PM: John Nester, Mike Barth
05/26/22 – TEI submits SOSS for work. TEI receives signed SOSS and PO for project.
06/28/22 – TEI, John Nester, Jesse Estes and John Gilbert conduct project kick-off meeting. TEI to provide review sets and recommendations to CMI and Hamilton County by the end of July for review and comments.
07/27/22 – TEI has reviewed existing model and contacted Duke Energy for updated available fault information. TEI to schedule meeting in next week or so with John Nester to review options and recommendations.
08/24/22 – TEI receives updated information from Duke for available Fault. Current version of SKM software allows additional information regarding gear (Circuit breakers, etc) that the 2010 version did not allow, and actual data utilized in lieu of infinite bus (worst case) data. With new version of software, incident energy levels are less than threshold of 40 cal. TEI discusses with John Nester, a complete re-label of the building.
09/26/22 – TEI develops ITB package for the proposed upgrades to the electrical systems in the buildings per conversations with HCFD. TEI submits review set to HCFD. Upon receipt of comments, ITB number and bidding dates will be established.
10/26/22 – ITB has been issued, Prebid meeting conducted, (2) addenda issued. Bids open Friday 10/28/22.
12/15/22 – DK low bidder. TEI vets DK bid and sends recommendation to Hamilton County. Hamilton County drafts contract and sends to DK for signature. DK returns signed Contract.
01/25/23 – DK receives PO and signed contract from HCFD. HCFD and TEI working to schedule preconstruction meeting to kickoff the construction.
02/23/23 – Preconstruction meeting completed. DK sends submittals to TEI for review. Submittals will be returned by the end of the week and equipment can be ordered.
03/29/23 – Materials have been ordered. Construction will commence upon receipt of materials.
04/27/23 – Construction to commence upon receipt of materials.
05/23/23 – Construction to commence upon receipt of materials. DK has the VFDs in their shop. Scheduled ship date for the replacement MCC bucket is mid to late June. Scheduled ship date for the replacement MCC is mid to late October 2023. DK may install VFDs on wall sooner than MCC. Will schedule pre-const meeting next week to discuss options.
06/28/23 – Pre construction meeting was conducted. Once Bldg Mgr notifies that the compressed air lines that are in the location that the VFDs are scheduled to be installed have been relocated, DK will install the VFDs on the wall. Anticipate that all Chiller shutdowns will occur once the MCC arrives (November ish) when the CH is not in cooling mode.
08/24/23 – work pending equipment procurement.
09/26/23 – work pending equipment procurement.
10/26/23 – TEI requests status update from DK on the reciept of MCC. Upon receipt of MCC – the installation will be scheduled ASAP while not in cooling mode since the MCC serves chillers.
12/06/23 – DK indicates that ship date for MCC pushed by manufacturer from 11/1/23 to 03/14/24. TEI questions when it was ordered, and DK indicates the PO was issued on 03/17/23. DK questioned why the ship date delay? No response. TEI requests a meeting with DK, to develop an alternate plan for installation since it will now likely occur in cooling season.
01/30/24 – Waiting for equipment to arrive on site to schedule the installation (scheduled ship date = Mid March 2024).
02/28/24 – TEI has DK confirm ship date (=03/14/24) for equipment. HCFD and TEI schedule pre-const meeting with DK on 03/08/24.
03/27/24 – DK confirms receipt of MCC. VFDs are powered and the other MCC bucket already replaced. DK to schedule an outage to install the new MCC over a weekend and to coordinate with weather and CH schedules.
04/24/24 – MCC scheduled for installation on 05/04/24. Bucket to be swapped out during the same outage.
05/29/24 – MCC install did not occur. New date being coordinated (tentatively 06/22/24).
06/26/24 – Install of MCC occurred on 6/22. No issues reported back.
07/24/24 – TEI prints off the arc flash stickers for the CH. Planning to install starting Aug 1 – pending availability of HCFD to escort/open doors.
08/28/24 – Upon review – labels were not correct that were printed. TEI reprints labels and will install pending coordination with building manager.
09/25/24 – TEI scheduling applying labels with bldg mgr and will apply all labels in the building.
10/30/24 – TEI applies labels throughout the building
12/11/24 – TEI delivers final AF report to HCFD with the AF tables and the model single lines in the reports.
02/26/25 – HCFD reports issues with MCC replaced. DK indicates additional bucket requested by HCFD ship date of 08/2025.
04/23/25 – Project pending additional equipment shipping 08/2025.
05/28/25 – No updates
06/25/25 – No updates
07/30/25 – No Updates. Breaker scheduled to ship next month.
08/27/25 – Breaker has arrived. DK working with HCFD to schedule the installation.
09/24/25 – Breaker is installed. Waiting on final phenolic labels to come in and be installed and then project will be complete after DEG and HCFD do a final final punchlist.
12/10/25 – DEG conducts final walkthrough. All work complete. Project complete pending closeout.
01/28/26 – Project in Closeout
04/29/26 – Breaker received and delivered to trades. Project can be closed out.