Hamilton County Facilities

A&D-A

Alms & Doepke – 222
Archive

Alms & Doepke – City Knock Down (F028)

PM: Rycca Thacker, John Millar
05/06/25 – County approved SOSS.
05/23/25 – County and THP had a kick off meeting.
08/28/25 – THP anticipates sending bid documents to contractors on 8/29/25.
09/02/25 – THP issued bid documents to American Façade Restoration, Buckeye Concrete Restoration, Hardig Industrial Services, and ZSR Contracting and Restoration. Kestner was unresponsive.
09/09/25 – Site prebid meeting occurred.
09/17/25 – Bids were received from three contractors. American Façade Restoration was the low bidder.
09/19/25 – THP reviewed the proposal with American Façade Restoration.
09/22/25 – THP published the a recommendation for American Façade Restoration to complete the work for the County to review.
09/24/25 – County requested additional bidders from the Bold list be invited to bid the project.
09/25/25 – THP sent three additional requests out to BSBE and MBE firms.
10/03/25 – THP received one proposal from LRT that was $15,000 over the low bidder.
10/15/25 – County issued a PO for AFR to complete the work.
10/29/25 – AFR is working through background checks. AFR is proposing to complete the work 11/10 to 11/14. Work is weather dependent and second shift.
12/11/25- THP has completed the survey at the building and is working on providing a City report regarding the observation by next week.
01/18/26 – The report has been approved by HC and THP submitted the report to the city.
04/30/26 – OK to archive this project.

Alms & Doepke – City Knock Down (F028) Read More »

A&D – Water Heater Draft Study

PMs: Tony Matre, Terry Cannon

01/27/25 – Wireless space pressure sensors installed 1/24. Initial pressure readings indicate the water heater room is slightly negative (0-0.025 in WG) compared to both outside and the elevator machine room. The observed airflow showed consistent flow from the elevator machine room into the water heater room and from the water heater room to outside, suggesting the pressure would be elevator machine room > water heater room > outside. The observed draft on the water heater was a slight backdraft from the flue into the water heater room. The thermal camera was used to look for temperature gradients in the flue which could indicate a clog, but none were observed. ThermalTech is continuing to observe pressure readings and look for irregularities.
02/26/25 – Wireless equipment has been installed and we are monitoring the room. We have had one incident where the air seemed to be moving into the elevator room. TTC discussed with Glen cover all transfer openings and continuing to monitor for another 30 days.
03/13/25 – Covers were placed on the VAV duct and the transfer grill between the mechanical room and elevator to isolate the room from draft influences. Another test was conducted when there was little draft by opening the door to provide combustion air, but this did not fix the issue either.
03/25/25 – Draft still an issue. ThermalTech camera the flues and found them to be clear.
TTE brought in a Enervex for a third party review of the installation. They suggested extending the flues another 6ft each and thought the additional elbows added below the heaters might be a problem, they are running flue calcs for us to review.
04/23/25 – Project recommendations sent to Tony and Glenn and some additional conversation was had, but we have not been given direction to where to go next. We recommend new roof penetration and longer flue pipes to eliminate the issues.
05/28/25 – Project on hold.
06/25/25 – Waiting on County direction for next steps.
07/30/25 – Prices came back too high and too much scope. Barrett reached out to DK to realign cost and scope.
08/28/25 – Prices updated and given to Tony and Glen for next steps.
09/24/25 – Archived.

A&D – Water Heater Draft Study Read More »

A&D – Elevator System PM Agreement

PM Tony Matre, Mike Barth
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre met to establish project schedule. The project in process.
02/26/25 – No updates this month
03/26/25 – No Updates this month.
04/23/25 – Project manual near completed. XBE paperwork to be submitted for approval then ITB will be issued.
05/28/25 – No Updates

A&D – Elevator System PM Agreement Read More »

A&D – Exterior Camera Upgrades 2024

PM: Matt Butz, Mike Barth
04/24/24 =  TEI receives signed SOSS and PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations.  TEI developing drawing package.
06/26/24 – TEI hand delivers drawings for HCFD to review.
07/24/2024 – HCFD moves location of NWS to 3rd floor data room. TEI updates the drawings.
08/28/24 – Project pending installation from DK.
10/30/24 – DK installs camera.
12/11/24 – TEI issues Punchlist. DK sends signed off punchlist to HCFD and TEI. Pending Closeout.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Finalizing binders.
06/25/25 – DK, DEG and HCFD to me re final closeout
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.

A&D – Exterior Camera Upgrades 2024 Read More »

A&D – First Floor Drinking Fountains

PM: Rycca Thacker, Terry Cannon
02/01/24 – Create project for single upgrade of core area drinking fountain.
02/23/24 – Met onsite to review existing conditions. Champlin putting SOSS together for TTE to use for SOSS to county for one EWC on first floor. Build out into Security space seemed doable.
03/19/24 – SOSS submitted for approval, full scope.
03/22/24 – Fees seemed high for single drinking fountain, second SOSS submitted with reduced scope.
04/24/24 – On hold waiting on direction from County on next steps.
05/29/24 – On hold waiting on further direction from County.
06/26/24 – On hold waiting on further direction from County.
07/24/24 – On hold.
08/28/24 – On hold.
09/24/24 – On hold.
10/30/24 – On hold.
12/12/24 – On hold. Ready to archive.

A&D – First Floor Drinking Fountains Read More »

A&D – Mother’s Room Upgrades

PM: Rycca Thacker, Terry Cannon
01/22/24 – Fieldwork rechecked, owner review set by Friday.
01/31/24 – Drawings sent to Rycca for review. We will assist with permitting through the City of Cincinnati and with install as needed by Trades.
02/23/24 – County reviewing drawings.
03/22/24 – Still on hold.
04/24/24 – On hold waiting on direction from the County on next steps.
05/29/24 – On hold waiting on further direction from County.
06/26/24 – On hold waiting on further direction from County.
07/24/24 – On hold.
08/28/24 – On hold.
09/24/24 – On hold.
10/30/24 – On hold.
12/12/24 – On hold.
12/31/24 – HC said to archive this project.

A&D – Mother’s Room Upgrades Read More »

A&D – Digital Clocks

PM: Rycca, Barth
07/27/23 – County requested SOSS for this project.
08/24/23 – TEI submits SOSS.   Project pending SOSS approval.
09/26/23 – Project Pending SOSS Approval.
10/26/23 – Project pending SOSS Approval.
12/06/23 – Project pending SOSS Approval.
01/30/24 – TEI receives signed SOSS and PO.  Project proceeding with Documents.
02/24/28 – No updates on this project this month.
03/27/24 – Project waiting on direction from HCFD.
04/24/24 – Project pending direction from HCFD.
05/29/24 – No updates.
06/26/24 – No Updates.
07/24/24 – No Updates.
01/30/25 – Ok to Archive this project.

A&D – Digital Clocks Read More »

A&D – Annual Facade Monitoring 2023 (F084)

PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/06/23 – Hamilton County approved the SOSS.
08/31/23 – THP plans to complete work from October through November.
09/28/23 – Rappelling of façade scheduled for October 3rd.
10/03/23 – THP completed rappelling and façade monitoring survey.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update.
06/24/24 – Email status of report and repairs to address both City issues.
06/27/24 – Budget sent to County for City repairs.
08/29/24 – THP working on repair package for City repairs.
12/10/24 – THP closing out the project.

A&D – Annual Facade Monitoring 2023 (F084) Read More »

A&D – Chiller Room MCC Replacement

PM: Rycca Thacker, Mike Barth
03/29/23 – TEI submits SOSS for project.   Project pending Approval and PO.
03/30/23 – SOSS and PO approved, RT will send.
04/27/23 – TEI starting field work and will develop SD/Cost estimates.
05/23/23 – TEI meeting building manager and HCFD to provide field investigation.  TEI evaluates (2) options – direct MCC replacement and replacing with PDP since the motors are served with VFDs now.   TEI submits SD PDFs and costs for the work.   HCFD to provide next steps.
09/26/23 – TEI submits design drawings to HCFD for review.  TEI receives review comments.   Drawings finalized.
10/26/23 – Upon determination of XBE requirements, this project will be issued as a small projects bid.
12/06/23 – Project issued for small projects bid.   Prebid conducted and Addendum published.  Bids due to TEI on Friday 12/08/23 at 4:00 PM.
01/30/24 – Project bids received and vetted.   Project in contract approval phase.   lead time for equipment will be roughly 12 weeks.
02/28/24 – Glenwood electric is sent the PO and signed contract.   Submittals yet to be received/approved by TEI.
03/27/24 – TEI receives submittals and approves.  Equipment is being procured.
04/24/24 – Construction kickoff scheduled for 4/29.
05/29/24 – Construction kickoff meeting occurred.  Glenwood orders electrical equipment (Scheduled ship date = 11/20/24)
06/26/24 – No Updates.
07/24/24 – No Updates.
08/28/24 – No Updates.
12/11/24 – HCFD, TEI and Glenwood meet on site for Pre-construction meeting. Panel in Glenwood shop – Enclosure no with Panel. Glenwood looking at early January for installation.
01/29/25 – HCFD requests installation schedule form Glenwood.
02/26/25 – Installation to begin in next week or so.
04/23/25 – Project installed, complete and punchlist completed. Pending punchlist and closeout.
05/28/25 – Pending closeout documents.
06/25/25 – TEI approves closeout documents. Project completion pending delivery of binders.
07/30/25 – TEI reaches out to Glenwood for binders.
07/31/25 – OK to Archive, all done.

A&D – Chiller Room MCC Replacement Read More »

A&D – South Entrance Access Control

PM = Rycca Thacker, Mike Barth

01/25/23 – TEI Submits SOSS.  Project pending SOSS approval and PO.
02/23/23 – TEI receives approved SOSS and PO.   Project kickoff to occur and work to be completed.
04/27/23 – TEI to submit review set to HCFD by 05/03/23
05/23/23 – TEI submits drawings to HCFD for review.  TEI receives comments from HCFD.  TEI to update the drawings from the comments and develop bidding documents.
06/28/23 – TEI and HCFD PM finalized small projects bid package and issues to selected XBE companies for bidding.  Bids due back to TEI on 07/13/23.
07/26/23 – TEI invites 8 XBE and 1 non-XBE bidders to give costs on project.  Recieved (1) bid.  bids came in higher than expected.  TEI sends bid information to project manager and waiting for further decisions.
8/24/23 – TEI vets bid from Glenwood electric, and makes recommendations to HCFD.  Project pending contract approval.
09/26/23 – TEI approves submittals.  Installation pending product procurement.
10/26/23 – Glenwood electric has equipment ordered and scheduled to ship beginning of November.   Upon receipt of all materials, installation will be schedules.
12/06/23 – Glenwood working on install schedule.
01/30/24 – Project install complete.  TEI and HCFD perform punchlist.  Upon completion of all punchlist items, and receipt of closeout documents, project will be complete.

02/28/24 – The Original bid portion of the project punchlisted.  CO work waiting on material procurement and scheduled install date.

03/27/24 – The Air Curtian Fan is installed.  Final punch items be completed this week.  Then project can be closed.

A&D – South Entrance Access Control Read More »

A&D – Façade and Foundation Repair (F063)

PM: Rycca Thacker, John Millar
08/15/22 – Hamilton County requested SOSS.
09/29/22 – THP anticipates publishing the SOSS 10/4/22. Working with Tru Scan and Thermal Tech.
10/17/22 – THP published SOSS.
01/25/23 – Model created, design ready to start.
02/23/23 – Civil surveys and field surveys in process. Surveys include roof and site work.
04/27/23 – Project updates: Civil survey complete, fall arrest SD complete, and field survey of attic completed. THP coordinating with potential contractors and geotechnical testing company to develop foundation repair package.
07/27/23 – THP anticipates issuing an complete SD set on 8/3/23.
09/28/23 – THP working on SD documents.
10/26/23 – THP scheduled to publish review set October 31.
12/06/23 – THP issued review set.
01/31/24 – THP needs to schedule review meeting with Hamilton County.
02/07/24 – THP met with County to review design development documents.
02/28/24 – THP working on bid documents.
03/28/24 – THP working on bid package.
04/25/24 – THP working on bid package.
05/30/24 – THP working on bid package. Bert said he wants to get it packaged to the point to where it can be bid ready, even if it is shelved.
06/27/24 – Rycca said to go ahead and bid out safety repairs from report.
07/25/24 – THP working on safety package for City Repairs.
08/29/24 – Safety package anticipated for issued 9/4/24.
09/26/24 – Safety review package anticipated for issued 10/09/4/24.
12/10/24 – THP closing out project.
01/24/25 – THP submitted closeout DD package.
02/26/24 – THP published City Façade repair letter.

A&D – Façade and Foundation Repair (F063) Read More »

A&D – Annual Façade Monitoring (F049)

12/14/22 – Hamilton County published a project list for 2022. City Inspection to be completed by June 30.
04/06/22 – THP Submitted SOSS for review by the County.
04/12/22 – County Approved the SOSS.
04/14/22 – THP Completed rappelling survey of the façade.
06/29/22 – THP issued reports and City form.
06/30/22 – THP Scheduled to submit form to City.
08/25/22 – Project complete.
10/27/22 – Ready to Archive.

A&D – Annual Façade Monitoring (F049) Read More »

A&D – JFS Furniture Redesign DD-CA

02/08/22 – Signed SOSS Received. Kickoff meeting scheduled for 03/22
03/22/22 – DD Kickoff meeting held. Weekly meetings scheduled for friday mornings for duration of DD phase.
04/13/22 – THP requested to review proposed cabinet layout on the fifth floor on the west side of the building.
04/14/22 – THP – Champlin approved THP proposal.
04/22/22 – Weekly DD meetings in progress.
04/26/22 – THP reviewed the cabinet location and analyzing the conditions.
04/28/22 – Kevin asked about dehumidification in the basement. ThermalTech to look at existing conditions and trending this area. Three months DD and three months CD; inclusion meeting during CD phase.
05/27/22 – Weekly DD meetings in progress.
06/30/22 – Weekly meetings complete. DD drawings to be submitted 7/1, DD estimate 7/8.
07/28/22 – Weekly CD User group meeting to start end of august.
08/23/22 – First weekly meeting scheduled for 8/26.
09/29/22 – CD ongoing. Last progress meeting scheduled for 9/30.
10/17/22 – ThermalTech conducted several field trips back to the building for final design
10/26/22 – LEED Checklist returned to Champlin from ThermalTech with comments and suggestions. Drawings, titleblocks, spec headers all being coordinated wth Champlin.
10/26/22 – Final Owner Review meeting scheduled for 10/28/22.
10/27/22 – Friday final owner review will be electronic review. Print three 11×17
12/15/22 – Project out to bid.
01/26/23 – Project still in bid phase. final addendum to be sent out next thursday. Bid opens 2/9.
02/14/23 – Bid opening – Universal is apparent low bidder
02/22/23 – Bid Review is scheduled for 3/3. Meeting rescheduled to two weeks from now. Furniture package is currently under review. Champlin has requested additional information from furniture vendor.
03/30/23 – Champlin sent Letter of Recommendation for Universal. County still deciding whether to move forward with contract with Universal.
04/27/23 – Universal answered several follow up questions. County is proceeding with awarding the bid to Universal. Contract is in progress.
05/25/23 – Monthly meetings with users scheduled.
06/29/23 – No update.
07/27/23 – No update.
08/31/23 – No update.
09/28/23 – No update.
10/25/23 – No update.
12/07/23 – No update.
02/29/24 – No update.
03/28/24 – No update.
04/25/24 – No update.
06/27/24 – No update.
08/29/24 – No update.
09/26/24 – No update.
10/30/24 – No update.
12/12/24 – No update.
01/30/24 – No update.
02/27/25 – OK to Archive.

A&D – JFS Furniture Redesign DD-CA Read More »

A&D – Accessible Employee Entrance

12/03/21 – Signed SOSS Received.
01/25/22 – Product research and preliminary brainstorming started. Field survey to verify existing conditions.
02/24/22 – Field verification complete. Products research complete.
03/31/22 – Options sent to County for review. Waiting on scope decision to price.
04/28/22 – Kevin Holt confirmed this project will not be moving forward. OK to Archive.

A&D – Accessible Employee Entrance Read More »

A&D – Access Control Maintenance Agreement

PM = Rycca Thacker, Mike Barth
12/13/21 – JFS issues RFQ and bids come in significantly higher than expected.  TEI and HCFD to develop an ITB with a clearly defined scope for rebidding purposes.
01/25/22 – TEI working on RFQ – will submit to RT for review and comment.
02/23/22 – TEI and Rycca to finalize requirements of scope and develop bidding schedule for the ITB.
04/27/22 – TEI and Rycca to finalize requirements of scope and develop bidding schedule for the ITB.
05/26/22 – TEI and Rycca discuss scope items and TEI is finalizing the ITB for HCFD review and approval.  TEI to submit to HCFD by June 10.
06/28/22 – TEI submits the final draft of RFP to HCFD for review.   Issuance of ITB pending review comments and direction from HCFD.
07/27/22 – The project is currently in the bidding phase.  Bids are due 8/26/22.  Prebid meeting scheduled on 08/03/22.
08/24/22 – Prebid meeting conducted and addenda issued.  Bids are due Friday 08/26/22.
09/26/22 – Bids received.  Glenwood apparent low bid.  TEI vets bid.  Recommends Glenwood for the project.  In contract phase.
09/29/22 – Archive next month.

A&D – Access Control Maintenance Agreement Read More »

A&D – Plumbing Modifications

PM: Rycca Thacker, Terry Cannon
10/28/21 – TTC provided update on low flow plumbing issues at the A&D Building. In the past month, we had a major leak at the main sanitary leaving the building. Plumbers called Underground Detective to survey the pipe from the building to the street. TTC to get a test kit for testing in Fifth Floor East.
12/13/21 – TTC in contact with RC Frey & Associates to order the part for testing purposes.  A new SOSS was created for this part of th Study.  Once I get the part in town, i can coordinate with Danny on the installation needs of this part of the test.
01/25/22 – TTC needs to coordinate and pick this part up or have it ordered by County.
02/24/22 – TTC has to get this done this week. I will talk to Danny about getting this ordered.
03/31/22 – TTC stopped at Ferguson earlier this week and the part is special order, order into “inside sales” and as soon as they confirm, we will put on order through TTS.
04/28/22 – TP-4 is here and TTC picked it up and will drop it off today at the meeting. The next step is to coordinate with Danny and Steve on installation.
05/25/22 – Plumbing fixes relocated to the Furniture design job. I spoke to Danny about piping changes inside the chase when we open it open. I plan to discuss at Friday Champlin meeting on a Furniture project. I have also searched out what may be an even easier fix with a new Zurn product but I don’t have the specifics quite yet.
06/30/22 – Need to schedule 5E wall opening with County. Ask at the meeting.
07/27/22 – I was able to get into the chase with three existing chases on the 6th floor and found what I needed for plumbing design.
08/24/22 – Setting up a field trip with Danny, hopefully on Friday at 8:30 am to go over installation.
09/22/22 – Found the flush timers online and there is some discussion to try the flush timers first instead of installing the trap primers first.
09/29/22 – TTC to provide equipment selection to Danny to purchase and install.
10/26/22 – Working out final order details with GenieFlush from California. We should be able to order the equipment by Friday.
12/15/22 – Parts are in, TTC needs to meet with Danny to install and test.
01/24/23 – Two auto flushers were installed two weeks ago and set to two hours intervals. WE will monitor and keep track of clogging.
02/21/23 – One flusher is on 4E and one is on 5E. The fifth floor is working just fine, the fourth floor has a sticky flush rod, TTC to reach out to the vendor for a replacement part.
03/29/23 – We reached out to the vendor for a replacement part and he would like pictures of the bad module.
04/26/23 – No updates.
05/21/23 – No updates.
06/28/23 – Archive.

A&D – Plumbing Modifications Read More »

A&D – Sewage Ejector Pumps

PM: Terry Cannon, Tony Matre

10/28/21 – Sewage ejectors not working correctly. Tony called for replacement work on them. Prebid set for today 2pm today.
11/30/21 – Bids received, QCM apparent low bidder. Pre Award meeting held virtually and QCM recommend for work.
12/14/21 – Tony getting PO for work to QCM for job. TTC to setup a pre const meeting late Dec 2021.
01/18/22 – Pre Const Mtg with QCM. Equipment approved and on order. The meeting went well, Drew and his foreman looked the job over. We are shooting for a Feb or March start date.
02/24/22 – No update on equipment delivery yet. QCM talking to Corporate Equipment every day to finalize a delivery date.
03/31/22 – Changed to submersible pumps, approved new submittals, created new dwgs and sent to vendor, should be installed mid-April.
04/18/22 – New pumps were installed and completed. MC and EC are done, and controls are coming to hook up the alarm points.
04/28/22 – The system is working well, pump #2 is going out on overload. EC dispatched to look at on Wednesday, they called Streamkey to look at the issue on Thursday. ALC controls are not hooked up yet, need additional wiring for the interface.
05/25/22 – Project complete and punchlist distributed to QCM. Emcor ALC waiting on badged low voltage electrician to run their alarm wiring before we close out. I sent all closeout docs to QCM. The system is working well.
06/30/22 – Just waiting on controls to finish DDC work, closeout documents from QCM.
07/27/22 – Controls work is complete. TEI requested O&M and Closeout documents from QCM.
08/24/22 – Project complete, we’ve requested closeout documents.
08/26/22 – All closeout and final payaps received. Project ready to closeout.

A&D – Sewage Ejector Pumps Read More »

A&D – 7th Floor Access Control Modifications

PM – Rycca Thacker, Mike Barth

10/26/21 – ThermalTech receives signed SOSS and PO. HCFD asking for design to be complete by 11/05/21.

12/13/21 – TEI submits drawings to TEI with to HCFD for review.   RT returns drawings to TEI with additional scope changes.  TEI to finalize drawings for issuance by EOY.

01/25/22 – TEI sends drawings to HCFD for review and final comments, to be issued upon receipt of comments.

02/23/22 – TEI sends drawings to Glenwood Electric to obtain quote (since Glenwood is under warranty for system).  Upon receipt of quote from Glenwood, TEI and HCFD will determine next steps.

04/27/22 – TEI reviews quote with RT and Glenwood.  Recommendations forwarded to JFS.  Next steps pending approval from JFS.

05/26/22 – JFS approves the Glenwood quotation.   HCFD executes CO for project and Glenwood is procuring materials.   Install to occur upon receipt of materials.

06/28/22 – Install to occur pending material procurement.

07/27/22 – Install to occur pending material procurement.

08/24/22 – Install to occur pending material procurement.  As of 8:00 PM on 8/24/22, Glenwood received materials at their shop on 08/24/22.   Glenwood is coordinating resources and will contact Rycca Thacker in the next few days to schedule installation.

09/26/22 – Project in construction phase.  Upon notification from Glenwood that install is complete, TEI and HCFD will perform punchlist.

10/26/22 – TEI and HCFD to perform punchlist.

12/15/22 – TEI and HCFD to perform punchlist.

01/25/23 – There were hardware issues on the stair tower doors.   Glenwood ordered replacement hardware and tentative ship date is approx 3 weeks.  TEI will finalize punchlist upon installation of pending hardware.

02/23/23 – Project completion pending installation of hardware.

04/27/23 – Project completed.  RT and TEI perform punchlist walk through.  Upon receipt of all close out materials, can be archived.

05/23/23 -Waiting on  receipt of all close out materials.

A&D – 7th Floor Access Control Modifications Read More »

A&D – Computer Room Emergency Power Connections

PM – Rycca Thacker, Mike Barth
08/26/21 – HCFD sends signed PO and SOSS to TEI. TEI to start immediately, as the switchgear cleaning work is contingent on the this work.
10/26/21 – TEI submits preliminary plans and opinion of probable cost to HamCo for review. Project pending project funding.
12/13/21 – TEI and HCFD gets quotation from CE Power to provide the install of the work.  HCFD drafts and issues a PO for the work to be installed, and requests schedule from CE Power.
02/23/22 – All equipment has been ordered and anticipated delivery was end of February, early March.   CE Power to notify TEI and HCFD upon receipt of all equipment and schedule installation and cleaning.
04/27/22 – Equipment is installed in the building. HCFD and TEI requesting dates from CE Power to perform Switchgear PM and Tie ins during same outage.   Tie in pending CE Power availability.
05/26/22 – Tie in date tentatively scheduled for June 20 (Juneteenth Holiday).  Pending approval from HCFD and JFS personnel.   JFS requested that it move to as Saturday in case there were issues and needed the Sunday for repairs.   Final date TBD.
06/28/22 – Date of tie in moved to 07/09/22.  Tie in to be competed concurrently with switchgear cleaning (same power outage).
07/27/22 – Power outage cancelled by Duke energy due to tornados in the area, and unavailability of Duke crews.   CE Power, HCFD, JFS and Duke to reschedule.
08/24/22 – Reschedule date is 09/10/22 pending no storms etc. in area.
09/26/22 – Installation complete.  testing, training and punchlist to be scheduled.
09/29/22 – Work on SOSS for putting CRAC and Condenser on backup power.
10/26/22 – TEI submits SOSS for placing CRAC unit condensers on the backup power.   project pending SOSS approval.
12/15/22 – TEI receives approved SOSS and PO.   Project Design in progress.
01/25/23 – CE power punchlist incomplete.  TEI sends follow up email to request that the work completed ASAP.    Alex on site on 01/25/23 to confirm the existing power feeds to the condensing units, and a review set will be send to HCFD prior to bidding.
02/23/23 – TEI to submit to HCFD bid set for final review.
03/29/23 – TEI to submit review set to HCFD by 05/03/23.
05/23/23 – TEI submits review set to HCFD for comments.   Upon receipt of owner review comments, project will be issued for bids (small projects method).
06/28/23 – TEI, RT and Kleeman meet on site and discuss project.   Trades electricians to provide installation of the circuits.  TEI to procure the permit from IBI for trades.
08/24/23 – Drawings are submitted to IBI for permit.  Comments received and answered from IBI.  Permit expected in next day or two.
09/26/23 – Plan review complete and permits ready to be picked up at IBI.  TEI will deliver to HCFD for work to be completed by trades.
10/26/23 – TEI procures the permit for the work and sends to HCFD.  Trades to install work.
12/06/23 – Trades to notify TEI when they are ready for inspections.
01/30/24 – Trades completes work.   TEI and Trades have IBI inspect work and passed inspections on 1/30/24.
02/29/24 – Project complete, need as-builts to close out.

A&D – Computer Room Emergency Power Connections Read More »

A&D – First Floor EMF Study

PM – Rycca Thacker, Mike Barth

03/24/21 – HCFD requests SOSS from TEI for an Electromagnetic Investigation of the first floor of the A&D building. ThermalTech soliciting venders to provide us a quote to measure the EM waves in the area, and will submit SOSS once we receive the quotation.
04/28/21 – TEI submits SOSS to HCFD. Project pending approval of SOSS and PO.
05/26/21 – TEI receives signed SOSS and PO. Study phase started.
06/23/21 – TEI, Rycca, Steve T, and Claude T perform walk through of space on 06/23/21 to document the EMF readings in the area of concern. Initial readings were higher than expected levels. Report and recommendations to follow.
07/28/21 – TEI working on report – with continued research for appropriate recommendations.
08/26/21 – TEI nearing wrapping up draft of report to deliver to HCFD. Will complete the report upon completion of 2022 estimates.
10/26/21 – TEI to deliver draft of report to HCFD 11/05/21.
12/13/21 – TEI submitted hard copy draft of report to HCFD for review and comments.  Final report pending HCFD review.
01/25/22 – Final report pending HCFD review.
02/23/22 – Final report pending HCFD review.
04/27/22 – TEI receives comments from HCFD on  04/18/22.  TEI incorporating comments and will deliver final draft to HCFD.
04/28/22 – Today’s discussion centered around adding to the study with a physicist recommendation on lead abatement protection. Champlin will lead collecting the information for the additional study and pulling in a third party person to help us update our report. Eventually, this will turn into a new report to the County. Meeting next Tuesday with THP, TEI and Champlin.
09/26/22 – TEI hand delivers (4) hard copies of the EMF report to HCFD.
10/26/23 – Project still on hold until further notice from HCFD.
12/12/24 – BW said to go ahead and send the final report to Rycca and close the project.
02/27/25 – OK to Archive.

A&D – First Floor EMF Study Read More »

A&D – Moisture Investigation

10/27/20 – THP sent SOSS for moisture investigation.
12/10/20 – THP and TEI to follow up on water line testing.
01/28/21 – THP completed multiple water tests and has determined water sources. THP developing excavation proposal. Draft report partially completed.
02/23/21 – SOSS requested by Hamilton County.
03/23/21 – THP provided SOSS. Three posts migrated to this project.
04/22/21 – Excavation completed along the north elevation, along with subbasement excavation.
04/29/21 – THP finalizing draft report. Anticipated publish date 5/7/21.
05/27/21 – THP updating the report with the excavation information.
10/27/21 – Budget issued in September then final report with updated interior repair added issued on 10/27/21

A&D – Moisture Investigation Read More »

A&D – JFS Furniture Renovation 2020 SD

06/22/20 – Kick-off meeting. Attended by Mike and Christy from Champlin, John from THP, Mike and Terry from ThermalTech, Susan and Megan from IPM, Rycca, Bert, and JFS executive team from County.
07/09/20 – THP provided a proposal to Champlin for structural support.
08/21/20 – SOSS submitted. Waiting for authorization to proceed.
09/23/20 – SOSS Approved. Kick-off meeting attended by Christy
10/29/20 – programming received from Michael Patton. Typical cubicles were revised and sent to Rycca. Ready to present to JFS.
12/10/20 – Regular design meetings in place.
01/26/21 – TEI and IPM worked out details on walls around the fintube radiators along the outer walls.
01/27/21 – Weekly meetings on Fridays. Final programming meeting scheduled 2/5.
02/25/21 – Weekly meetings still ongoing. planning to start on the 1st and 5th floors.
03/25/21 – Ongoing weekly floor-by-floor presentations of space planning to Michael Patton.
04/29/21 – Ongoing weekly meetings. Field verification walk thru scheduled 5/3/21
05/07/21 – Final Coordination meeting with JFS
05/20/21 – Sent final misc. questions to Michael Patton.
05/21/21 – Received 4th and 5th Floor comments and revisions from JFS
06/03/21 – Field verification to determine signage scope.
06/24/21 – Rough draft of SD Set sent to Rycca for review.
06/25/21 – TEI owes Champlin a SOSS for the plumbing work. Gender-neutral question is out there too.
07/28/21 – Archibus #2106 is updated with MEFP cost and sketches for this project including plumbing updates for bad flow conditions.
07/29/21 – SD documents submitted to Rycca for JFS review. The next step will be a design review with TEI on final design decisions. THP will need to review the new layout from the load study perspective.

08/26/21 – Final Review meeting with County, Thermaltech and Champlin.

09/15/21 – Champlin provided County with updated estimate.

10/12/21 – Champlin provided County with a breakdown of door types being replaced for review.

10/28/21 – Project is complete. Ready to Archive.

 

 

A&D – JFS Furniture Renovation 2020 SD Read More »

A&D – JFS Director’s Office Renovation

08/30/19 – Champlin submits SOSS
09/11/19 – Champlin received approved SOSS & PO.
10/31/19 – Susan is coordinating furniture selection. Project will go to bid after that.
12/02/19 – Bids received from 3 bidders. RCF is apparent low and Purchasing is processing this to move forward.
06/25/20 – Furniture on site but may not be used given retirements and Covid. Project can be archived at this time.

A&D – JFS Director’s Office Renovation Read More »

A&D – JFS Internal Door Replacement

06/17/19 – County requests JFS Internal Door Replacement Project Scoping Meeting
07/02/19 – Meeting with Facilities (Tony Matre, Steve Sears, Cloude Toulson, Bert, Kru and Jeff)
07/11/19 – Champlin submits SOSS
09/11/19 – Champlin received approved SOSS and PO.
09/13/19 – Champlin performs site visit to verify all office door locations to be included.
10/28/19 – Champlin performs site visit with Hardware Consultant to confirm door hardware. Hardware consulting on going.
12/10/19 – Bid set sent to county
01/07/20 – Addendum #1 sent to County
01/16/20 – 5 bids were submitted to County.
01/22/20 – Champlin met with Megen Construction.
01/27/20 – Champlin sent official recommendation to award bid to Megen Construction.
03/26/20 – Waiting on official Contract to be given to Megen to return their door submittal
04/17/20 – Scope of work reduced to egress and security doors only.
05/04/20 – Megen given contract.
05/13/20 – Zoom meeting between Champlin and Megen to discuss scope changes.
05/28/20 – Waiting on revised estimate from Megen to proceed
06/24/20 – Waiting on revised estimate from Megen to proceed
06/29/20 – Megen provided revised estimate and other pre-construction information necessary.
07/21/20 – Pre-construction meeting attended by Champlin, Megen and County to further discuss the project. still waiting on project schedule and schedule of values from Megen.
07/28/20 – Door and Frame Submittal returned to Megen.
07/31/20 – Site visit scheduled to walk through areas of additional scope.
08/07/20 – Megen sent Safety materials.
08/18/20 – Schedule of Values and Project Schedule received from Megen construction. Megen has provided construction schedule showing NTP of August 3 and completion on December 7. On site work scheduled to start October 9. Mark-up of doors to be added sent to Claude/Steve for review and confirmation prior to creating a bulletin for contractor pricing. Waiting on direction to proceed.
08/24/20 – Change order for decrease in scope sent to Megen.
09/09/20 – Add services for Thermal Tech sent to Rycca.
09/21/20 – Megen workers complete background checks. Megen visits site to confirm existing conditions
10/09/20 – Scheduled start date.
10/29/20 – Construction started. OAC meetings scheduled for every Friday through end of construction projected by Megen to be December 7th.
12/10/20 – Working on new RFI for this project. Work on answer after tomorrow’s meeting.
01/15/21 – Restarted weekly construction progress meetings.
01/25/21 – Megen provided construction completion dates as follows: Basebid 2/23/21 bulletin 2 work. 03/02/21 Bulletin 1 work 3/22/21.
01/26/21 – Champlin returned comments requesting accurate pricing for 2 potential change orders.
02/08/21 – Progress Walk-thru attended by Sam Hofmann, Randy Johnson, John Nester, Steve Terheiden, and Rycca Thacker
02/19/21 – Bulletin #03 issued for replacement of existing closer/holders. RFI approved for supplier change from Interior Supply to LaForce.
03/19/21 – First Punchlist by Sam Hofmann, Mike Murphy, Rycca Thacker, Steve Terheiden, and Steve Kenneda.
03/26/21 – Second punchlist scheduled.
04/29/21 – Final punch scheduled for 4/30.
05/07/21 – Verified operation of closer/holders with fire alarm system. (attendees include, Rycca, Steve T, Mike B, Mike M, Sam)
05/10/21 – Champlin sent Rycca contractual dates and sequence of events as a word document.
05/12/21 – Final punch by Rycca, Steve T, Mike B, Mike M, and Sam.
05/14/21 – Punch list issued to Randy and Steve K.
05/18/21 – Rycca receives invoice from Phazor for replacement of fire alarm relays. Champlin send invoice to Megen. Randy acknowledges receipt and indicates he’ll forward it to accounting for payment.
05/25/21 – Contacted Megen regarding schedule of completion of punch list items.
06/24/21 – Megen notified us remaining materials received. intend to install on June 28th.
07/28/21 – Megen issued completion date of 7/28
08/26/21 – Waiting on Medeco Cores to be delivered.
11/08/21 – Final punchlist with County and Champlin. Still waiting on Medeco Cores from Megen.
11/17/21 – Finished second half of final punchlist
11/30/21 – Sent finalized report to Megen. Gave deadline of December 31. Requested filled out responsibility columns and schedule. Have not received either
01/21/22 – Final punchlist finally received from Megen.
01/25/22 – Backpunch by Sam and Rycca.
02/10/22 – Backpunch items completed. All construction services complete.
03/31/22 – Close out documents to be complete by friday.
04/28/22 – Close out documents received from Megen. Under final review.
05/26/22 – Close out documents to be reviewed.
06/30/22 – O&M manual reviewed and returned comments to Megen. Awaiting corrections
08/25/22 – Still waiting on Payroll information.

12/15/22 – All closeout documents and payroll information received. PROJECT COMPLETE

A&D – JFS Internal Door Replacement Read More »

A&D – Movable Wall (F005)

07/01/19 – Hamilton County requested to review and design a movable wall.
07/12/19 – THP provided an SOSS.
07/23/19 – County approved SOSS.
08/29/19 – THP completed initial design. THP to meet with County to review approach and design needs.
02/27/20 – Wall manufacturer went out of business, so project on hold.
06/25/20 – Facilities will touch base with JFS on the viability of this project.

A&D – Movable Wall (F005) Read More »

A&D – Façade Coating Survey

06/10/19 – Hamilton County requested SOSS to survey masonry coated area and remove loose debris.
06/12/19 – THP met with American Façade Restoration to discuss contractor scope and to get a proposal.
06/19/19 – THP submitted an SOSS for design services and AFR proposal to complete the work.
08/29/19 – Work scheduled to start after F117 complete.
10/31/19 – See F117 for project status.
01/24/20 – THP finalized Alms & Doepke window sill repair details and emailed to AFR proposal for change order #6.
01/30/20 – See F117 for project status. Construction work complete. Final paper work closeout in process.
02/27/30 – Refer to F117 for project status.

A&D – Façade Coating Survey Read More »

A&D – Access Control System Design

05/29/19 – Hamilton County requests SOSS for the project.
06/26/19 – TEI submits SOSS to facilities. Project pending SOSS approval and PO.
07/24/19 – TEI receives signed SOSS and PO for project. TEI, Facilities and JFS to conduct project kickoff meeting on 07/25/19 to begin project.
08/27/19 – ThermalTech emails Claude T to request 100% review meeting for a time on (or around) 09/11/19. After final review comments, project will be issued for bidding.
09/25/19 – ThermalTech, HCFD, and JFS meet to review 100% documents. HCFD send TEI federal procurement requirements. TEI adds to the project manual and submits to HCFD for review by prosecutors office. Project will be issued for bidding upon receipt of comments from the prosecutors.
10/30/19 – Project will be issued for bidding upon receipt of comments from the prosecutors.
12/11/19 – Project bids received, Glenwood Electric is apparent low bid on the project. TEI vetted bid and submitted recommendation that HamCo proceed with authoring the contract with Glenwood.
01/28/20 – Upon approval of contract and issuance of PO to Glenwood Electric, a pre-construction meeting will be scheduled and the project construction will commence.
02/26/20 – Glenwood’s PO and contract approved. Construction kickoff meeting scheduled for 02/27/20 at 1:00 PM.
03/26/20 – Construction kickoff pending the return of the background checks.
04/30/20 – Construction began – paused due to non-shipment of parts from MFGR. Glenwood clarifying scope and working to get actual ship dates.
05/27/20 – Construction underway. Control cabinets installed in basement through 7th floor on west end of the building. Controllers installed on 6,5, and 4 on the est end of the building. power supplies ordered and pending on time delivery, power supply install anticipated to start on or around June 1. Anticipated project completion is end of June.
06/23/20 – All controllers are installed. All power supplies have been installed and powered. Glenwood and Claude Toulsen are working to develop new badgeing standards (photos, logos, facility codes, etc). Upon completion of the badge standardization process, and all of the JFS data is updated to new standard, the database will be imported to the Kantech system and the system will then be migrated over to the new system.

07/29/20 – JFS is working with Glenwood to transition old database into the new database, and upon completions of the development of the new database, new system pretty much ready for rollout. The door on the southwest corner of the Parkhaus Garage is on the old system, and will not be functional after change over without adding to system. Glenwood provided pricing for changeover. HCFD, JFS, AMB and A&S to determine next steps.

08/21/20 – Glenwood waiting on Pictures from JFS to include in the software before they can transition over to Kantech system. Glenwood working to respond to punchlist information that the installation is not in compliance with the specification.

09/23/20 – JFS completes their preparation work with the new employee photo database. Discussion occurred when Glenwood stated there was no additional expandability in the new system. TEI provided documentation of the basis of design product had substantial expandability built into the system. Glenwood ordered additional cabinets to provide the expandability that was included in the specifications. Glenwood to begin installation of additional cabinets and the associated programming on 9/28. Estimating 2 additional weeks from then for completion of installation. Upon completion of installation, TEI will perform final Punchlist and process closeout documents.

10/27/20 – Glenwood is on site programming all cards and integrating the new database. Additional batteries are on site, however, additional power supplies were back-ordered, and are scheduled to ship 10/30/20. Will be installed upon receipt.

12/09/20 – Glenwood on site doing switchover to new system. All upper floors are on the new Kantech system, and the new doors in the basement and sub-basement are installed and on the new system. Exterior doors are scheduled to be switched over on 12/14/20, and building staff and Sheriff’s office has been notified and is planning for the switchover.

01/26/21 – TEI and Matt Butz performs punchlist for project. Upon completion of Punchlisted items and closeout, project will be complete.

02/23/21 – TEI and Rycca Thacker perform punchlist back-check. TEI requests final closeout documentation from Glenwood to close out the project.

03/24/21 – TEI receives and is reviewing the O&M manuals from Glenwood. Upon approval of O&M Manuals, TEI will deliver to HCFD. TEI and Glenwood working to provide all close out paperwork for the project.

A&D – Access Control System Design Read More »

A&D – Cooling Tower Replacement

01/07/19 – ThermalTech met onsite with BAC representative and reviewed condition of existing towers. TEI sent in an SOSS for the study for approval to Facilities later that day in hard copy and email.
01/21/19 – SOSS approved TTC setting up report and getting prices for replacement and repairs.
02/28/19 – All prices are in and preliminary report has been written. TTC to review, updated and send to Bert and Steve for their use.
03/27/19 – TTC must review final cost estimate tonight to share with County tomorrow.
04/25/19 – TTC will submit report today.
05/27/19 – Prices and Study submitted to County. Awaiting County decision on repairs.
06/27/19 – Talked to Tony Matre about bidding out the replacement of the cooling towers this year and he said check in with Bert about project viability. The schedule would be to start after cooling season and be complete prior to 2020 cooling season.
07/24/19 – Meeting schedule with County on 7/25 to discuss options. TTE fieldwork is complete for the cooling towers. PID has been converted to CAD for use on this project. There are questions about the design and cooling tower sizes to be discussed at Thursday meeting.
08/28/19 – Project is in to the owner for review. Funding is set for approval from JFS in August.
09/24/19 – Project undergoing some funding and County review. TTE will have project ready to bid when final okay comes from Owner, looking to mid November.
10/30/19 – Project on hold. TTC checked with lead times on Evapco towers who claim to still be two to three weeks.
12/11/19 – Had some movement on this project this week. TTE to submit a small SOSS for some additional services for extra design work.
12/12/19 – The money has been approved for this project but the paperwork is not fully approved at this time.
01/24/20 – ThermalTech putting final bid documents together for bidding in February 2020, award in spring, be read to construct in November 2020. TTC discussed project with Steve Terheiden last week on Ameresco walk through.
02/20/20 – SOSS and PO should be on their way for work in Feb/Mar.
03/19/20 – Prebid meeting at the site with about 6 bidders. Several items to be released on Addendum including a 6th Floor drawing clarifying sweeper piping.
04/23/20 – Bids were open to five bidders, most were underbudget. TEI conducted a post bid review with Debra Kuempel and found them to well recommended bidder for this project. They have the scope covered, would really like to start the job early if possible and have all of the Alternates covered in the bid.
04/28/20 – TTC spoke to Tony Matre about Alternates on this job and awarding the rest of the work. We will need contracts and a PO to get started, County thinking about allowing the CT to be replaced over the summer long weekend.
05/25/20 – Project in for approval. Debra Kuempel check on approval of job on Monday. We are accepting several of the Alternates but not the extra basin heater extras.
06/22/20 – Project setup and communication this month with RT this month for doing the work this fall. TEI updated Debra on project status and assured them this project is still a go. I don’t think this work will be done over the summer even in multiple parts over weekends, but this is something we can discuss at the Pre-Const mtg.
07/23/20 – Pre Const Mtg held on site with Debra Kuempel, TTE and County. We are getting all things in place for this job and potentially look for an earlier than fall start if we can get the equipment earlier. TTE issued the Const Mtg notes this night.
07/29/20 – 3D scanning schedule for Thursday. Submittals have been preliminarily worked out with Stoermer Anderson, Debra and TTE. The SS towers will weigh less than the existing towers and fit on the existing steel. We are discussing ladder and drainage details for the final submittal which should be next week. The delivery time for the towers may be as fast as 6 weeks per our discussions with Marley. DK has submitted the SOV, Schedule and Employee list for review.
07/30/20 – Lightning protection questions on the A&D was discussed. We have enough UL listing verification and THP will fix the drainage issues when they do their project.
08/24/20 – Debra inquired about roof build. TTC contacted GBBN for basic roof layout and send photos showing the roof structure from underneath to DK for this job. DK also inquired about submitted a payapp for this project this month which TTC said would be okay.
08/26/20 – No payapp has been submitted that TTE has seen yet.
09/18/20 – This month we approved final submittals. DK should have the CT on order with Marley. Now we are prepping for install.
09/24/20 – We got 30-day electric data back from DK. MCB says we will work with this data for the IBI permit. BW mentioned that we have to check the LED light pattern on the new CT so we don’t affect the historic district lighting effects.
10/28/20 – Checked in with Debra this month, got a handle on final background checks. Cooling Towers scheduled to ship Nov 11, being confirmed. TTC to check on permit status with Debra tomorrow.
11/18/20 – THP – as part of the Cooling tower replacement project, City of Cincinnati requested a structural review of the cooling tower structure and the proposed replacement towers. As part of the Cooling tower replacement project, City of Cincinnati requested a structural review of the cooling tower structure and the proposed replacement towers.
11/20/20 – THP completed site visit.
11/24/20 – THP published a letter addressing the City’s letter.
12/02/20 – THP submitted a SOSS for the work completed.
12/09/20 – THP received approved SOSS.
12/10/20 – We have been working on permitting, submittals and structural steel approvals with DK and THP this month. The permit appears to be approved at the City for DK to pick up. We need an update on the background checks, which seem to be taking longer than anybody would like. The county issued a PO direct to THP for their work getting the permit through the City office. All the equipment is in town for the job and TEI went to the rigging yard to approve it and send pictures of it for invoicing.
12/29/20 – Working with Debra to get guys through background checks to get started. Bert and Rycca have followed up with several emails on the subject. Phone conversation with DK has them starting in January and completing the job in January as well.
01/23/21 – Contractors on-site removing cooling towers today. Some issues with disassembly prevented them from getting both towers off the roof but they were able to get west tower, piping, and ladder removed. And for the east tower they removed the piping and ladder and full prepped the CT to be removed. The next crane lift is scheduled for Jan 30 and DK will remove the old tower and put up both new towers. The structural will be wire brushed and repainted and we are getting a change order to replace some more of the CWR piping.
02/24/21- DK moved inside during cold weather and started working in the basement. Slow progress as of last week. Weekly const mtgs set for Thursday until the project is complete.
03/23/21 – Punchlist Tuesday by Terry and Mike. TTC has been following up with Debra & Marley this week on several items pertaining to the construction of the tower. DK pricing replacement of the final platform behind the east tower. Punchlist due out Friday, County comments welcomed.
03/25/21 – TTC to check on OSHA compliance on the top of the tower including the gate, and kickplate. TTC to reach out to THP and get contact information for LJB.
04/20/21 – Change Order #2 approved for additional painting, grating and hot tap from high pressure city water system.
04/28/21 – DK reports all change order work is complete, final cleanup being done.
04/29/21 – Project is complete, punchlist is distributed, DK finalizing clean up on project.
05/26/21 – Change Order for electrical and controls work is in final approval. DK controls punchlist work has been complete and the system is running under revised control. Electrical and Mechanical inspections are complete and approved. Steps are not installed. Change Order control work to monitor the condenser water pumps via CT is not complete yet.
06/25/21 – We’ve checked in with DK several times on the final items to complete this job. (1) Steps are in fabrication. (2) Control programming is complete. (3) CWP circuit monitors are ordered but not installed yet. The good news is that the cooling towers are working well.
07/28/21 – Project is complete minus the steps. Safety docs sent to Rycca for record. DK is starting closeout manuals.
07/29/21 – Debra reported in today with updates. Warranty set for 5/26, closeout manuals being created, safety reports were sent to Rycca and steps over sweeper piping will be fabricated this week.
08/26/21 – DK is complete except for the steps which Joe is bringing over this week for the building.

10/28/21 – This job cannot be closed out until Maxwell provide actual pay stubs for their work. County will not pay final invoice until this is resolved. Debra contacted today to get this resolved.

A&D – Cooling Tower Replacement Read More »

A&D – Interior Finishes- Phase 2 and Phase 3

05/29/18 – GBBN is contacted by Facilities to begin assembly of the SOSS for this project. ADA Inclusion and THP Load Study must be included.
05/30/18 – IPM sends input to GBBN. GBBN requests SOSS input from THP and ADA Inclusion Consultant.
06/25/18 – GBBN receives SOSS input from THP and Preview Group for inclusion into SOSS.
06/26/18 – GBBN delivers final SOSS to Facilities.
07/26/18 – GBBN receives approved SOSS from Facilities.
07/27/18 – GBBN informs all design team members of approval and returns signed copies of Proposals to each design team members.
08/13/18 – Facilities requests GBBN make revisions to the “Project Scope of Work and Schedule” after consulting with all design team members.
08/15/18 – GBBN completes revisions to the “Project Scope of Work and Schedule” and transmits to Facilities.
08/30/18- GBBN to have internal design team meeting to kick-off Construction Document phase of project.
09/17/18 – GBBN begins Construction Document layout and production.
09/27/18 – Facilities requests GBBN and team put SOSS together for Construction Administration Phase 3 together. GBBN constact IPM and Accessibility Consultant for Proposal.
09/28/19 – GBBN contacts Facilities about LEED component of Phase 3 SOSS. Silver certification is requested.
10/04/18 – GBBN and TEI discuss LEED component of Phase 3 SOSS. TEI reviews LEED C.I. Checklist for MEP involvement.
10/07/18 – GBBN has internal office meeting to discuss LEED C.I. possibilities for this project. Findings shared with TEI.
10/16/18 – THP contacts GBBN about Floor Loading Study. Requests more information on types, sizes and weights of existing file cabinets shown on Second Floor West.
10/17/18 – GBBN performs site visit to document and photograph existing file cabinets. GBBN researches weights of fully loading file cabinets and reports findings to THP.
10/18/18 – IPM revises Second Floor layout to show a mirroring of West Side and East Side Departments to facilitate files moving from wood structure to steel frame structure.
10/21/18 – JFS approves IPM proposal to mirror the departments on the Second Floor.
10/24/18 – JFS reports additional changes to IPM/GBBN related to transaction Kiosks and Transaction Windows in Core, and cubicles on the West side, of Second Floor.
10/25/18 – THP completed initial field survey and review of the proposed floor plan. THP presented findings to GBBN for review with the County. We discussed LEED-CI feasibility with County at Partner Mtg. GBBN to submit a review of our findings that this building will not have enough credits to qualify for LEED certified and does not meet some of the pre-requisites for plumbing and water efficiency (an exemption would have to be requested).
11/02/18 – THP completed initial floor loading analysis of the proposed floor plan and published a summary letter.
01/14/19 – Entire Design Team meets to discuss project deliverables and scheduling in preparation for JFS and Facilities update meetings.
11/16/18 – THP developed a loading criteria and proposed a modified floor plan for review.
11/20/18 – THP and GBBN finalized a new plan to based on the loading criteria.
11/26/18 – GBBN receives approved SOSS and associated Purchase Order for Phase 3 of the project.
01/23/19 – GBBN and ADA Inclusion Consultant perform field verfication of all floors and spaces of entire buildings.
01/03/19 – Results of Mock-up Survey distributed to Design Team.
01/28/19 – GBBN/IPM/TEI meet with Facilities and JFS for Design Team update meeting. Revised Project Schedule presented to all attendees.
02/04/19 – GBBN holds in-house LEED review meeting. Contacts TEI via teleconference to discuss LEED Certification possibilities and shortcomings.
02/05/19 – GBBN relays findings of LEED Certification review by GBBN/TEI to Facilities.
02/07/19 – JFS sends clarification email on status of “supervised visits” for the Visitation Conference Rooms.
02/24/19 – GBBN receives ADA Inclusion Study from The Preview Group.
02/25/19 – GBBN and IPM meet with Facilities and JFS for Design Team update meeting. Meeting Mintues from last meeting distributed. IPM presented their recommendations for furnishings of the Peripheral spaces to JFS. Clarifications were made related to JFS’s provisions of task chairs. GBBN presents update on ADA Inclusion Study and LEED update for the revised project scope. IPM sends latest updated electronic drawing files to GBBN for Room and Door Numbering purposes.
03/08/19 – IPM updates owner on outlet/data wiring types and locations for new proposed spaces.
03/20/19 – ADA Inclusion Study language modifications as requested by Facilites is negotiated.
03/22/19 – GBBN transmits new floor plans with room numbering and finish/room schedules ot JFS for Safe Harbor Committee use.
03/26/19 – Progress meeting held with Owner. New plans, with Room and Door Numbering completed. Room Schedules with room areas completed, three sections per floor, for Claude Toulson’s use.
03/28/19 – IPM confirms wall verses core drill outlet locations for new Conference Rooms. Owner review meeting held with Facilities and JFS.
03/29/19 – IPM completes preliminary Recycling Specification for Owner review.
04/01/19 – GBBN copies Phasor As-Built outlet/data locations for TEI on thumbdrive.
04/02/19 – GBBN and IPM confirm to TEI that the new systems furniture will have task lighting, LED which will replace the existing fluorescent task lighting on the existing stations. Not all existing workstations have task lights. Facilities confirms any future workstation whips/outlets should be included in this Bid Package. Location of new and/or relocated thermostats has been decided by Facilities.
04/11/18 – GBBN conducts on site field verification of hte existing reflected ceiling conditions. Facilities decides to match the 6th floor light well soffits on the other floors with existing windows located insidethe new Offices. TEI confirms this decision will not adversely affect the lighting of the Offices.
04/12/19 – GBBN informs IPM and Facilities the Fourth Floor Plans do not show the existing small stair in the Core leading up to the East Side.
04/15/19 – TEI sends specifications section for Mechanical discipline. Meeting held with Owner to review project status.
04/22/19 – IPM sends updates on floor plan changes for JFS requested changes.
04/24/19 – TEI attends progress meeting with facilities, IPM and JFS. Reviewed MEP progress and left progress copies for all in attendance. TEI requested that IPM meeting to review every furniture power feed location.
05/06/19 – GBBN completes IPM Floor Plan and Furniture changes to the electronic drawing files. Copies of final plans sent to ThermalTech for their use as background drawings.
05/28/19 – Facilities confirms there will be no scope for the project related to “Safe Rooms”.
05/29/19 – IPM sends revisions to the Third Floor Plan to GBBN. ThermalTech drawings are mostly updated to last set of background drawings. HVAC, Electrical, and Plumbing should be read to review end of week.
06/13/19 – GBBN/IPM/TEI attend Design Progress Meeting.
06/26/19 – GBBN sends updated background electronic drawing files with updates from recent field verification.
07/01/19 – Design Team is scheduled to present the Owner with Review set of latest documents for Owner Review.
07/08/19 – GBBN submits Owner Review Set with Specifications, to Facilities, two sets, for review.
07/10/19 – GBBN issues additional specification sections to Facilities to be added to the Owner Review Set.
07/19/19 – GBBN, TEI and IPM coordinate discussions about project schedule and agree to the concept of eight weeks per phase. GBBN reports decision to Facilities.
07/23/19 – IPM requested that GBBN add addtional verbiage, in the specifications, requiring all General Trades Contractors, submit detailed line item quotes for the systems furniture. The Architects and Consultants will be allowed to review these quotes, to determine compliance with the specification,s before bids are awarded..
07/24/19 – Conversations with Facilities agreed that this additional information be added to the Supplementary INstructions to Bidders, Post Bis Instruction, 6.1.2.
08/26/19 – Facilities informs the design team that Project specific Federal Bidding language will be forthcoming by the end of the month or in early September for inclusion i nto the specifications. Facilities will also plan on delivering any review comments, from the earlier Owner Review Set, to the design team at the same time.
09/23/19 – The design team requests a meeting with Facilities to discuss added scope from JFS to determine what additional esitmating input is required for Project Request Estimate update.
09/24/19 – A meeting has been established for Friday 9/27/19 at 10:00 am.
10/18/19 – GBBN and TEI complete Opinion of Probable Costs updates for all disciplines. All discipline updates are sent to Facilities for their use. Facilities reports that review of the upddates have resulted in the project still being on track and the Design Team may proceed in wrapping up the Bidding Issuance Documents.
12/04/19 – GBBN contacts Purchasing Department for ITB information. ITB Number is #005-20.
12/09/19 – GBBN field verification of Fifth Floor Core offices to be demolished.
12/11/19 – Drawing Index updated. 160 sheets in set. Specification updated for all disciplines.
12/12/19 – ITB drawings and specifications to be distributed to Purchasing and ARC.
12/20/19 – Pre-Bid meeting held at Alms and Doepke Building. Meeting Minutes generated, along with Sign-In Sheet and issued by Addenda #1.
01/03/20 – Addenda #1 released to ARC and Purchasing Department. Specifications, drawing and Question revisions issued.
01/16/20 – Addenda #2 released to ARC and Purchasing Department. Question and Answer deadlines moved back one week. Specification and Questions addressed.
01/31/20 – Addenda #3 scheduled to be released to ARC and Purchasing Department. Bid Opening to be moved back one week to 2/13/20 at 11:00 am.
02/13/20 – Bid Opening held by Purchasing Department. Four bids received. Apparent low bidder is Graybach.
02/14/20 – GBBN conducts bid Interview telephone with Graybach following the bid opening. Telephone memo authored and transmitted to Facilities Department. Irregularities in responses summarized at bottom of memo, including apparent low bidder’s inability to provided required detailed breakdown within 24 hours as required by project manual and addenda. Follow up email sent to Graybach accordingly.
02/14/20 – GBBN receives telephone call from Graybach with additional Bid Rejection Interview questions. Facilities emails answers for transmittance to Graybach.
02/15/20 – Pursuant to the request by the Facilities Department, GBBN contacts Graybach, LLC to inform them of the ruling jointly by the Facilities Department and the Purchasing Department finding their apparent low bid to be non-responsive.
02/15/20 – Bid Interview conducted with Triton Services, Inc. at the request of Facilities Department. Telephone Memo authored and transmitted to Facilities. Triton Services delivers detailed breakdown used in Bid preparation to GBBN and Interior Project Management aa requested by Facilities.
03/02/20 – Pre-Award Meeting is held. Owner indicates the Recycling and WiFi Alternate Bids were to be accepted. Minutes to be distributed by GBBN.
03/03/20 – Triton Services confirms the manufacturer of the WiFi System will be as specified by ThermalTech.
03/15/20 – GBBN authors and distributes the Pre-Award Meeting Minutes to all attendees.
03/16/20 – GBBN solicits the successful bidders actual bid construction cost figures for the General and Mechanical disciplines for the permit application. The digital electronic submittal is completed and the CD burned for delivery to the City of Cincinnati.
03/17/20 – GBBN delivers and submits the hard copy and digital electronic permit submittal to the City of Cincinnati, for both Building and Mechanical Permits.
06/04/20 – BOCC rejects ITB-005-20.

A&D – Interior Finishes- Phase 2 and Phase 3 Read More »

A&D – System Furniture Mock-ups

05/16/18 – Design Team is notified that JFS has signed off on the latest IPM Floor Plan designs for all floors of Systems Furniture layouts. GBBN is asked to put together a preliminary schedule for the entire project including design.

05/24/18 – Design team and Facilities meets in Kick-off meeting to discuss scope of work. GBBN presents Preliminary Schedule.

05/30/18 – GBBN is notified by Facilities that JFS desires to have the mock-ups located in the Field Office Configuration. Exact locations to be determined. Standard configuration ‘B’ later chosen.

06/14/18 – SOSS is completed and submitted to Facilities. F058A is designated for the SOSS.

06/21/18 – SOSS approved and delivered to GBBN by Facilities.

07/05/18 – Decision was made to pull new workstation mock-ups from existing walls to allow staff to completely walk around the cubicles. No whips will be connected to the building system so no permitting is required.

07/06/18 – Meeting between Facilities and Design Team to finalize scope and deliverables.

07/11/18 – No Alternate Bids are required in the specifications.

07/13/18 – All three selected contractors have confirmed interest in the project. Documents are to be completed and issued.

07/16/18 – Facilities agrees to sixty (60) calendar days for receipt of Small Bid Packages from bidders.

07/19/18 – Documents are emailed to the three pre-selected bidders by Facilities.

07/26/18 – Pre-Bid Meeting to be held at Alms and Doepke Building Lobby.

08/03/18- GBBN issues Addenda #1 to bidders including the Pre-Bid Meeting Minutes.

08/10/18 – Bid Opening is held at CAB 5th Floor Purchasing Office. Three (3) bids are received.

08/11/18- GBBN interviews KFI by telephone and confirms complete understanding of scope of work. GBBN makes recommendation to Facilities to accept KFI as Lowest and Responsive Bidder.

08/13/18- GBBN makes revisions to AIA contract and delivers to Facilities.

08/28/18- Facilities mails copies of approved AIA contracts to KFI for their signature and Insurance requirement confirmations.

09/20/18 – Pre-Construction Meeting held at A&D Building. Facilities requests Background and Tax Exempt Package to be sent to KFI.

09/21/18 – Facilities sends Tax Exempt Package to KFI.

09/24/18 – Facilities sends Background and Tax Exempt Package to KFI.

10/16/18 – KFI sends Sales and Use Tax Construction Contract Exemption Certificate.

12/06/18 – GBBN authorized Application for Payment #1 and delivers to Facilities.

12/11/18 – GBBN authorized Application for Payment #2 and delivers to Facilities.

12/14/18 – KFI onsite for repalcement of existing damaged worksurface. Incorrect surface was delivered. Vendor authorizes order for correct damaged worksurface replacement.

1/18/19 – KFI onsite to replace damaged worksurface countertop. All work is successfully completed. Facilities agrees to closeout project.

A&D – System Furniture Mock-ups Read More »

A&D – Critical Façade Repairs (F104)

12/28/17 – THP publish SOSS to Hamilton County as requested.
02/15/18 – Hamilton County approved SOSS.
02/20/18 – THP published review documents.
03/09/18 – THP published bid documents.
03/15/18 – Prebid meeting completed.
03/29/18 – Bids received. American Façade Restoration the apparent low bidder.
04/3/18 – THP sent a letter of recommendation after a phone interview with AFR.
04/4/18 – THP sent draft AIA County / AFR contract to the County for review.
04/26/18 – County prosecutor reviewing the contract.
06/06/18 – Hamilton County and AFR under contract.
06/28/18 – AFR reported they plan to start work mid to late July. Work should take about two weeks.
7/23/18 – Preconstruction meeting completed.
7/26/18 – Anticipated start of construction will be 8/6/18 with work expected to be completed 8/31/18.
08/30/18 – AFR actively working on North, South and West elevations. Concrete and stone patching repairs 90% complete. South Elevation pilaster repair 50% complete.
9/5/18 – AFR substantial completion reached. THP reviewed work and generated a punchlist.
9/11/18 – AFR completed punchlist work.
9/27/18 – AFR working on closeout documentation.
10/25/18 – Project complete and closeout documentation complete.

A&D – Critical Façade Repairs (F104) Read More »

A&D – Access Control System Study

02/20/18 – ThermalTech met with the facilities department and A&D staff to discuss the need for a study for the existing access control system. ThermalTech submits SOSS for study for the project. Project pending the approval of the SOSS and PO.
03/27/18 – Project Pending approval of SOSS and PO.
04/25/18 – Project pending approval of SOSS and PO.
05/30/18 – Project Pending approval of SOSS and PO.
06/29/18 – Project Pending approval of SOSS and PO.
07/25/18 – Project Pending approval of SOSS and PO.
08/29/18 – ThermalTech receives approved SOSS and PO (5778030). ThermalTech, Facilities and JFS conduct study kick-off meeting on 08/28/18 and schedule field investigation of 09/13/18. ThermalTech beginning code research and product research beginning 09/01/18.
09/26/18 – ThermalTech completes field investigation with JFS (Claude Toulsen). Report is in progress. ThermalTech to send draft copy to BW for review upon completion.
10/23/18 – ThermalTech working to complete draft of report, and will send to BW and CT for review by 11/09/18.
11/28/18 – Report Draft is still in process. ThermalTech to wrap up draft and send to BW and CT for review.
01/29/19 – Report Draft is still in process. ThermalTech to wrap up draft and send to BW and CT for review.
02/26/19 – ThermalTech reached out to Basis of Design (VAX) for final pricing, and opinions of probable cost in report pending reciept of the pricing from the supplier. NOTE – Supplier local rep resigned and has not been replaced to date. TEI communicated with corporate offices.
03/26/19 – ThermalTech issues report to HamCo facilities and Claude Toulsen for review and comments. ThermalTech receives comments from BW, and final issuance pending comments from CT.
04/24/19 – Issuance of final report pending receipt of comments from Claude Toulsen.

A&D – Access Control System Study Read More »

A&D – Life Safety Drawing Updates

Partner Lead: GBBN
03/01/17 – GBBN – Hamilton County requested SOSS and indicates a separate F-Number be used.
04/11/17 – Facilities responds to GBBN scope questions.
04/13/17 – GBBN issues SOSS to Facilities.
06/29/17 – Meeting was held to review updates of Life Safety Drawings and explain concepts and fundamentals used in color selection and hatching determination. The color of orange and blue were chosen due to each being located across the color wheel from each other for greater contrast.
07/11/17 – Facilities confirms the plan views in the CAFM drawings are to be rotated “accordance with their position so left and right are always true to the egress path.
08/23/17 – GBBN forwards to Risk Management Safety Department the GBBN modified Alms & Doepke Life Safety Plans for internal review.
08/24/17 – Risk Management Safety Department approves GBBN modified Alms & Doepke Life Safety Plans.
11/30/17 – Drawings have been received from GBBN. Facilities coordinating with existing frames and carpenters’ will mount on the wall and rotate as necessary.

A&D – Life Safety Drawing Updates Read More »

A&D – Painting and System Furniture Replacement Renovation- Phase 1/ Phase 2

09/02/16 – Letter from Mr. Michael Patton of JFS giving update
06/07/17 – BOCC votes to approve the project for JFS.
06/21/17 – BOCC votes to approve the Meeting Minutes of the 06/07/17 Board Meeting.
06/23/17 – Facilities suggests Design Team begin thinking about an SOSS or SOSS’s for this project.
06/24/17 – GBBN contacts IPM and TEI to discuss ideas for numbers and durations of SOSS. Potential Agenda document circulated by GBBN.
05/26/16 – Facilities sends back Agenda review comments to GBBN. Facilities requests possible dates for Kick-off Meeting from Design Team.
07/24/17 – GBBN, IPM and TEI attended a kick-off and status meeting with Facilities and JFS. A SOSS was requested from the Design Team for the Phase I, Schematic Design and Programming Phase of this project.
07/31/17 – GBBN and TEI send to Facilities an inquiry about Systems Furniture Wire configurations. Facilities responds indicating the 3 circuit configuration is acceptable.
08/04/17 – Facilities responds to GBBN’s questions about scope and renderings for the SOSS.
08/08/17 – GBBN receives SOSS data and input from IPM and TEI for the Phase I Schematic Design and Programming Phase.
08/10/17 – GBBN authors and delivers the SOSS to Facilities.
09/14/17 – GBBN and IPM have meeting with JFS to re-engage on discussions related to logistics and scheduling on project.
09/15/17 – GBBN issues Meeting Minutes to Design Team and owner for review.
10/25/17 – Meeting with JFS for Children’s Services A&D Interiors Programming Meeting to include discussions with the Executive team followed by discussions with the division which is located on 4th floor, 5th floor, and some of 6th floor.
11/28/17 – IPM updates Facilities on status of project and Design Team meetings with JFS.
01/25/18 – 2nd Floor, from 3rd Floor completed. More Offices/Conference Rooms have been requested on these floors as well as the 5th/6th. This extra scope of adding more privacy offices, stacked by floors, will be investigated. THP will be needed as a consultant to investigate File Storage Capacity. ADA consultant will be required for ADA Comprehensive Audit Reviews. Cost estimating will be required after IPM completes Design Layouts for each floor to determine of costs for high cubes or hard-wall offices to ceiling are more effective. The SD SOSS will be reviewed to determine if additional scope can be absorbed or not. All programming documents will be distributed to All Groups for review by May of 2018.
02/22/18 – 2,4,5 finished, 3 is drafted, others are being updated, project going well.
04/09/18 – IPM requests additional fees to continue programming due to JFS increased scope creep. IPM sends proposal to GBBN for SOSS preparation.
04/11/18 – IPM issues project update for JFS meetings and decisions rendered.
04/16/18 – Meeting with Design Team and Facilities to discuss project status and schedule for the remainder of the project. IPM distributes the latest floor plan layouts to each party.
04/18/18 – GBBN/THP/IPM discuss file groupings and storage relative to a Load Study to be performed by THP.
04/26/18 – Meeting update stated that final drawings are in approval stage by JFS. Once the executive group signs off on these drawings the plans will be ready for the partners. They are trying to gain efficiencies in people relocation and keeping storage with each group. Use LEED approach for this project, make it green as possible and we will probably go after LEED-CI. Provide SD documents and two estimates, one for LEED and one for standard.
05/16/18 – Facilities circulates the final schematic Phase 1 drawings, created by IPM, as approved by the JFS Executive Committee.
05/17/18 – TEI sends SOSS input to GBBN for the Phase 2 portion of the project.
05/23/18 – Facilities indicates LEED may be a component of this project. GBBN discuss internally what the scope of work will be for Certifying this project. This information is shared with the design team.
05/24/18 – GBBN, IPM, TEI and Facilities meets to discuss the remainder of the project. GBBN presents the finalized Preliminary Design and Construction Schedule for the project.
05/29/18 – IPM sends to GBBN the SOSS input for the “Mock-Up Only” SOSS.
05/30/18 – IPM sends to GBBN the SOSS input for the remainder of the Phase 2 (through CD’s) project.
5/30/18 – Facilities confirms JFS has requested the Approved Standard Cubicle “B”, also referred to as the “Field Office Cube Configuration”, be the typical workstation to be used for the Mock-Ups.

A&D – Painting and System Furniture Replacement Renovation- Phase 1/ Phase 2 Read More »

A&D – Rekeying Project

08/22/16 – Bert Watts requested GBBN contact Tony Matre to discuss a potential re-keying project for this facility.
08/24/16 – A voice mail was left with Tony to make initial contact.
08/30/16 – A kick-off meeting was held with JFS, Facilities, GBBN and Assa Abloy to discuss keying options and electronic security locking devices. A site walk through was held to allow Assa Abloy to view existing door hardware types.
08/30/16 – GBBN authors and delivers SOSS to Facilities for the project.
09/06/16 – Facilities requests another copy of the SOSS Coversheet with updated SOSS number.
09/22/16 – Facilities requests literature to document various Keying Master/Grand Master options, Pros and Cons along with an estimate for the rekeying, without any door maintenance, based on the 307 existing doors listed on the spreadsheet by the Building Manager earlier and sent to GBBN. Assa Abloy estimated 30% of the existing doors were panic hardware for this exercise.
09/23/16 – Assa Abloy sends Opinion of Probable Cost estimate for re-keying and the schematic documents relaying the Master Keying options to GBBN. GBBN forwards the information to Facilities via email.
10/12/16 – GBBN authors revised SOSS and delivers to Facilities.
11/28/16 – RFP received from four vendors. Bid Tabulation compiled by GBBN and sent to Tony Matre.
12/01/16 – GBBN instructs Acme they have been selected as the Low Responsible Bidder. GBBN authors AIA contract and delivers to Tony Matre.
12/5/16 – GBBN contacts Acme concerning bidding questions to complete bid recommendations to Owner.
01/10/17 – GBBN confirmed fee is exhausted and henceforth GBBN has completed all obligations. Assa Abloy contacted by GBBN about representing the Owner at the Keying Meeting.
01/26/17- Keying meeting held at A&D with Acme Lock and Assa Abloy. Drawings from bid set are to be used for the proper door numbering to be used on the documentation. Existing malfunctioning card reader in basement stair will be repaired by Maintenance and not part of this project. All drawings and specification section sent to Tony Matre for future use.
03/10/17 – Inquiries were received by GBBN relative to recent meetings and keying schedules between JFS and Assa Abloy. Steve Sears reports to GBBN that Acme Lock still has not received all their Background Checks to begin working onsite. He mentioned JFS is still conduction internal discussions related to input needed by Acme for the keying hierarchy requirements. /Steve felt the process was still moving forward. GBBN reported this information to Assa Abloy.
09/14/17 – GBBN holds impromptu meeting with Assistant Building Manager. The Keying Project is scheduled to soon begin fabrication once final submittals are approved.
11/18/17 – Last we’ve heard they are working on the cores or shipping them. Keep on project list for coordination for A&D Furniture job.
02/22/18 – Project complete, need to decide what to do with old keys. 15 minute changeover to new keying system. Project ready to archive.

A&D – Rekeying Project Read More »

A&D – Wireless Network Project

03/29/16 – Bert Watts requested a SOSS for a wireless network study for all floors of the building (Sub-basement through 7th floor). ThermalTech issues SOSS. Project pending approved SOSS and PO.
04/27/16 – TEI receives approved SOSS and PO. TEI, Bert Watts, John Nester, Claude Toulsen and Mark Miller have kickoff meeting to discuss existing conditions and JFS desired WiFi parameters. JFS investigating with the state network possibility to add to state network hardware.
05/25/16 – TEI conducts walk through of the building with Claude Toulsen. Identified locations of existing WAP’s, Identified proposed locations for new WAP’s, discussed state requirements and standards, and Claude T to forward to TEI state requirements and recommendations.
06/27/16 – ThermalTech working with Claude Toulsen to identify the state requirements for the system components. The State standards and the county standards do not match. Although JFS is not mandated to utilize the state standard equipment, CT would like to know the implications of using that equipment (cost, etc). ThermalTech to provide costing data for both the state and the county standard systems and make recommendations accordingly.
07/27/16 – TEI meeting with Claude Toulsen on 7/27/16 for progress meeting. The state equipment supplier (Aruba) has been non-responsive for weeks when I have made attempts to contact them for technical support. TEI to discuss this with CT and we are recommending that JFS utilize the Fortinet (county standard equipment) versus the Aruba.
08/23/16 – TEI to submit to Claude Toulsen and Bert Watts final draft of report for final comments and distribution by 8/31/16.
09/28/16 – TEI received final comments from Bert Watts, pending comments from Claude Toulsen for final distribution.
10/25/16 – TEI received final comments from Claude Toulsen – will conclude study portion of project.
01/25/17 – TEI submits SOSS for implementation of report recommendations. Project Pending approval of SOSS and PO.
02/22/17 – TEI receives approved SOSS and PO for the project. Project kick off meeting scheduled with Facilities and JFS on 2/23/17 at 2:00 PM.
03/22/17 – TEI performs field work and finds existing spare breakers in panels on each floor to provide power to the network switches and the WAPs that are a part of the project. Working on Construction cost estimates to have ready for discussion at 04/06 design meeting.
04/26/17 – ThermalTech has meeting with JFS staff and Facilities. TEI completing Bid Docs for Final design review meeting by end of April. TEI to request meeting first week of May to provide final review and establish bid parameters.
05/22/17 – ThermalTech and facilities meets with JFS staff. TE and Facilities presents the HamCo telecom group policies to JFS staff. JFS staff to meet independently and return to TE and facilities with direction that they wish to pursue. TE waiting on final design criteria from JFS IT staff.
06/27/17 – ThermalTech to coordinate with Purchasing, JFS and facilities for dates to put in the ITB. ITB to be issued ASAP. Hold until funding is in place.
07/25/17 – Project on HOLD until funding is in place.
08/28/17 – Project on HOLD until funding is in place.
08/31/17 – Redo entire business model so telephone support will be more prevalent. Wi-Fi not required. BW will set something up in the future.
09/26/17 – project to be completed in conjunction with the furniture/painting project.
05/30/18 – project to be completed in conjunction with the furniture/painting project.
11/28/18 – project to be completed in conjunction with the furniture/painting project.
01/29/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
03/26/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
04/24/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
05/29/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
06/26/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
07/24/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
08/27/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
09/25/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
10/30/19 – project to be completed in conjunction with the furniture/painting project (bid as an alternate).
10/31/19 – Move project to Archive, its in the A&D Interior finishes projects.

A&D – Wireless Network Project Read More »

A&D – ADA Assessment

Partner Lead: GBBN
06/16/11 – Bert Watts indicated this Project Request should be broken into eight (8) separate SOSS’s based on each of the separate buildings.
06/17/11 – SOSS submitted in person to Bert Watts
09/16/11 – Signed SOSS received from Bert Watts.
08/24/13 – GBBN completes estimating on impacts of ADA Assessment Studies.
02/26/14 – Assessment report has now been fully reviewed and finalized. The cost estimate component is now in the preliminary stage of completion.
10/13/15 – Bert Watts requests that all Assessments be completed by the first of the upcoming year
12/03/15 – Assessments completed, printed and three sets delivered to Bert Watts.
12/15/15 – Facilities report to GBBN that Preliminary Cost Estimate portion of reports have incorrect references to County Administration Building.
01/08/16 – GBBN picks up reports from Facilities for making corrections.
04/18/16 – Facilities sends Estimating Project Requests showing the cost estimating portion of these Assessments as listed projects
06/28/16 – Opinions of Probable Costs for the implementation of the entered into Archibus as a Project Request Estimate.
03/23/17 – GBBN and Facilities agree to have Assessments completed at the same time as the Annual Project Request Estimating.
07/24/17 – GBBN printed all Archibus Project Request Estimates from 2016 (#801, 802, #627 and #804) and 2018 (#1862, #1851 and #1831) for inclusion into final reports.
10/25/17 – GBBN has final Project Request Estimates completed for insertion into final reports.
10/28/20 – Waiting on hard copies.

A&D – ADA Assessment Read More »