Hamilton County Facilities

CH – Server Room Construction

PM: Matt Butz, Terry Cannon

01/06/21 – Foundation submittals arrived and was approved by THP.
01/26/21 – Graybach is ramping up the start of the project again shooting for a 2/15 restart date. The schedule is being updated for this start date. We will start sending out weekly updates on background checks and project updates this week. More steel submittals have been submitted and returned and we are currently finalizing and coordinating efforts with all the sub-contracts on status of equipment approvals from last year. A couple of RFI have been submitted, answered and returned for the GC.
02/02/21 – Change Order #2 arrived. Very large change order, TEI requested additional backup to this change order before taking it to the County. On 2/10reached out to Graybach for additional information and further breakdown on Subs costs for this CO.
02/03/21 – Updated LEADS list arrives, only one Graybach employee aprp2/10 – Permits approved for Building and HVAC work. Paid for and picked up by Graybach. Skip Zimmer is our inspector for this job.
02/06/21 – Three sets of questions/suggestions have been sent in on the steel submittals have been sent it and THP has been reviewing and answering. Everything has been approved except for the weight of the hatch. The county asked that the hatch weight 50 lbs or less and the submittal has them at 92 lbs, we continue to work with Graybach and their sub for an acceptable weight. As of 2/17 we do not have the final solution and they believe there is a cost impact to that solution when we make the change.
02/10/21 – Graybach making headway on badging. One superintendent, Nick Neyer, approved. He will be ready to go on March 1. Several other people have been. Graybach requested we setup Pre Const Mtg #2. Send me good days this week for that meeting please. Barth and I can do Tuesday afternoon, Wednesday morning, Friday all day.
02/16/21 – Concrete mix submittal arrived and uploaded to Procore.
02/17/21 – Rebar submittals returned. Fall arrest submittal submitted, uploaded to Procore on 2/22.
02/19/21 – Safety guide submitted arrived, forwarded on 2/22.
02/22/21 – Background check update worksheet attached.
02/24/21 – Pre Const Mtg held. Graybach furnished SOV and Project Schedule for final review. TTC to distribute meeting notes and changes order to the county. Graybach scheduled to start on March 8 with demo and complete the job in July 2022.
03/09/21 – Const Mtg #1 held. Graybach started its own Procore site for this project. Room 263 scope discussed and reviewed with Graybach. Ceiling heights were discussed in regards to the HVAC and Fire devices.
03/16/21 – Const Mtg #2 held. Parking lot spacing and usage discussed. RFI submitted to Procore site. Hallway door options discussed, project schedule closer to final, change order #2 and #4 were discussed and submitted for consideration.
03/23/21 – Const Mtg #3 held. Project schedule submitted, follow-up afterwords targetted dates for site work and eventual server room work. TTE reviewing material change order cost from 2021 means. Geiler, Graybach, County, ThermalTech to have a conference call on upcharge for Liebert units. TTE working on Rack options for the job to discuss with CMS and Facilities. Data cable and server racks to be purchased by owner, fiber provided by DK, HC telecom providing data and phone in Room 263.
04/29/21 – Weekly Const mtgs underway. Room 263 progressing, studs are up, rough-in inspection is complete, HVAC and electrical work is started. In the Courtyard the concreate has been poured and THP has checked on progress. Terracon has been on site for special inspections. The grade beams and column bases are in place and getting wet today. Additional meetings for finalizing racks, discussing change orders and coordinating with CMSNet.
05/27/21 – Room #263 work continues for mid-June move in date. GBBN punchlist 5/28, TEI punchlist 6/4.
05/28/21 – GBBN punchlist distributed to contractors. Spencer’s last day on the project.
06/04/21 – ThermalTech punchlist visit complete and distributed.
06/08/21 – Met on Platform questions and generator placement.
06/09/21 – Met Kohler on-site for generator placement questions and code requirements.
06/17/21 – Prosecutor moves into Room #263.
06/22/21 – Met with Fire Marshal on generator placement, code questions and CFD requirements. ThermalTech summarizes meeting notes for CFD, following up on additional research for generator needs.
06/24/21 – Created bollards drawings, sent to Graybach for pricing.
06/25/21 – Discussed resolving the CFD and BPS issues on the generator and platform placement work and needs. Steering committee meeting when very well. FM-200 safety characteristics passed along to committee. If the generator fits on the existing platform and can be five feet from the wall, that is preferred. Add bollards around the platform okay, adding paint for fire proofing on structure okay too, THP to get more info for TEI.
07/06/21 – Const Mtg. Progess continues. We are working on change order items and starting server room demo.
07/13/22 – Const Mtg. Server room demolition continues. Questions from GC, controls and fire protection.
07/20/21 – Const Mtg move to 7/22.
07/22/21 – Full Const Mtg with all subs. We are working on plumbing pan, fire protection coordination, mechanical layout, window removals, schedule, demo and HVAC controls. Server room demo well underway. Work in CMS spaces making good progress and new walls and wall openings are looking good. Follow up meeting with County on reclaiming the HVAC shaft into an electrical room was held. COR sent to Graybach for pricing.
07/28/21 – No const mtg this week. CFD emails resent and permit drawings were sent directly to fire department per their request.
08/24/21 – Weekly Const Mtgs continue. First floor mechanical and fire work continue. Coredrills plans for this week. Patching continues and painting to start next week. The schedule is becoming clearer for Server Room work but we need a decision on the generator placement. Pipe support RFI submitted for comment.
08/25/21 – CFD returned our calls and emails and agreed to our proposals on the emergency generator so we can move forward with moving the generator 5ft away from the building in all directions, no bollards, no painting and fuel oil system is okay.
08/26/21 – Material change order cost submitted for approval.
09/07/21 – Const Mtg. Generator placement and structural changes discussed.
09/14/21 – Const Mtg.
09/21/21 – Const Mtg.
09/28/21 – Const Mtg. Sprinkler piping relocation requested.
10/05/21 – Const Mtg. Condensing units set on platform.
10/12/21 – Const Mtg. Battery charging question.
10/19/21 – Const Mtg. Condensing Unit placement, disconnect locations discussion.
10/26/21 – Const Mtg. Condensing unit orientation, disconnect location picked, generator steel rework finalized. Fuel oil routing discussed. RFIs for electrical (Clean agent panel power and Fiber optic cable selection ) responded to in Procor. Projected date to set the Egen on platform is 11-11.
11/02/21 – Const mtg discussed project updates, fire protection changes for hot aisle design and generator controls meeting.  Working with CDW on Rack order.
11/09/21 – Const Mtg. JCI submitted revised hot aisle fire protection drawing.  TEI approved.  Fiber rating and telecomm wiring discussed.  Generator lift scheduled for 11/11.  DK to complete steel modifications prior to setting the generator.
11/11/21 – Const Mtg. Generator lift schedule in Courtyard.  TEI on-site and logged with pictures and video.  The generator was set without incidence.
11/16/21 – Const Mtg. Discussed next stages of work including CO for armored cable, server rack selections, fiber cable requirements, fuel oil excavation and generator control.
11/23/21 – Const Mtg. Graybach working on updating change orders from the previous PM.  TTC and Reid meeting on CO status. Final fuel oil line coordination discussed.  We confirmed the racks would arrive unassembled to the job site.
11/30/21 – Const Mtg. COR 21, 22 sent in by Graybach this week.
12/04/21 – Fuel oil excavation begins in Courtyard, Geiler working weekends and late nights.  Geiler hit several underground conditions while digging the trench for the fuel oil pipe but in the end the line is in adn it was pressure tested adn held for days.  Geiler backfill adn cover the pipe.  Plates cover the trench.
12/07/21 – Const Mtg.  Fuel Oil line pipe is underground Reviewed Generator controls sequences.  Fuel Oil valves provided by TEI to Geiler for official submittal from WC Storey.  Blacktop and sealing later this week.  Under platform to be turned over to DK next week.
12/09/21 – Several options for temporary boiler power submitted to county for approval by MCB.  TTC and Matt review and comment.  TTC working with Ameresco and feasibility to use new JC steam boilers ahead by Jan 17 to carry the load temporarily.
12/12/21 – TTC working with Bert and Matt on potentially changing the number of server racks purchased and sending out surveys to departments that are interesting in coming over to the new server room.  TTC latest density calculations show that we have plenty of spare capacity even if we reduce the number of server racks in the server room to 22 total racks instead of 24.  Physically this appears to fit better in the space with the latest equipment layout.  TTC to follow up with CDWG.
01/25/22 – Flooring work mostly complete. Generator controls and sequences worked out with Buckeye, testing of the generator tanks can begin. Final piping and fuel oil ties can be scheduled. Electrical outage and temporary power plan in place for Feb 5, 12. Geiler will be back for Gen exhaust and venting work. 9 server racks have arrived and are at the DK warehouse. The CH Server Survey has been sent for distribution.
02/24/22 – Met Fire Marshal on site and got approval for generator and fuel oil installation from CFD. Generator tanks have been tested and passed, exhaust and venting work completed, cable trays are being installed in the room now. Electric work continues, power outages complete, temporary connections made, Server Racks on on site, floor waxing tentatively scheduled for early March, and Server survey came back from CMS yesterday.
03/31/22 – All racks are in the room. Power being pulled to room this weekend. HP was onsite and assembled half the units. HAC coming soon, RFI for new duct size opened. Rack Survey being converted to rack loading. CMS gets 6 or 7 racks in the layout. Equipment startup next week.
04/28/22 – Final electric shutdown is scheduled for this weekend. HPE was onsite to verify missing parts this week and will be back on Thursday and Friday to install accessories. Missing parts are on order (I think). Door access control and security cameras hookup was resolved and email sent. DK to test fuel oil pump system and start coordinating Al Harden field visit for final testing with Buckeye and TEI.
05/25/22 – The contractors are almost complete. Graybach has performed their punchlist review and uploaded to Procore for ThermalTech review. HPE has not given us an update on the warranty replacement parts yet so we are field changing some stuff to make this work out for us when the parts arrive. The Clean Agent system is live and all water removed from the room. Door access and security cameras are on. The facilities switch is programmed with Honeywell IP addresses, we need to get a Cat6 cable pulled from 2 to 5 for Honeywell to communicate. Randy will be back June 6 week to finish up. Liebert startup is being scheduled. Internal fuel oil pump testing next Tuesday with TEI then we will schedule Al Harden for final. Final department survey due from TTC to County. Rack switches were not included in our budget. We should setup a design meeting with CMS about final configuration details in the next couple of weeks. TTC to help provide update at next steering committee meeting.
06/14/22 – Telecomm meeting about fiber interconnects was held with Mitch.
06/17/22 – TTC replaced the warranty items on the server racks and got them to a place where they all work and the HAC is contained.
06/20/22 – The Generator Load Bank testing was completed today. The second fire alarm test was conducted with unsatisfactory results. TEI trying to get contractors to rectify issues and troubleshoot the system. The remaining fuel oil pump started leaking today and was shutdown but testing continued.
06/23/22 – Bert asked about the condenser coil cleaner and protecting the refgrigerant lines.
06/29/22 – A change order meeting was held with the county today to review the cost submitted with change order COR4 for the job. The contractors provide cost and hour backup for their change order COR-4. We reviewed with County.
06/30/22 – Graybach punchlist items are starting to be completed. TEI needs to issue its punchlist this week.
07/27/22 – This month the Facility Switch was installed and Honeywell setup communication was started. The fiber connections are in. The HAC are finished. The fuel oil containment pipe is installed but no terminated. The final generator test is being scheduled for early August. IBI permit for modified grounding is approved and was paid for on 7/26. JCI submitted revised change order for fire alarm devices in the Server Room, DK and Graybach to fully submit.
07/29/22 – IBI Grounding permit was approved today. Information sent to contractors.
08/11/22 – Generator Testing passed city inspection. We still need to connect fuel oil drain line to county detection system.
08/22/22 – We have been working on final change order cost all week adn finalized remaining change orders with Graybach. Sent to County for review.
08/23/22 – Attended change order meeting with Graybach and DK and resolved final change orders with contractors. Worked on finalizing and inspection schedule to wrap this project up with the city and contractors and turn over to the city.
08/26/22 – All inspections to be complete by 9/15/22. Schedule backup testing for the generator.
09/10/22 – Final electric testing scheduled. Kirk key operation tested. All test passed.
09/21/22 – Fire Alarm pretest scheduled with JCI & Dk. Discrepancies found and rectified.
09/22/22 – Fire Alarm and General Const final fire alarm test scheduled in the evening. Final inspections passed.
09/23/22 – Final change orders being collected. Next payapp reviewed.
09/25/22 – CRAC training scheduled for 10/6 with County & ThermalTech.
09/10/22 – Final electric testings for backup power sources. Test passed.
09/20/22 – Final Fire Alarm & General Const inspection. Inspection passed.
09/29/22 – TTC to check on parking lot spaces, coordinate with Tony, Rycca, Matt.
10/26/22 – Clean agent training complete, electric training complete, signs arrived, final cleanup instruction issued to Graybach. Closeout documents coming in for final approval. Floor condition needs to be addressed by Graybach for dents and paint on floor. CMSnet ready for access.
12/15/22 – Graybach says floor tiles are replaced, clean and wax scheduled for this Saturday, coordinating with Jesse on access. Met with Planning & Development, requested data from Facilities on server counts, met with CMS and Telecom on core switching and interconnection. Reviewing and approving closeout documents from Procore.
01/24/23 – Telecomm finishing their work for communications. TTC really needs to get the rest of the departments ready to start migrating to the server room by reaching out to each of the departments. I have been in contact with HP a multitude of times and been passed to two new sales reps trying to find the keys. Birdscreen in production. Labels need to be made.
02/22/23 – Closeout documents are approved, Graybach working on hard copies. Meeting on 2/27/23 for RCIC cutover.
03/30/23 – Signage on switches complete, birdscreen to meet DK on site, O&M one hard copy complete we need two more hard copies for the county, backup generator is below critical high alarm after last weekend work, firmware patch delayed for two weeks for generator comms, surveys sent out to tenants, core switch coming next week, RCIC meeting mid-April with CMS and CAGIS.
04/26/23 – Currently working on telecom communications, decommissioning the Admin 9th floor, repathing the fiber connections, survey final room tenants, applying firmware patch to generator and some controls checking on Honeywell system. We’ve met with CMS, Telecom, CAGIS and City this month several times.
05/21/23 – Several department meetings coming up next two weeks. Most departments have returned our calls and we have space for them in the server room. We are working on getting the fiber cable ran from CH to Admin right now so we can close out.
06/28/23 – This month we finalized meetings with the end users for spaces and confirmed nobody has too much equipment for the Rack they’ve been assigned. We’ve also had several meetings with Debra Kuempel on providing this fiber line but they are not doing the work nor are they giving us a cost to do the work. Our next step is to solicit a price from another vendor for this work. Both CMSnet and Telecom have communications up and running in the server and are ready to start testing communications in the room. Next month we potentially can have equipment in the room full time.
07/26/23 – Fiber meeting wtih DK scheduled for this Friday. Prices came in from Glenwood. We are working with City on their fiber prices.
08/29/23 – City prices coming Friday. Working with P&D, DDS and Risk Mgmt for move-in timelines. CMSnet is in the space and using the system. The second Liebert has been started, the temperatures have been turned down some.
09/27/23 – Risk Mgmt released to move in on their schedule. P&D scheduled to move in October 5. Met with Chris yesterday and measured his equipment and confirmed it all fits in the Rack we’ve designated for P&D. Scheduled a meeting with the Treasurer for Oct 6 for a walk through with them in the server room. All equipment appears to be running and operating properly.
10/25/23 – Room is ready for occupancy. The Emergency Power Off button was accidentally engaged this month. The room was restarted and ThermalTech created as step by step guide for a cold system restart. An alarm Lexan cover was installed by TTE to prevent another accidental EPO. Keys assemblies were removed and given to Acme to match locks and keys, no final word back form Acme yet. HPE can source new locks for about $3500 for 12 (6 front, 6 rear) locks, TTE would install these if accepted but we are hoping Acme can rekey them for cheaper. Jack Wilson at Acme is our contact. Mickey Halls at HPE is leaving the company and we have a new contact to finish the order if we go that route.
12/06/23 – Email to DK and Graybach today about the scope reduction letter. No final acceptance from DK has been forthcoming. We have shared everything the city gave me with Graybach and emailed them an update. HPE has provided the Sole Source letter for the keys. We are in the process of getting a PO for the new keys. Met with City CAGIS this week and showed them the server room specifics and access.
01/31/24 – This month P&D has moved into the server room. HCSO has moved into the Server Room and the final key order was placed and is scheduled to arrive on 3/4/24. The remote temperature sensor is not working for TE.
02/23/24 – Closeout documents updated and turned over to Matt on two USB’s.
03/22/24 – New CMSnet locks are installed on CMS racks. Keys left for CMS and marked for each rack. The new locks are individual to each rack. CAGIS is currently moving over to the server room this evening. Matt and Terry were on site while the movers were onsite. As of 11pm Telecom got communication pathways all setup. Switches are installed, servers are installed, i know telecom can ping the equipment. Just waiting for CAGIS to come back online now.
04/24/24 – Project is complete. Closeout documents are submitted. Ready to Archive.

Scroll to Top