Hamilton County Facilities

JC – Selective Cell Door Replacement 2023 (Ph 3 Cornerstone)

PM: Matt Butz, Sam Hofmann
02/22/23 – SOSS received. Kickoff to be scheduled soon.
03/30/23 – Kickoff held on site. Sheriffs chose 7 doors for base bid and another 4 as an alternate. They will provide a few more doors to be added into the scope as alternates.
04/27/23 – Still waiting on additional doors from sheriffs.
05/25/23 – No update.
06/29/23 – List of doors and alternates has been provided. Drawings can be complete by end of month.
07/27/23 – Drawings will be complete by end of August.
08/31/23 – Drawings will be complete by end of September.
09/28/23 – Meeting held with Captain Wilson to confirm scope. Project will be out to bid 10/10.
10/25/23 – Project is out to bid.
12/07/23 – Bids returned. Cornerstone is lowest bidder. Bid review meeting held 12/5. Project now in contract phase.
02/29/24 – Cornerstone to send submittals in near future.
03/28/24 – Still waiting on submittals from Cornerstone.
04/25/24 – No Update.
05/30/24 – Submittals received and returned.
06/27/24 – Cornerstone field verification completed this week. Doors to be ordered.
08/29/24 – No Update.
09/26/24 – Cornerstone placed order. Pre-con meeting to be scheduled in near future.
10/31/24 – No Update.
12/12/24 – Cornerstone has material in hand. Coordinating best time with sheriffs and ongoing lock project work.
01/30/25 – Work to be scheduled in line with lock project corrections.
02/27/25 – No update.
03/27/25 – No Update.
04/24/25 – First Pod began. All frames installed but doors did not fit. New doors shipped immediately to finish the first pod. The rest of the doors will ship end of May.
05/29/25 – Pod complete and back punched. Next pod to begin next week.
06/26/25 – Next phase punch scheduled for tomorrow. Final phase to begin in 3 weeks.
07/31/25 – Next set of frames and Phase 4 frames to be manufactured together. 12 week lead time for delivery.
08/28/25 – Frames to be delivered mid september.
09/25/25 – Frames will be delivered next week.
10/30/25 – Cornerstone to remobilize monday.
12/11/25 – Phase 2, 3 and 4 have effectively merged into one project. All material is on site. Scope has been scheduled per unit with phase 2 and 4.
01/28/26 – Work Complete. Closeouts outstanding.
02/26/26 – No update.
03/26/26 – No update.
04/30/26 – No update.
05/28/26 – No update.
06/25/26 – No update.
07/30/26 – Closeouts reviewed and missing items requested.
08/28/26 – No update.
09/24/26 – No update.
10/29/26 – No update.