Hamilton County Facilities

JC – Loading Dock Upgrade

PM: John Nester, John Millar,
07/29/21 – Creating SOSS.
08/03/21 – SOSS submitted to Hamilton County for review.
08/09/21 – Hamilton County accepted SOSS.
08/25/21 – THP met at Justice Center with John Nester (Hamilton County) and Mike Barth (Thermal Tech Engineering.
08/25/21 – THP met at Justice Center with John Nester (Hamilton County) and Mike Barth (Thermal Tech Engineering) to review project and begin putting bidding documents together.
9/16/21 – THP sends project manual and drawings to Hamilton County for review. THP revises bidding documents based on County review and sends bidding documents to Triton, KFI, and Schrudde-Zimmerman.
9/22/21 – KFI notifies THP they will not be bidding on the project. THP sends bidding documents to Diversified Facility Solutions and Leo Brielmaier.
9/27/21 – THP holds pre-bid meeting at HC Justice Center. Triton and Leo Brielmaier are the only contractors to attend.
10/5/21 – THP issues addendum No. 1
10/11/21 – Bid due date. THP receives only one bid from Triton.
10/14/21 – THP calls Triton to discuss/review bid.
10/15/21 – THP sends Hamilton County bid review/award recommendation letter for Triton.
11/15/21 – Signed contract and PO issued. Triton to have contractors receive background checks as needed and start submittal process. Pre-construction meeting and NTP to follow in near future.
2/23/22 – Waiting for lead time on new loading dock. Will schedule Pre-Con meeting with Hamilton County and Triton when we have updated lead time/schedule.
3/16/22 – Triton informs Hamilton County and THP that the loading dock lift supplier has received the new lift.
3/14/22 and 3/30/22 – Hamilton County and THP has reached out to Thermal Tech for review of the submittal and to see if an electrical permit is necessary for this project. No response from Thermal Tech.
3/30/22 – Need to confirm with John Nester, Hamilton County the time frame for the project and schedule a pre-construction meeting.
4/20/22 – Triton submitted site specific safety plan.
4/27/22 – Thermal Tech reviewing electrical permit needs of the lift.
6/30/22 – Thermal Tech reviewed the electrical connection and no permit is needed. Contractor working on background checks.
5/26/22 – Thermal Tech reviewed submittal and confirmed a new electrical permit is not required.
06/10/22 – Finalizing and confirming background checks have been performed for necessary crew members for Triton and Sub-Contractors.
07/26/22 – Pre-Construction Meeting has been scheduled for August 2.
08/02/22 – Pre-Construction Meeting at Justice Center with Hamilton County, Sheriffs Department, Thermal Tech, and Triton.
08/10/22 – Field site visit with Triton and sub-contractors.
08/25/22 – Work is scheduled to be performed overnight. Expected to be completed in 1-night.
08/25/22 – New loading dock lift was installed on 08/25/22.
08/26/22 – THP and John Nester visited the site. THP sent field report to Triton for punch list items.
08/30/22 – Issue with loading dock motor. Motor has seized up/burned up. Triton to coordinate with Equipment Depot to get new motor and fix the issue.
09/15/22 – Repairs to the loading dock lift are completed and it is up and running.
09/19/22 – Sheriffs Department informed THP and John Nester that a sizable gap exists between the loading dock edge and the platform edge. THP notified Triton and Triton is working on getting Equipment Depot back on site to review the issue and complete the punch list items.
09/30/22 – The sizable gap between the loading dock edge and the platform edge has been corrected and the other punch list items have been completed.
10/13/22 – Triton, Hamilton County, and THP met onsite to review the loading dock lift and completion of punch list items. Equipment Depot to complete paint touch ups on a final follow up visit.
10/21/22 – Triton working on finalized pay app and all required documents for project closeout.
12/07/22 – Required close out paperwork and final pay app submitted to Hamilton County.

Scroll to Top