TPC – Air Compressor Upgrade

PM: Terry Cannon, John Nester
07/29/21 – Remaining air compressor items after Ameresco work is complete. Is there any way to convert the final remaining devices to electronic? TTC to check on smoke purge control with fire alarm
08/26/21 – Met with Ameresco on scoping remaining pneumatic devices 3 times in the last two weeks. FA testing at Admin on Thursday night to verify existing sequences but the latest thought is that we will have to keep a pneumatic air compressor at the building. We will put a small project bid together for that work and get that out for bid ASAP.
10/19/21 – Final bids were submitted. ThermalTech created a bid tab and sent to the County.
10/22/21 – Talked to Bert about updated bid tabulation and waiting for final approval to move forward.
12/13/21 – Spoke to all vendors about the job and to be ready to start this job as soon as the Admin Fire Alarm.  We are set to begin this project and can schedule a kickoff with the county as soon as convenient.
01/25/22- Construction Work is scheduled to begin late February or early March. We are asking for submittals now.
02/24/22 – Submittals are in, will start right after Fire Alarm.
03/31/22 – Admin FA testing happening now, this project will be started after the FA is approved in April.
04/28/22 – Final FA test was completed and final meeting is coming up soon. TTC to send controls submittals back to Emcor ASAP. JCI submittal not received yet. This project is ready to get going in earnest.
05/25/22 – TTC needs to finish submittals and get Emcor scheduled for the next phase, will move this up to the front burner.
06/30/22 – Submittals are partially reviewed. TTC will setup kickoff meeting with Brian & Katie first week of July.
07/27/22 – The Pre-Const meeting was help with DK and a project schedule was submitted for work to begin in August through October. TEI starting to schedule contractors and vendors for a November final test.
08/09/22- Const Mtg #2 held with contractors. Things are going well DK is on schedule. We addressed several questions after the meeting on the walk through. TTE to work on FA final inspection schedule at end of job. EF-1,3,4,6, SF-8 complete.
08/23/22 – Const Mtg #3 and things are going even better. No major questions. EF-6,10,7, SF-1 Penthouse UH complete. Programming being updated as equipment is brought online. Graphics and controls look good.
09/22/22 – Const Mtgs continue, the job is about half done. DK is on schedule and continues converting pneumatic devices in the building. We have decided to submit a permit for this work and have it tested wit the city one final time. November 10 & 12.
10/26/22 – The project is complete from the DK scope. Pretesting went well and after some programming updates by Emcor during pretesting, the system is probably ready to test with the City. We spoke to Ameresco trying to use their existing permit to retest the system but that permit is closed. We will need to submit a new permit to the city.
12/15/22 – Work is complete, functional testing is complete, all systems are online and ready to go. AC has been turned off. TTC to issues cleanup punchlist to Debra. Project ready to start closeout.
01/24/23 – Work is complete and we talked to DK about cleaning up the rest of the job. AHU-1E is experiencing some issues probably note related to this job but also some issue that are related to this job. Two pneumatic dampers were found that need to be upgraded, but these dampers are already scheduled for demo in the Auto Title project so we instructed DK to lock them open and we have turned off the Air Compressor. Closeout documents started on this job.
02/21/23 – Project is complete, no closeout documents yet.
04/26/23 – Closeout documents requested.
06/28/23 – TTC will check with Steve on closeout documents.