Hamilton County Facilities

[General Services] – THP-A

General Services – THP
Archive

2026 Project Cost Estimates

PM: Rycca, Mike, Sam, Eryn, Terry, Mike, John

07/31/25 – We discussed the quantity of 2026 projects coming our way and we think about 20 project are new. The County will self-inflate the refresh cost estimates. Rycca will print and share the original list with us soon.
08/20/25 – ThermalTech received approved SOSS received from County.
08/28/25 – TTE Internal kickoff start, completion matrix created, Champlin assignments accepted and the TEI MBE partner engaged for work this year. Elevar SOSS submitted to HC 08/27.
09/24/25 – ThermalTech DEG working on estimates, most are done. Fieldwork in JC scheduled for this week. Gazelle will start uploading to Archibus this week.
09/25/25 – Elevar estimates ongoing and meetings with tenants scheduled.
10/30/25 – Elevar complete with estimates. ThermalTech complete with estimates.
12/11/25 – Complete. Davies partner creating binder PDF of each estimate before module is closed.

2026 Project Cost Estimates Read More »

General Structural Services (F019)

PM: Rycca Thacker, John Millar/Paul Bellman
04/24/25 – THP completed an initial analysis of the Hillcrest storage shed truss/decking for review by the County. Preliminary findings for published via email.
07/30/25 – THP was requested to review Justice Center parking configuration and walked the site with John and Tony.
08/14/25 – THP published two Justice Center parking options for review by the County.
08/28/25 – THP attending monthly meetings, updating website and coordinating structural questions.
09/25/25 – THP attending monthly meetings, updating website and coordinating structural questions.
10/24/25 – THP submitted updated General Service SOSS.
10/29/25 – THP attending monthly meetings, updating website and coordinating structural questions.

General Structural Services (F019) Read More »

2025 Project Cost Estimates

PM Watts, Murphy, Cannon, Millar, Barth, Thomas, Thamann
04/25/24 – Project module is open for 2025 projects.
06/27/24 – Murphy has assigned estimate leaders on each estimate, sent to all partners for approval.
06/27/24 – BW suggested that we meet with every requester and get their input on the submitted request. And we coordinate when the walk through will happen. Architectural they always needs to meet with county people. Budgets due on 7/12/24. This project is due end of August.
07/22/24 – Elevar – SOSSs submitted for CIP, New, and Resubmitted 2025 projects.
07/24/24 – ThermalTech – our approved SOSS was received last week, we’ve started the work, our electrical resubmittals are done, Champlin and Elevar are setting up field trips.
07/25/24 – Champlin submitted SOSS and has all the new projects fieldwork scheduled for last week of July and first week of August.
08/27/24 – Elevar: SOSSs approved and estimates ongoing.
08/28/24 – ThermalTech: Almost all field is compete. NEW and CIP estimates are progressing nicely, much of the data has already been entered. RESUBMITTED projects have been updated for Electrical Scope, Mechanical, Plumbing and Fire Scope are being update and reviewed this week. Mike Barth and Terry Cannon should begin QC reviews first of September. MBE currently entering all estimates that TTE has completed and turned over for entry. For New Estimates Completed 62% Elec, 31% Mech, 29% Plumbing, 28% Ready for Final Review.
09/24/24 – ThermalTech is complete with all entries. TTC and MCB are currently reviewing the data entered for the QC process except that TTC has to enter the 800 controls estimates manually. Elevar is complete with all entries.
10/29/24 – ThermalTech: all ThermalTech estimates are entered.
12/12/24 – ThermalTech has printed PDF binder files for its estimates.
12/31/24 – Ready to Archive.

2025 Project Cost Estimates Read More »

2024 Project Cost Estimates

PM: John Nester, All Partners
06/29/23 – SOSS requested and approved for all partners
07/27/23 – Estimates underway. Vendor prices coming in for TTE new projects and estimates are being updated as we get information and quotes in. Re-estimates are also being updated with 2024 pricing. Discuss floor plans need with Champlin for New A/E estimates.
08/28/23 – ThermalTech has 40 of 48 new estimated ready for internal review. We have 68 of 179 re-estimates ready for internal review.
09/25/23 – Project estimates are complete. Champlin, THP and ThermalTech completed last Friday. TTC sent a summary of items for the Re-estimates to the team on Monday.
12/15/213 – Archive project.

2024 Project Cost Estimates Read More »

THP 2023 General Services (F069)

11/09/22 – Hamilton County requested SOSS.
11/21/22 – THP provide SOSS for review.
12/12/22 – Hamilton County approved SOSS.
12/29/30 – THP coordinated Courthouse stone knock downs and surveyed southeast corner of the building.
12/30/22 – THP supported Champlin with 2020 Auburn flooring repairs.
01/06/23 – THP and AFR completed knock down work at Courthouse.
01/26/23 – THP updated project status work and attended monthly mtg.
02/23/23 – THP updated project status work and attended monthly mtg.
03/14/23 – THP attend WBE/MBE training meeting for Partners.
03/30/23 – During March, THP hired and coordinated special inspection work for 800 Broadway concrete pour.
04/26/23 – Railing redesign work for 800 Broadway work concrete platform and bulletin was completed.

THP 2023 General Services (F069) Read More »

2023 Project Cost Estimates

PM: Bert Watts, All Partners
05/25/22 – All estimates sent to Partners for SOSS
06/29/22 – ThermalTech has started updating estimates in the Archibus module. Several reestimates are complete. We are gathering information on the new projects but we need them set to estimating and we have to give them updates on scope and equipment for estimating before they start entering new ones in earnest. We have started requesting prices from vendors as well. We will send the County list for access. It would be helpful to have a coordination meeting on who is leading and who is working on the combined estimates.
05/31/22- THP Issues SOSS for review by the County.
06/10/22 – THP SOSS approved.
06/30/22 – THP developed internal spread sheet for projects. Initial draft complete. THP will publish for possible use by other partners.
07/27/22 – THERMALTECH UPDATE. Most electric cost estimates are complete and ready for Barth review. Limited mechanical estimates are complete at this time. Architectural and Structural coordinated has started for the “new” estimate. Once we get the proposed floor plans, we will update the MEP estimates.
08/24/22 – ThermalTech Update – We are working on these estimates every day to meeting Sept 1 deadline. Champlin has provided SD drawings for almost ever project for our use on the “New” estimates. We are coordinating on individual estimates on a case by case basis. Electrically, all resestimates are complete. Mechanically we have about 25 estimates remaining. We have completed several new estimates and will spend the bulk of our time next week completing the new estimates with the new drawings we’ve received.
09/04/22 – ThermalTech projects are complete for both reestimated and new estimates. TTC will review as time permits.
01/22/23 – Met with John and Ben and reviewed details that would make the Cost Estimating module better for the partners.
01/24/23 – Ready to Archive

2023 Project Cost Estimates Read More »

JFS – General Services

PM: Bert Watts, John Millar
06/10/21 – County requested a general structural service proposal.
06/11/21 – THP sent SOSS.
07/12/21 – County approved SOSS for TEI, THP, and CHA.
10/28/21 – TTC provided an update on low flow plumbing issues at the A&D building. In the past month, we had a major leak at the main sanitary leaving the building. Plumbers called an underground detective to survey the pipe from the building to the street. TTC to get a test kit for testing in Fifth Floor East.
04/28/22 – Loading dock upgrades and striping and loading sign.

JFS – General Services Read More »

Animal Shelter – Roof Replacement

05/21/21 – Hamilton County requested SOSS for the roof replacement of two roofs with alternates.
06/03/21 – THP provided SOSS for roof replacement project.
06/15/21 – County approved SOSS.
08/02/21 – THP visited site to survey and document existing conditions.
08/16/21 – THP issued Opinion of Probable Costs to Hamilton County for project budget approval.
08/20/21 – THP issued progress drawings and project manual for Owner Review.
08/25/21 – THP visited site to review condition of exposed decking in office and verify conditions at Entry canopy.
09/01/21 – THP received and reviewed AIA contract documents for project manual.
09/02/21 – THP met Hamilton County at site to review drawings and confirm scope of work items and Alternates.
09/03/21 – THP finalized and issued documents for bid.
09/09/21 – THP received and replied to substitution request email from roofing supplier and updated specifications.
09/14/21 – THP led pre-bid meeting at Animal Shelter.
09/15/21 – THP developed pre-bid meeting notes and issued Addendum 01.
10/05/21 – Bid opening. Received bids from Ace Exteriors, Wm. Kramer & Son, and Imbus Roofing.
10/06/21 – THP had conversations with Ace Exteriors to qualify bid, discuss pricing for canopy replacement, and request references and manufacturer’s certifications.
10/08/21 – THP finalized letter to Hamilton County summarizing bid process and recommending award to Ace Exteriors, including Base Bid and Alternate 1 scopes of work.
10/08/21 – THP responded to email from Hamilton County summarizing reasons bids received for canopy exceeded original estimates.
10/18/21 – THP received and began review of roofing products received from contractor as substitutions due to material availability.
10/20/21 – THP had conversation with Contractor and emailed Hamilton County about status of registering Ace Exteriors as a vendor.
10/21/21 – THP received from Contractor and forwarded to Hamilton County completed Substitutions form missing from bid proposal.
10/28/21 – THP issued revised title sheet with wind load information for Office/Admin. and Cat House roofs and requested Contractor review with manufacturer the potential implications on warranty and adhesive requirements.
11/05/21 – THP had conversation with Hamilton County to discuss material substitutions proposed by Ace Exterior due to material availability and schedule issues.
11/05/21 – THP had conversations with Wm. Kramer & Son about material availability and confirmed they would not be able to provide the specified roof insulation and cover board by spring 2022.
11/05/21 – THP emailed Hamilton County recommendations to proceed with the project using the substitute materials proposed by Ace Exteriors.
11/10/21 – Hamilton County emailed contract to Ace Exteriors.
11/23/21 – Ace Exteriors emailed Hamilton County the signed contract, worker compensation certificate, and a project-specific certificate of liability insurance.
12/23/21 – Hamilton County emailed the signed contract and PO to Ace Exteriors and requested development of required preconstruction documents.
01/28/22 – THP emailed Contractor about status of materials order, development of required pre-construction documents, completion date, and additional details to be developed.
02/01/22 – THP emailed Contractor draft of revised roof plan and details showing contract scope and new details at interface between project scope and canopies to remain.
02/04/22 – THP finalized and issued revised documents for Permit and Construction.
02/10/22 – THP reviewed and returned product submittals for roofing materials.
03/08/22 – THP received and reviewed Contractor’s pricing and lead time information for aluminum v. galvanized edge metals.
03/10/22 – THP had conversation with County about approval of proposed metal substitution due to increased costs and lead time issues, and re-reviewed submittals for roof specialties.
04/05/22 – Preconstruction meeting.
04/12/22 – THP issued minutes from preconstruction meeting.
04/12/22 – THP reviewed submittals and requested revised insulation layout.
04/13/22 – THP had conversation with Contractor about discrepancy in slope of tapered insulation between documents and submitted revised insulation layout, and retuned submittal with exceptions noted.
04/13/22 – THP had conversation with Contractor about installation issues and additional cost of taller fascia that would be required with 1/4″ slope tapered insulation v. 1/8″ slope indicated in documents. Contractor to request updated/revised tapered layout to reflect the 1/8″ slope.
04/19/22 – THP received, reviewed, and returned re-revised insulation layout submittal.
04/22/22 – THP had conversations with Contractor and Hamilton County to discuss delayed start date due to weather and insulation slope issue, and emailed team about rescheduling first progress meeting.
05/02/22 – THP met project team at site for progress meeting and site visit to document progress.
05/02/22 – THP emailed Contractor a link to a shared folder containing original construction drawings.
05/02/22 – THP developed and issued minutes from progress meeting #1.
05/03/22 – THP issued field report 01 from 5/2 site visit.
05/03/22 – THP reviewed pencil copy of Contractor’s first application for payment and replied with comments.
05/03/22 – THP reviewed and approved notarized copy of Contractor’s first application for payment and forwarded to Hamilton County.
05/12/22 – THP met Contractor on site to review and document progress.
05/15/22 – THP issued field report 02 from 5/12 site visit.
05/16/22 – THP met project team at site for progress meeting and site visit to document progress.
05/20/22 – THP developed and issued minutes from progress meeting #2.
05/20/22 – THP issued field report 03 from 5/16 site visit.
05/24/22 – THP visited site to review and documented completed installation of EPDM.
05/26/22 – THP issued field report 04 from 5/24 site visit.
06/01/22 – THP reviewed Ace fascia and coping profiles submittals.
06/29/22 – Progress meeting and site visit scheduled to review installed drains and progress of edge metal installation.
07/22/022 – THP visited site to do final inspection of completed work and identify punchlist items.
07/25/22 – THP published field report and punch list for roof work from 7/22/22 visit.
08/09/22 – THP emailed Contactor about status of completing punchlist items.
08/09/22 – THP developed Change Order #1 for unused Cash Allowance and Unit Price credit and forwarded to Contractor for signature.
09/21/22 – Contractor emailed team about status of completing punchlist.
09/26/22 – THP emailed Contractor about acceptance of remaining two punchlist items, status of second application for payment, closeout documents, and approval of Change Order #1.
10/28/22 – THP visited site to confirm completion of punchlist items, and emailed Contractor about the status of closeout documents, approval of Change Order #1, and the application for payment #2 for substantial completion.
11/09/22 – THP replied to email from Contractor rejecting request for additional use of Cash Allowance.
11/18/22 – Contractor provided preliminary closeout documents for THP’s review.
11/21/22 – Change Order #1, a credit for unused Unit Price Repairs and Cash Allowance, was signed by Contractor and Hamilton County.
12/01/22 – THP reviewed Contractor’s preliminary closeout documents and replied with revisions to be made and additional documents to be provided.
12/07/22 – Contractor provided revised closeout documents for THP’s review.
12/12/22 – THP reviewed revised closeout documents and emailed Contractor to proceed with providing hard copies, including notarized legal documents and the project binder.
01/03/23 – THP reviewed Contractor’s hard copies of closeout documents and project binder and requested revised as-built drawings using permit set as basis for markups.
01/04/23 – THP received revised as-built drawings, emailed Hamilton County a link to a shared folder containing digital copies of all closeout documents, approved Contractor’s second and final application for payment, and delivered project binder.
02/23/23 – OK to Archive.

Animal Shelter – Roof Replacement Read More »

2022 Project Request Cost Estimates

04/21/21 – Cannon created post from Bert Watts email for 2022 Project Request.
05/27/21 – Bert sent the preliminary list out to the partners for SOSS authoring. Kickoff meeting next Tuesday with TEI, THP, and Champlin.
06/11/21 – Started research on 230 MEP upgrades including new above grade boiler and chiller room.
06/22/21 – Met at Comm Center to discuss project scopes for repurposing and academy rework.
06/25/21 – User meetings held to discuss the scope for most Champlin lead estimates.
07/28/21 – Work continues on the individual estimates. Some will be complete by July 31 and all will be complete by August 31. Cost, data and scope still coming in the CH controls, Mechanical Yard items which are the “biggies” for TTC. Champlin is making progress. Smaller estimates will be done by 7/31, the rest by 8/31.
08/20/21 – Champlin has provided almost all of the floor plans we need to complete estimates. TEI is currently putting together the cost and scope documents for the remaining estimates.
08/24/21 – Teleconference held on the 230 East 9th estimates between all partners to finalize the scope and estimating. TTC followed an update later that day with additional information after speaking with BW about the #2105 estimate.
08/26/21 – TEI – work continues and we plan on making the 8/31 completion date as discussed. Estimate and drawings are being uploaded daily.
10/28/21 – Project complete. A couple of final projects have been added and updated to the list.

2022 Project Request Cost Estimates Read More »

THP General Structural Service (F021)

PM: Bert Watts, John Millar
11/17/20 – THP submitted SOSS.
11/17/20 – County approved SOSS.
02/18/21 County requested THP review planned installation of two freezer units in 800 Broadway.
02/22/21 THP reviewed new refrigerator units at 800 Broadway basement. THP made recommendations via email for installation and location on the raised platform flooring structure.
04/05/21 – County reached out to review replacement RTU on the Florida roof of the 800 Broadway building. THP reviewed documents and visited the site the week of 4/13/21.
04/23/21 – THP published a review of the condition. Big picture new unit should work. Existing unit and new unit are schedule to be placed on unknown wood members. THP noted wood structure should be reviewed after the existing unit is removed, prior to the installation of the new unit.
05/10/21 – THP published draft flag pole footing sketch to Champlin for review.
05/21/21 – THP published final flag pole footing sketch.
05/27/21 – THP review proposed RTU replacement at 800 Broadway. Planned replacement next week.

THP General Structural Service (F021) Read More »

2020 Roof Access Assessment (F018)

06/16/20 – Requested a SOSS for an Assessment of Facilities roof access (tie off and OSHA safety).
06/18/20 – County publish list of buildings to be included in the assessment.
06/25/20 – THP contacted LJB to provide anchor consulting support. THP plans to visit and catalog the roofs conditions next week for the SOSS.
07/14/20 – THP, LJB, and County surveyed downtown building roof to understand general conditions and needs of the County
07/28/20 – THP & LJB had a final scope meeting.
07/30/20 – LJB plans to provide a proposal to THP on 7/31. THP plans to submit final proposal early August.
08/11/20 – THP submitted SOSS to the County.
08/26/20 – Project placed on hold.
11/30/20 – THP received SOSS and PO for project.
01/13/21 – THP and LJB under contract for project.
01/15/21 – THP, LJB, and Hamilton County had kick off meeting.
01/28/21 – THP and LJB staff applied for background checks and waiting on approval.
02/25/21 – THP and LJB staff background checks approved. THP started field work on 02/24/21 – THP and LJB field work will continue until March 5th tentatively.
03/25/21 – THP and LJB completed initial site visits.
03/31/21 – LJB sent draft roof assessment report to County for review.
04/05/21 – County, THP and LJB met to review draft report.
04/29/21 – THP and LJB finalizing report based on comments from the meeting.
05/24/21 – LJB uploaded Draft report. THP reviewing cost and presentation.
07/16/21 – THP sent review drawing of report to LJB.
07/22/21 – THP and LJB reviewed comments. Overall minor updates to drawings.
08/26/21 – LJB working on final report.
09/16/21 – THP and LJB presented final documents to the County.

2020 Roof Access Assessment (F018) Read More »

THP – General Structural Services

PM: Bert Watts, John Millar
11/06/18 – Hamilton County requested SOSS.
11/15/18 – THP provided SOSS.
11/19/18 – Hamilton County executed the SOSS.
03/28/19 – THP completed internal review of Master Agreement. THP will forward to County by 3/29/19.
— New Contract —
04/08/19 – Hamilton County requested SOSS.
04/10/19 – THP provided an SOSS for review.
04/22/19 – THP provide updated SOSS with new F series number.
04/24/19 – THP SOSS approved.
05/10/19 – A small piece of Terra Cotta fell from the Alms and Doepke Building. THP coordinated contractor support to remove the remaining loose pieces of terra cotta. THP to follow up with a summary report.
06/07/19 – THP issued a draft Terra Cotta report for review.
06/10/19 – THP issued final A&D Terra Cotta report.
10/07/19 – THP attended kick off meeting for review CAB entry project. Based on current project request, THP will not have a role in this project.
10/31/19 – THP estimate up loaded into Archibus.
11/20/19 – 250 WHT Trench Drain work order for cleanout and review planned. THP to review concrete conditions.
12/4/19 – 250 WHT Trench Drain – THP reviewed initial conditions and is reviewing with the City options.
12/10/19 – 250 WHT Trench Drain – Trench drain partially collapsed and is closed. THP and American Façade Restoration reviewed the conditions. AFR placed plates over the main drive lane.
12/11/19 – 250 WHT Trench Drain – THP issued a repair for pricing. AFR hopes to provide a price on 12/13/19.
02/13/20 – County requested THP review corroding steel at the Burlington Garage facility.
02/20/20 – County requested an SOSS for Courthouse bridge issues noted in City bridge inspection report.
02/26/20 – THP completed an initial visit to Courthouse bridge.
02/21/20 – THP and County reviewed field conditions at Burlington Garage. THP to generate an SOSS.
02/27/30 – For 250 WHT Trench Drain work refer to F117 for project status.
06/09/20 – THP met with Champlin at Juvenile Justice Center to review flooring field conditions. No visible structural deterioration or distress, but much of the structure is covered (flooring & fire proofing). THP to review approach with Champlin.
10/29/20 – THP has sent multiple email request to City to try to close out City Facade Inspections for 2020 Auburn and 230 East Ninth.
02/18/21 County requested THP review planned installation of two freezer units in 800 Broadway.
02/22/21 THP reviewed new refrigerator units at 800 Broadway basement. THP made recommendations via email for installation and location on the raised platform flooring structure.
04/05/21 – County reached out to review replacement RTU on the Florida roof of the 800 Broadway building. THP reviewed documents and visited the site the week of 4/13/21.
04/23/21 – THP published a review of the condition. Big picture new unit should work. Existing unit and new unit are schedule to be placed on unknown wood members. THP noted wood structure should be reviewed after the existing unit is removed, prior to the installation of the new unit.

THP – General Structural Services Read More »

800 Broadway Polygonal Pavilion Roof Repair

October 26, 2011 Update THP develops test repair options and met with SSRG to review for pricing. THP to submit separation SOSS for contractor work.

Past Comments

Due to findings, weather sensitive repairs, and schedule; THP proposed completing a safety survey and trial repairs. County requested a letter report summarizing needed work to be possibly incorporated into a larger 2012 project. A SOSS for the letter reported was requested.

September 23, 2011 THP met with County to review conditions of roof.

Early September THP completed field review and design analysis.

August 3, 2011 SOSS approved.

July 18, 2011 THP Submitted SOSS for review.

800 Broadway Polygonal Pavilion Roof Repair Read More »

2011 General Structural Services

Hourly budget funds exhausted for F24A. THP directed to submit for additional $5,000 as F24B.

Past Comments

July 26, 2011 County approved SOSS F24A.

July 18, 2011 THP submitted SOSS F24A for additional funds.

Hourly budget funds exhausted; Bert Watts requested a SOSS for the second half of the year.

Bert Watts requested THP provide a SOSS for the study and repair of the 800 Broadway limestone panels.

THP reviewed reported cracking of Hillcrest Oak Cottage and provided a summary letter on May 5, 2011. Bert Watts requested an SOSS to complete a study of the cracking issues.

THP completed initial review of 800 Broadway limestone condition and provided summary email for review.

THP reviewing 800 Broadway LEED EB proposal structure.

May 5, 2011 SOSS approved.

April 28, THP provided SOSS.

April 24, 2011 SOSS requested SOSS.

2011 General Structural Services Read More »

Parkhaus Garage Repairs THP Prime

October 26, 2011 Update – Contractor noted they are waiting on Joint and several warranty from the manufacturer, which is anticipated later this week.

Past Comments

All pay requests minus retainage approved; waiting on warranty and closeout paperwork.

August 31, 2011 Substantial letter completion letter issued; along with final deduct change order due to liquidated damages.

All work complete as of early August.

July 22, 2011 RAM issued via email that the new hand rail embed should be fabricated and on site at the end of the week of July 25.

July 12, 2011 THP issued new hand rail embed replacement details to RAM. RAM submitted details for embeds to be fabricated.

July 7, 2011 THP approved and forwarded to Hamilton County, RAM request for payment, Pay Application No 4, in the amount of $20,617.20.

July 6, 2011 THP noted, RAM damaged some existing handrail embeds when removing existing handrail. THP to review conditions and issued repair details.

July 5, 2011 RAM re-mobilized on site to begin replacement of the handrails at the NW stair and liquidated damages begin.

June 9, 2011 THP approved and forwarded to Hamilton County, RAM request for payment, Pay Application No 3, in the amount of $29,794.20.

May 26, 2011 THP approved, with exceptions noted, the steel hand rail shop drawings for NW stair tower.

May 23, 2011 RAM demobilized from the project site so Hamilton County has full use of the garage facility. RAM will re-mobilize on site once the steel handrail shop drawings and fabrication are complete. Per liquidated damages letter RAM is scheduled to return for installation of the steel hand rail on July 5, 2011.

May 25, 2011 steel hand rail shop drawings for NW stair tower received.

May 23, 2011 substantial completion date but RAM has not satisfied the substantial completion date requirements. No steel hand rail shop drawings submitted for NW stair tower. Liquidated damages letter pertaining to steel hand rail to be issued by THP per Bert Watts (Hamilton County) direction and approval. Steel hand rail shop drawings and fabrication were never weather dependent work items.

May 23, 2011 THP issued Field Report No 05 for Phase 2 (final) membrane strip installation.

Weekend of May 20, 2011, RAM completed vault slab placement over anodes, and remaining Phase 2 membrane strip installations. Inclement weather postponed this phase of membrane installation till this date.

May 17, 2011 Anode testing report by Bushman and Associated issued.

May 13, 2011 THP issued Field Report No 04 for completion of Phase 1 membrane strip installation. THP also approved and forwarded to Hamilton County, RAM request for payment, Pay Application No 2 in the amount of $54,344.40.

May 10, 2011 Membrane manufacturer (Neogard) letter pertaining to exposed membrane aggregate being compromised was issued.

May 6, 2011 THP issued Field Report No 03 for Phase 1 membrane installation. Inclement weather prevented completion of all of Phase 1 membrane strip installation areas.

May 6, 2011 Final T&M tickets submitted by RAM for anode relocation.

April 29, 2011 Change Order No 01 work items approved by all parties for a deduct to the projects Cash Allowance in the amount of $8,735.00. Total project budget remains unchanged.

April 26, 2011 THP issued Change Order No 01 to reflect Bulletin No 01 pricing so RAM may begin the additional work. This Change Order added two weeks to the substantial completion date. New substantial completion date is May 23, 2011.

April 25, 2011 Hamilton County accepted Bulletin No 01 pricing which was within the projects original Cash Allowance.

April 25, 2011 RAM submitted Bulletin No 01 pricing.

April 21, 2011 RAM began membrane work on Levels 2 through 5.

Week of April 18, 2011 Anode placement began in the vaults.

April 15, 2011 THP issued Bulletin No 01 to RAM for pricing for additional concrete and waterproofing repairs.

April 13, 2011 Progress Meeting.

April 8, 2011, THP issued Field Report No 02.

April 7, 2011 RAM completed construction joint sealant replacement on Levels 2 through 5.

As of March 24, 2011 RAM has not submitted steel shop drawings for hand rail.

March 18, 2011 THP approved RAM’s Pay Application No 1, in the amount of $40,194.80, and forwarded to Hamilton County.

March 3, 2011, THP issued Field Report No 01.

Anode installation scheduled to begin week of April 4.

Weather conditions for this weekend appear favorable, so RAM may perform sealant replacement April 1 weekend.

January 6, 2011 preconstruction meeting completed. Work to scheduled to begin February 7 to allow for weather.

THP has all submittals except cathodic protections.

Contract approved.

County commissioners reviewing contract.

Contract signed by Ram reported to be returned to County.

September 27, 2010 THP sent updated contract for County review.

September 9, 2010 THP sent draft contract for County review.

Bids received and Ram Construction apparent low bidder.

Bids due August 18, 2010.

Pre-bid meeting scheduled for August 4, 2010 at 10:00 a.m.

Project out to bid on July 23, 2010.

Project Documents sent to County for review on July 19, 2010.

THP and Jim Bushman accessed vaults to confirm conditions for implementing corrosion protection system on June 23, 2010.

THP is coordinating work with corrosion consultant.

Parkhaus SOSS approved May 14, 2010.

SOSS submitted 3/3/10.

THP anticipates SOSS delivery by 3/5/2010. (2/24/10

Kickoff meeting complete.

THP needs to schedule a kickoff meeting.

THP working with subcontractor to develop proposal.

Parkhaus Garage Repairs THP Prime Read More »

1021 Patrol Headquarters Waterproofing Repairs THP Prime

October 19, 2011 THP, SSRG and County met to review the leak to determine if work is warranty or a new item. Due to lack of water/leak; the team decided to wait until rain/leak event and review the condition at that time.

New leak reported in same switch gear room in late September during a heavy rain.

Past Comments

September 15, 2011 County finalizing process of SSRG final pay application.

September 14, 2011 SSRG sent prevailing wage information to County.

September 11, 2011 THP forwarded final pay application and close-out manual to the County.

SSRG completed punch list items early August and THP verified items were complete.

July 13, 2011 THP published punch list to SSRG. Steven noted the work will be completed and THP is holding onto the final pay application (retainage) until the work is complete.

THP is waiting on warranties to process final pay application.

THP plans to punch on June 30, 2011.

Change Order No. 1 work (Window repairs) complete as of Friday, 5/20.

Change Order No. 2 sign by HGC, awaiting County approval.

THP forwarded Change Order No. 2 for the urethane injection of the electrical and sprinkler rooms to HGC for signature on 5/16.

During heavy rains of late April, leaking at the switch gear room and sprinkler room (new leak) occurred. THP recommended injection of crack from interior of both room. April 25, 2011 THP and HGC met to discuss the condition and request pricing.

During restoration repair, additional window sill and steel structure repairs associated concrete sill were identified. THP requested cost from HGC to complete the repairs. Change Order #1 approved by the County.

Subsurface waterproof and exterior injection work complete by HGC.

January 27, 2011 Work on hold until weather is within allowable specifications (early spring). The County requested all submittals and background checks be completed this February.

March 30, 2011 THP sent HGC the change Order form for the repair work associated with the window deterioration.

March 28, 2011 THP received approval from the County to proceed with a change order for HGC to repair the deteriorated window.

March 25, THP received final pricing from HGC regarding the work to repair the deteriorated window.

March 25, 2011 HGC finished the drain tile and landscaping work which completed all base bid work.

March 23, 2011 THP requested pricing from HGC for associated window deterioration.

March 23, 2011, HGC completed injection repairs and installation of the drain tile / back fill.

January 27, 2011 Work on hold until weather is within allowable specifications (early spring). The County requested all submittals and background checks be completed this February.

THP is waiting on submittals and contractor background check.

County conducted preconstruction meeting on 12/29.

Project needs to schedule a preconstruction meeting.

The requested project schedule and submittals from Structural System.

Contract approved.

October 29, 2010 the County provided updates to the proposed Contract. THP updated and returned the contract.

October 8, 2010 THP sent draft contract to County for review.

September 30, 2010. Bids were within budget and THP recommended Structural Systems (HGC).

Bids are due September 30, 2010.

September 21, 2010 Addendum #1 was issued, which was the meeting minutes from the prebid meeting.

September 17, 2010 bid documents were sent to HGC, ZSR, Lithko Restoration, and Langenheim & Thomson Company.

September 16, 2010 THP provided bid documents to the County.

September 9, 2010 County provide comments to review documents.

September 3, 2010 THP provided review documents to the County for review. Project estimate is below County threshold for publically bid project, so project bid is by invitation.

County requested construction budget and THP reviewing.

THP provided owner review documents on August 23, 2010.

County approved drainage system.

County reviewing THP proposed approaches of a new slab or drainage system (THP on hold).

THP and County had kick of meeting on June 21, 2010 to complete repairs recommended in report

THP issued letter report on June 18, 2010.

THP arranging with contract excavation of wall area.

Excavation needed for investigation is planned for mid-March, due to adjacent utility lines and required handwork.(2/24/10)

SOSS approved 2/3/2010.

THP submitted SOSS 2/1/2010.

THP needs to submit SOSS and complete survey.

Kick off meeting completed with Bert Watts and John Millar.

1021 Patrol Headquarters Waterproofing Repairs THP Prime Read More »

Memorial Hall 2010 Facade Assessment

Can project be closed out?

March 8, 2011 report entered into Archibus.

March 4, 2011 report sent to County.

THP working on report.

January 3, 2011 THP & Lithko completed a water test of the south wall parapet.

January 2, 2011 Lithko restoration a safety survey to remove all loose stone material. THP completed façade lift inspection during safety survey.

THP working on project.

January 3, 2011 THP & Lithko completed a water test of the south wall parapet.

January 2, 2011 Lithko restoration a safety survey to remove all loose stone material. THP completed facade lift inspection during safety survey.

December 10, 2010 THP completed initial visual survey. Survey revealed loose sandstone and THP recommended completing a knock down survey by a contractor. Due to weather conditions repairs should occur in the spring. THP getting pricing from the contractor.

November 15, 2010 SOSS approved.

October 26, 2010 THP submitted SOSS for review.

October 26, 2010 THP and County completed kick off meeting.

October 19, 2010 County requested SOSS from THP.

August County and THP discussed preliminary Memorial Hall assessment numbers.

Memorial Hall 2010 Facade Assessment Read More »

Galbraith Service Garage Lintel Investigation

Lead Partner: THP

03/16/16 – County requested THP investigate a deteriorating lintel at the service garage.

03/18/16 – THP visited the site to review field conditions.

03/31/16 – THP provided an SOSS for review.

07/08/16 – County approved SOSS.

07/28/16 – THP to schedule field work and complete field work in August.

08/22/16 – Field Assessment trip completed.

09/28/16 – THP anticipates final report being released 10/15/16.

Galbraith Service Garage Lintel Investigation Read More »

THP – Facility Building – Envelope Planning Development

01/26/17 – Hamilton County requested SOSS.
03/23/17 – THP developing SOSS.
02/22/18 – Facilities requested overall portfolio assessment report for all the work they have been collected. Historical review of when surveys were completed.
04/04/18 – THP sent SOSS for review.
06/21/18 – SOSS approved.
10/01/19 – THP sent draft format for review.
10/17/19 – HC approved format.
08/27/20 – THP sent report this morning.

THP – Facility Building – Envelope Planning Development Read More »

General Services – THP

09/17/13 – County requested SOSS for 2014 structural services.
09/26/13 – THP issued SOSS.
09/26/13 – Hamilton issued executed SOSS.
01/30/14 – THP waiting for active water infiltration in the Coroner Building to evaluate scope of work. Work will probably occur in the spring.
02/27/14 – Coroner Building work on hold.
06/13/15 – THP met with County to provide review of existing plaza sealant joints and recommendations for future repairs.
08/26/15 – County requested THP review Sprint / Clearwater Tower to be installed on the CAB building.
09/24/15 – THP completed initial review of Sprint Tower, then project placed on hold. County requested typical load capacity of the roof. THP to review with the County.
12/03/15 – County requested SOSS for 2015 structural services.
12/09/15 – THP issued SOSS.
12/10/15 – County approved SOSS.
11/17/16 – Hamilton County requested SOSS for 2017.
01/09/17 – THP provided SOSS.
04/27/17 – THP analysis the computer flooring in 800 Broadway for testing equipment. Based on unit information and response from flooring manufacturer; the unit can be located in the room. THP noted the pallet jack may have trouble with the ramp and could damage the floor.

General Services – THP Read More »

Scroll to Top