PM: John Nester, Terry Cannon
02/23/23 – All fieldwork is complete. TTE writing report now and creating cost estimates.
03/29/23 – Report is complete and in for final review with TTC.
04/25/23 – Report sent back as not complete, need pricing and scope updates.
05/21/23 – Phasing drawings completed. Cost estimated updated, final report updated for review. It shoudl be ready by Thursday meeting.
06/28/23 – New version ready to send in for review. This version has the cost estimate, sanitary repairs and drawings included.
07/26/23 – Report is done and priced up. Need to give Facilities the report, drawings and appendices on a thumb drive.
08/29/23 – Coty updated the report this week and cost in the 2024 adn the report were reconciled to some extent. TTC needs to spend time finalizing this work.
09/27/23 – Report is complete, cost estimate is done. I hope to send to JN before the meeting.
10/25/23 – Report is complete, still owe John a final copy.
12/06/23 – OMG I can’t believe this has not been sent to John yet. I HAVE to get this by end of year.