/25/26 – No update.
08/28/26 – Phillip onsite to review rust damage. Champlin to provide report.
09/24/26 – Report submitted. No update on solution.
10/29/26 – Roller bolts have been discovered missing on several doors. Sheriffs to provide report.
JC – Cell Door Lock Replacement (Cornerstone) Read More »
PM: Matt Butz, Mike Barth
08/26/21 – HCFD send signed PO and SOSS to TEI. TEI contacts HCFD PM to set up design kick off meeting, date is pending.
10/26/21 – TEI has began the design process, setting up drawings and using archive drawings to show on demolition plans. Once kickoff meeting occurs, the field verification process will occur and the project will proceed.
12/13/21 – TEI develops demolition drawings from existing building plans from archives, and conducts design kick-off meeting with HCFD and building manager. Next step is to schedule field work to document/confirm existing conditions. TEI to work with building manager on schedule.
01/25/22 – TEI fieldwork pending return of background checks for James Smiddy and Alex Woods.
02/23/22 – Background checks returned and employees badges approved. TEI and HCFD to schedule the field work with building managers.
04/27/22 – TEI hires MobilComm to provide survey of signal strength for FF radios (per CFD requirements). Upon receipt of report from MobilComm, recommendations for BDA may be included in design specifications. TEI fieldwork complete. Existing conditions documented and moving forward with new work drawings.
05/26/22 – MobilComm reports back that the building has a non compliant system. New BDA system will be installed. TEI Meeting with Fire Marshall on 06/07/22 with 90% complete documents for review/input.
06/28/22 – Project deign near complete – Pending Barth review, documents will be sent to HCFD Week of 07/04/22 for review and comments. ITB will be issued upon receipt of review comments.
07/27/22 – TEI sends drawings to Hamilton County facilities for review. Upon receipt of review comments, the package will be issued for bidding.
08/24/22 – Project being sent to purchasing on 08/26/22 for bidding. Available to bidders on 08/30/22. Prebid scheduled for 09/14/22 and bid opening scheduled for 09/28/22. ITB # 075-22.
09/26/22 – Project out for bids. Bids open 09/28/22.
10/26/22 – Bids received and opened. DK apparent low bidder. JCI/Simplex vender in bid. TEI vets bid and makes recommendation for award. Project to commence upon contract approval and PO to DK.
12/15/22 – DK signs and returns contract to HCFD. Once PO is issued, pre-construction meeting to be scheduled.
01/25/23 – DK receives approved contract and PO. HCFD and TEI working to schedule preconstruction meeting to kick off the construction.
02/23/23 – Pre construction meeting completed. JCI developing submittal documents.
03/29/23 – TEI speaks with JCI about status of Submittal Package. JCI states that the submittals are tracking about 2-3 weeks behind the 800 Broadway submittals (anticipated receipt of submittals = late April to Mid-May).
04/27/23 – JCI indicates that the submittals for the JC shall be sent to DK by mid May. Still tracking same as indicated last month. TEI to review and turn around upon receipt of submittals.
05/23/23 – JCI indicated that the submittals will be sent to DK this week. DK has not received to date.
06/28/23 – DK has not sent submittals to TEI for review to date. Submittals will be reviewed by TEI upon receipt.
07/26/23 – TEI receives submittals for project. Reviewing and will return. Pre construction meeting (along with 800) is scheduled for 7/28.
08/24/23 – TEI, HCFD and DK meet (at 800) to discuss project. work in JC to mobilize late Q1/early Q2 of 2024. Matt Butz asks about the BDA equipment at the JC, and how quickly it can be installed (issues with the existing system). TEI reaches out to DK to request data about schedule.
09/26/23 – TEI reaches out to DK for CO cost to install the ERRS (BDA) ASAP versus waiting until the new JCI system is in the building. MobilCOMM states no issues with the plan. DK sending electrician to site to confirm existing system is compatible and will issue CO accordingly. TEI stresses with Gleason that time is of the essence.
10/26/23 – MobilCOMM has ordered to BDA for the JC and will schedule the installation upon receipt of the equipment. DK still on schedule to mobilize as previously identified.
12/06/23 – TEI asks DK to find status of BDA – should be at MobilCom per previous schedule. TEI will follow up with DK.
01/30/24 – Installation of BDA pending the background checks from MobileComm
02/28/24 – MobileCOMM cleared to work in building. TEI contacts DK and tells them that the install must be scheduled and we need to have install date by beginning of February partner meeting.
03/27/24 – MobilComm and DK to mobilize 4/1/24 to install and get the BDA installed ASAP.
04/24/24 – Work has began on the BDA upgrades, most work in basement complete and 1st floor is next. All areas with minimal/no coverage were addressed first.
05/29/24 – BDA installed and turned on in the lower levels of both buildings. Finalizing the install of the BDA in the next week or two. Started the install of the backbone for the JCI fire alarm system.
06/26/24 – BDA installed and complete. DK and Biederman working out PO issues to get permitted. Panels installed and backbone conduits being routed through the building. DK facing additional staffing issues.
07/24/24 – Staffing issues continue. Permits for BDA applied for – pending City approval. Work continues on backbone. DK developing means and methods and durations of timing needed in all inmate areas to coordinate with HCSO. JCI finalizing CO pricing for deluge system, but Jay at JCI tells TEI that the relays needed for the CO are currently on backorder and the scheduled ship date is 01/31/2038 (and this is NOT a typo!). TEI states this is NOT acceptable!
08/28/24 – Project in construction. Permits for BDA obtained, inspections completed (passed) and MobilComm to send approval paperwork to HamCo once received.
09/25/24 – Construction progressing in the building.
10/30/24 – Construction progressing in the building following behind the cell lock project.
12/11/24 – DK indicates that the backbone installation is nearly complete and that they will need to have JCI and Notifier at the next const meeting (01/08/25) for coordination of cross trip.
01/29/25 – Cross trip installed and working. DK to have JCI at next project meeting to review schedule and Deluge system (controlled on all floors).
02/26/25 – JCI, HCFD, and TEI meet to discuss deluge system on site. TEI sent JCI record dwgs of sprinkler system in building. Construction on-going.
03/26/25 – JCI has all parts for Deluge upgrade to DK. The Deluge upgrade to begin early April.
04/23/25 – Deluge work has started. Working in unit 1 of north tower, all floors. Then Unit 2 North, and so on.
05/28/25 – Side 2 of the north building to be completed in the next 2 weeks.
06/25/25 – Issues with the Deluge valves and water leaks. TTC attends FA meeting and evaluates the valves and to send in recommendations.
07/30/25 – Construction on the project progressing with availability of spaces. DEG submits memo with recommendations.
07/31/25 – TTC issued memo on the deluge valve issue in the North building. We will talk more about this after the meeting today.
08/27/25 – Construction progressing. Moving to south tower beginning of September.
09/24/25 – Construction progress continues. DK following the other projects as pods are made available.
10/29/25 – Construction progress ongoing. Anticipated completion April/May of 2026
12/10/25 – Construction progress ongoing. Change order issued at the OEC meeting today. JCI finalizing engineering change for the building department.
01/28/26 – All work (original Scope) in North tower near complete. JCI to submit documents to city by end of Janaury. Project ongoing. Anticipated completion Late April/Early May 2026.
02/25/26 – Project ongoing. Deluge work is being completed this week and next.
03/25/26 – Project ongoing.
04/29/26 – Pretest completed on 04/28 throughout both buildings. Consult with inspector to be scheduled to outline inspection process.
07/29/26 – 2 months of inspections completed and the CFD and CBD have approved all of the installations. DEG has assembled the punchlist for the project and issued to the EC. Most items were discussed at time of inspection and punchlist walk – and we anticipate that they have been completed. Training for building staff was 07/28/26.
07/30/26 – Electric issues at panel and distribution at fire pit shorted out. Wire ran in lighting conduit and DK has to do an emergency repair for the job. MB to investigate and report back.
08/26/26 – Project complete pending final IBI and Elevator inspections for JCI to sign off on permit. Scheduled for Week of 08/31. Closeouts requested from DK.
09/23/26 – All inspections except IBI complete. IBI pending renewal paperwork. Project pending final closeout.
10/28/26 – IBI final inspection passed and complete. Project pending closeout documents.
JC – Fire Alarm System Upgrades Read More »