JC – Façade Monitoring 2023 (F087)

PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/12/23 – Hamilton County approved SOSS.
08/31/23 – THP plans to complete work from October through November.
09/28/23 – Rappelling of façade scheduled for October 11th.
10/03/23 – Field survey of façade started.
10/11/23 – Rappel of façade completed.
10/26/23 – THP working on report.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update.
07/25/24 – THP completed assessment and report. No work needed. Final City report due 07/01/27 – Ready to Archive.