Hamilton County Facilities

JC – 2021 Cell Door Replacement (Ph 1)

PM: Matt Butz, Sam Hofmann
02/22/21 – Received approved SOSS. waiting for more information to proceed with design.
03/18/21 – Design Kick-off meeting with County, Sheriffs, Champlin and ThermalTech.
03/22/21 – Site visit by Sam Hofmann and Jeff Cyrus. Further developing plans and gathering information.
04/29/21 – Several Manufacturers researched. Wrapping up DD set for review.
05/21/21 – User meeting to finalize scope. Shereen provided existing building door details for coordination purposes.
06/08/21 – Updated plans sent to manufacturers for pricing. still waiting on Door and frame prices. Requested county to investigate existing hardware.
06/15/21 – Received information on low voltage locks. still waiting on information on high voltage locks.
07/14/21 – Champlin identified current contractor in building and requested updated specs and estimates.
08/25/21 – Final meeting held. scheduled to go out to bid on 9/2
09/02/21 – Bid issued
09/23/21 – Bid opening. Triton is apparent low bidder.
10/15/21 – Zoom meeting with Triton, Champlin, and Thermaltech. Letter of Recommendation sent to County.
12/09/21 – Contract and PO Issued. Permit filed.
01/26/22 – Construction kickoff meeting scheduled for 2/7.
02/24/22 – Submittals starting to be received. Progress meetings will start in June when construction starts.
03/31/22 – CA ongoing.
04/28/22 – CA ongoing. Information required from the sheriffs in order for Triton to order locksets. phone call with vendor confirmed the information is in the sheriffs possession. Our attempts to contact Sheriff have not been successful.
05/26/22 – Information from Sheriffs received. Submittals returned. Triton to provide a construction schedule when determined.
06/30/22 – Submittals resubmitted and returned. Triton to provide schedule when materials are ordered.
07/28/22 – Triton selected new Project Manager. Jeff W to provide update.
08/25/22 – Final submittals returned. project kick off to be scheduled.
09/29/22 – Kick off to be scheduled in near future.
10/27/22 – Update from Triton puts project start in late January.
12/15/22 – No update.
01/26/23 – Project on schedule to start in February.
02/22/23 – Update from Triton stated doors wont be delivered until end of March
03/30/23 – Triton mobilized on site. Jails delayed some materials but shouldn’t impact schedule.
04/27/23 – Phase 1 and 2 to be complete by 4/29.
05/25/23 – Phase 1 and 2 complete. Phase 3 ongoing.
06/29/23 – Phase 3 and 4 complete. Final phase to begin next week.
07/27/23 – All doors installed. Punchlist items outstanding.
08/31/23 – Backpunch returned to Triton for final touch ups.
09/28/23 – Project complete. Triton to provide closeouts.
10/25/23 – No Update.
12/07/23 – No Update.
02/29/24 – No Update.
03/28/24 – No Update.
04/25/24 – No Update.
05/30/24 – No Update.
06/27/24 – Closeouts received. Need to be reviewed.
09/26/24 – Sam to continue closeout paperwork reviews.
12/12/24 – No update
01/30/24 – Triton and County held meeting to review all outstanding documents needed.
03/27/25 – Closeouts received.
05/29/25 – Final payment released. OK to Archive this project.