PM: Sam Hofmann, Jesse Estes
02/27/25 – SOSS returned. Kick off to be scheduled in near future.
03/27/25 – Drawings have been started. Kick off to be scheduled.
04/24/25 – Drawings in progress. To coordinate with Elevar on format.
05/29/25 – No update.
06/26/25 – Field visit to walk through all buildings to be scheduled.
07/31/25 – Field visit complete. Drawings to be finalized.
08/28/25 – Final review meeting to be scheduled.
09/25/25 – Door Hardware Consultant to visit doors on site to provide feedback and cost.
10/30/25 – Assa Abloy is working on specs and estimate.
12/11/25 – Assa abloy is finalizing scope.
01/28/26 – Finalizing cost estimate and base bid scope
02/26/26 – Completing bid set and project manual.
03/26/26 – No Update.
04/30/26 – No Update.
08/28/26 – County is cleaning paint off labels and will report back which locations will still need to be replaced.
09/24/26 – Confirmation required on labels able to be cleaned.