Hamilton County Facilities

THP 2023 General Services (F069)

11/09/22 – Hamilton County requested SOSS.
11/21/22 – THP provide SOSS for review.
12/12/22 – Hamilton County approved SOSS.
12/29/30 – THP coordinated Courthouse stone knock downs and surveyed southeast corner of the building.
12/30/22 – THP supported Champlin with 2020 Auburn flooring repairs.
01/06/23 – THP and AFR completed knock down work at Courthouse.
01/26/23 – THP updated project status work and attended monthly mtg.
02/23/23 – THP updated project status work and attended monthly mtg.
03/14/23 – THP attend WBE/MBE training meeting for Partners.
03/30/23 – During March, THP hired and coordinated special inspection work for 800 Broadway concrete pour.
04/26/23 – Railing redesign work for 800 Broadway work concrete platform and bulletin was completed.