PM: John Nester, Sam Hofmann, Terry Cannon
02/27/25 – SOSS returned. Kickoff to be scheduled in near future.
03/25/25 – Preliminary HVAC and plumbing calculations started.
03/27/25 – Kick off meeting held. SD in progress.
04/24/25 – Follow up programing meeting held. SPoA is working on plans to be provided in next couple of weeks.
05/29/25 – Programming meetings in progress.
06/26/25 – Programming meetings still in progress. Finalizing schematic plan with SPoA.
07/24/25 – TTE sent SD cost for MEP work to Champlin for use on this project.
07/31/25 – Schematic design plan finalized. Site and DD developing.
08/28/25 – Last schematic meeting to be scheduled. County needs revised estimate for next steps. Keep Rycca looped in. TTE cost up near $2M so far.
09/25/25 – Estimate provided to county based on finalized SD Plans. County to determine feasibility of moving forward.
10/30/25 – Final schematic design meeting held to determine next steps with 7-9 million dollar budget gap. County to discuss with Cares to determine the minimum amount of renovation they need to use record center.
12/11/25 – Murphy met with Caroline to discuss scope and possible reductions. County to provide direction on funding of the project. No movement until budget is set.
01/28/26 – No Update.
02/26/26 – No Update.
03/26/26 – No Update.
04/30/26 – No Update. OK to Archive.