PM: Bert Watts, John Millar
11/06/18 – Hamilton County requested SOSS.
11/15/18 – THP provided SOSS.
11/19/18 – Hamilton County executed the SOSS.
03/28/19 – THP completed internal review of Master Agreement. THP will forward to County by 3/29/19.
— New Contract —
04/08/19 – Hamilton County requested SOSS.
04/10/19 – THP provided an SOSS for review.
04/22/19 – THP provide updated SOSS with new F series number.
04/24/19 – THP SOSS approved.
05/10/19 – A small piece of Terra Cotta fell from the Alms and Doepke Building. THP coordinated contractor support to remove the remaining loose pieces of terra cotta. THP to follow up with a summary report.
06/07/19 – THP issued a draft Terra Cotta report for review.
06/10/19 – THP issued final A&D Terra Cotta report.
10/07/19 – THP attended kick off meeting for review CAB entry project. Based on current project request, THP will not have a role in this project.
10/31/19 – THP estimate up loaded into Archibus.
11/20/19 – 250 WHT Trench Drain work order for cleanout and review planned. THP to review concrete conditions.
12/4/19 – 250 WHT Trench Drain – THP reviewed initial conditions and is reviewing with the City options.
12/10/19 – 250 WHT Trench Drain – Trench drain partially collapsed and is closed. THP and American Façade Restoration reviewed the conditions. AFR placed plates over the main drive lane.
12/11/19 – 250 WHT Trench Drain – THP issued a repair for pricing. AFR hopes to provide a price on 12/13/19.
02/13/20 – County requested THP review corroding steel at the Burlington Garage facility.
02/20/20 – County requested an SOSS for Courthouse bridge issues noted in City bridge inspection report.
02/26/20 – THP completed an initial visit to Courthouse bridge.
02/21/20 – THP and County reviewed field conditions at Burlington Garage. THP to generate an SOSS.
02/27/30 – For 250 WHT Trench Drain work refer to F117 for project status.
06/09/20 – THP met with Champlin at Juvenile Justice Center to review flooring field conditions. No visible structural deterioration or distress, but much of the structure is covered (flooring & fire proofing). THP to review approach with Champlin.
10/29/20 – THP has sent multiple email request to City to try to close out City Facade Inspections for 2020 Auburn and 230 East Ninth.
02/18/21 County requested THP review planned installation of two freezer units in 800 Broadway.
02/22/21 THP reviewed new refrigerator units at 800 Broadway basement. THP made recommendations via email for installation and location on the raised platform flooring structure.
04/05/21 – County reached out to review replacement RTU on the Florida roof of the 800 Broadway building. THP reviewed documents and visited the site the week of 4/13/21.
04/23/21 – THP published a review of the condition. Big picture new unit should work. Existing unit and new unit are schedule to be placed on unknown wood members. THP noted wood structure should be reviewed after the existing unit is removed, prior to the installation of the new unit.