A&D – JFS Furniture Renovation 2020 SD
06/22/20 – Kick-off meeting. Attended by Mike and Christy from Champlin, John from THP, Mike and Terry from ThermalTech, Susan and Megan from IPM, Rycca, Bert, and JFS executive team from County.
07/09/20 – THP provided a proposal to Champlin for structural support.
08/21/20 – SOSS submitted. Waiting for authorization to proceed.
09/23/20 – SOSS Approved. Kick-off meeting attended by Christy
10/29/20 – programming received from Michael Patton. Typical cubicles were revised and sent to Rycca. Ready to present to JFS.
12/10/20 – Regular design meetings in place.
01/26/21 – TEI and IPM worked out details on walls around the fintube radiators along the outer walls.
01/27/21 – Weekly meetings on Fridays. Final programming meeting scheduled 2/5.
02/25/21 – Weekly meetings still ongoing. planning to start on the 1st and 5th floors.
03/25/21 – Ongoing weekly floor-by-floor presentations of space planning to Michael Patton.
04/29/21 – Ongoing weekly meetings. Field verification walk thru scheduled 5/3/21
05/07/21 – Final Coordination meeting with JFS
05/20/21 – Sent final misc. questions to Michael Patton.
05/21/21 – Received 4th and 5th Floor comments and revisions from JFS
06/03/21 – Field verification to determine signage scope.
06/24/21 – Rough draft of SD Set sent to Rycca for review.
06/25/21 – TEI owes Champlin a SOSS for the plumbing work. Gender-neutral question is out there too.
07/28/21 – Archibus #2106 is updated with MEFP cost and sketches for this project including plumbing updates for bad flow conditions.
07/29/21 – SD documents submitted to Rycca for JFS review. The next step will be a design review with TEI on final design decisions. THP will need to review the new layout from the load study perspective.
08/26/21 – Final Review meeting with County, Thermaltech and Champlin.
09/15/21 – Champlin provided County with updated estimate.
10/12/21 – Champlin provided County with a breakdown of door types being replaced for review.
10/28/21 – Project is complete. Ready to Archive.