PM: Matt Butz, Sam Hofmann
02/22/23 – SOSS received. Kickoff to be scheduled soon.
03/28/23 – Kickoff held on site. design in progress.
04/27/23 – Overhead doors have been on site to assist with design. Bifold doors to be replaced with new bifold doors. Research needed for physical barrier to stop trucks from hitting garage doors.
05/25/23 – Two bifold door manufacturers are working on quotes. One has been out to site. Drawings in progress.
06/29/23 – Still have not received a quote. Followed up with manufacturers. Drawings in progress.
07/27/23 – Drawings can be complete by end of August.
08/31/23 – Drawings in progress. Nearly complete.
09/28/23 – Project will be out to bid 10/10.
10/25/23 – Project is put on pause until budget information is worked out.
12/07/23 – No update
02/29/24 – Submitted to ODRC for approval.
03/28/24 – State approval received. Final review set to be submitted 4/5.
04/25/24 – Request from the state requires additional design and funding. Waiting for further direction.
05/30/24 – No update.
06/27/24 – State approved the sally port door installation without the mini PLC system. Project to be bid out in near future.
07/25/24 – Project is out to Bid. Pre-bid scheduled for 7/30.
08/29/24 – Bids came in awardable. Robert Bell to review acceptable bids. Bid vet to be scheduled pending ok from Robert.
09/26/24 – Project in contract phase.
10/31/24 – Project still in contract phase. Preliminary site visit held for measurements.
01/30/24 – Submittals returned. Change order to receive hydraulic four-fold doors instead of electrical doors incoming. Kickoff to be scheduled closer to delivery of doors.
02/27/25 – Submittals returned. All doors by 4-fold are ordered and being delivered end of march. Change order #2 approved. Resubmittal for 4-fold door outstanding.
03/27/25 – All doors ordered. Alpha has mobilized to begin electrical work.
04/24/25 – Grant extension was approved. High-speed doors have been installed. North Sallyport doors are next. Trash compactor door has been added to the scope.
05/29/25 – Issue related to door and barrier arm connection has been solved. Overhead door to correct the issue next week. Bifold doors and trash compactor door to be delivered next week.
06/26/25 – North building complete. Change order to paint existing frames approved. Trash compactor door installation ongoing. Bi-fold door control units were delayed. installation to being next week.
07/31/25 – Doors punched yesterday. Multiple change orders requested on small items. Change order frame painting still outstanding.
09/25/25 – Pricing for various items still outstanding. Multiple issues with doors over the last month. Back punch to be scheduled.
10/30/25 – Back punch has yet to occur. Multiple failures this month have been recorded. Closeouts outstanding.
12/11/25 – Change order work outstanding. Meeting with Alpha and Overhead Doors to address continual failure of doors.
02/26/26 – Closeouts outstanding. Doors still having issues.
03/26/26 – No update.
04/30/26 – No update.
06/25/26 – Final closeout review complete. Pay app deadline of this friday.
07/30/26 – Closeouts delivered to County.