PM: Megan, Terry Cannon
05/14/25 – Field trip to site with Rycca.
07/28/25 – Owner review set sent to County.
08/20/25 – Option 1 & 2 sent to owner for review with cost estimates.
08/28/25 – We received prices for SS pans and will update the cost estimate and send back with updates today.
09/24/25 – Project is also on 2026 Project Cost Estimates, we will use same numbers for the estimate.
10/29/25 – Project is updated in Archibus 26-ADM-0138-2485.
12/12/25 – TTC needs to revisit site with Rycca for new scope.
01/25/26 – Ryan and Sam to meeting with Rycca for kickoff meeting – waiting to here back about when this will be. We do need to draft an SOSS for this work and bid it out Small Project.
02/25/26 – Waiting to send SOSS, latest news was that this may be included in a bigger floor renovation?
03/25/26 – Questions out about final scope and expanded floor plan. Revised SOSS not submitted yet.
04/29/26 – Scope questions answered, DEG owes Champlin revised SOSS for final floor plan.
05/27/26 – Project On hold.
06/25/26 – Project on hold.