PM: Megan, Sam Hofmann, Terry Cannon
05/29/25 – Added as new project.
06/25/25 – Checking dates for meeting.
07/24/25 – Design meeting conducted on site.
08/26/25 – Design continues, updated floor plans received from Champlin today.
09/24/25 – Prices and owner review documents submitted to Champlin. County to review budget and scope to determine if they have enough money to bid as is.
10/30/25 – Scope and Budget confirmed. Project will be issued for bid today.
12/11/25 – Triton is low bidder. Project is in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – No Update.
04/30/26 – Submittals are in process. County to schedule mobilization.
05/28/26 – Triton mobilized on 5/6. Construction and Bi-weekly meetings ongoing.
06/25/26 – Demo complete. Framing complete. Roughin inspections ongoing.
07/30/26 – Construction ongoing.
08/28/26 – Project nearing completion. Punch scheduled for next week.
09/24/26 – Punch walkthrough completed. Closeouts in progress.
10/29/26 – Backpunch complete. Closeouts received and being reviewed