PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/12/23 – Hamilton County approved SOSS.
08/31/23 – THP plans to complete work from October through November.
09/06/23 – Rappelling of façades completed.
09/28/23 – THP working on report.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update
08/29/24 – No repairs needed final report due next June.