TPC – Arc Flash Remediation Upgrades

PM: John Nester, Mike Barth
05/26/22 –  TEI submits SOSS for work.   TEI receives signed SOSS and PO for project.
06/28/22 – TEI, John Nester, Jesse Estes and John Gilbert conduct project kick-off meeting.  TEI to provide review sets and recommendations to CMI and Hamilton County by the end of July for review and comments.
07/27/22 – TEI has reviewed existing model and contacted Duke Energy for updated available fault information.  TEI to schedule meeting in next week or so with John Nester to review options and recommendations.
08/24/22 – TEI receives updated information from Duke for available Fault.  Current version of SKM software allows additional information regarding gear (Circuit breakers, etc) that the 2010 version did not allow, and actual data utilized in lieu of infinite bus (worst case) data.  With new version of software, incident energy levels are less than threshold of 40 cal.  TEI discusses with John Nester, a complete re-label of the building.
09/26/22 – TEI develops ITB package for the proposed upgrades to the electrical systems in the buildings per conversations with HCFD.  TEI submits review set to HCFD.  Upon receipt of comments, ITB number and bidding dates will be established.
10/26/22 – ITB has been issued, Prebid meeting conducted, (2) addenda issued.   Bids open Friday 10/28/22.
12/15/22 – DK low bidder.  TEI vets DK bid and sends recommendation to Hamilton County.  Hamilton County drafts contract and sends to DK for signature.   DK returns signed Contract.
01/25/23 – DK receives PO and signed contract.   TEI and HCFD working to schedule pre-construction meeting with DK to kick off the construction.
02/23/23 – Pre construction meeting completed.  DK has sent submittals to TEI for review.  Submittals to be returned by end of week and equipment can be ordered.
03/29/23 – Materials have been ordered.   Project to commence upon receipt of materials.
04/27/23 – Construction to commence upon receipt of materials.
05/23/23 – Construction to commence upon receipt of materials.  Material for TPC are at DK office, TEI to set up a meeting end of next week to talk install schedule, etc (pre-const).
06/28/23 – Pre construction meeting occurred.  DK scheduling mobilization with other county projects and will coordinate with HCFD, Bldg Mgr, and TEI.
08/24/23 – DK to be on site next week to work on the gear modifications to expose the adjustable trip settings on the gear.  door modifications are 1-day turn around.  gate shall be locked out/tagged out with no admittance to the electrical swgr room while the covers are removed from the gear.
09/26/23 – Gear modifications are complete.   grounding modifications are complete.   VFD  replacement and then re-labeling of building and project will be complete.
10/26/23 – TEI reaches out to DK to Schedule the installation of the VFD, now that the pneumatic controls were removed from the existing VFD.  Installation schedule to be received early November.
12/06/23 – VFD installed, connect and programmed.   Work associated in TPC is complete and ready to be punchlisted.  Work at CH is not complete, so project can not be closed.
05/29/24 – No Updates.
06/26/24 – No Updates.
07/24/24 – No updates.
08/28/24 – New Arc Flash labels applied in the building.
09/25/24 – no updates.
10/30/24 – no updates.
12/11/24 – TEI delivers final AF reports to HCFD including tables and single lines from the model.
04/23/25 – Updates tied to CH Arc Flash project.
05/28/25 – No updates
07/30/25 – No updates, waiting on CH breaker to close out.
04/26/26 – Ch breaker received and delivered to HC. Ready to closeout. OK to Archive.